Purpose
The purpose of this document is to define the conversion approach to create conversion for Object 9107 – Activity Rates in S/4 HANA.
Activity Rates are the current active rates for different activities performed either for production, plant maintenance, HR etc. The activity rates capture the planned cost for a certain activity over a period of time. E.g. Factory overhead is charged to production orders via relevant activity types maintained for absorbing factory overheads. The activity rates are maintained for a combination of activity types and cost centre combination.
The document details out the field list, extraction criteria, scoping, mapping, transformation logic, generation of the pre-load file and loading of the same with respect to the object 9107- Activity Rate.
The requirement is to migrate planned activity rates. The actual activity rates would be performed within the S4 system as a part of the month end activity.
The activity rates will be provided by the business in a Data Collection Template (hereinafter referred to as DCT) and transformed as applicable for S4HANA in Syniti and then loaded using the excel upload option.
Conversion Scope
The scope of this document covers the approach for migration of planned activity prices.
The data from legacy system needs to be confirmed by the business.
List of source systems and approximate number of records <number of company codes to be confirmed relevant for activity rates needs to be confirmed>. The data will be provided by the business in the DCT page. The data will not be extracted and transformed in Syniti. The source of data is DCT and not PF2 and WP2.
Additional Information
Multi-language Requirement
None
Document Management
Not Applicable
Legal Requirement
Not Applicable
Special Requirements
Not Applicable
Target Design
The Target design of the object 9107 – Activity rates is as below
Table | Field | Data Element | Field Description | Data Type | Length | Requirement | ||||
COEJT | KOKRS | KOKRS | Controlling area | CHAR | 4 | Mandatory | ||||
COEJT | BELNR | CO_BELNR | Document Number | CHAR | 10 | System Generated | ||||
COEJT | BUZEI | CO_BUZEI | Posting Row | NUMC | 3 | System Generated | ||||
COEJT | PERBL | PERBL | Period Block | NUMC | 3 | Mandatory | ||||
| COEJT | ||||||||||
TKG001 | ||||||||||
TKGXXX | ||||||||||
Total Price per | ||||||||||
Unit of Measure in CO Area Currency | CURR | Length:23 and 2 Decimals | ||||||||
System Generated | ||||||||||
COEJT | ||||||||||
TKG002 | ||||||||||
TKGXXX | ||||||||||
Total Price per | ||||||||||
Unit of Measure in CO Area Currency | CURR | Length:23 and 2 Decimals | ||||||||
System Generated | ||||||||||
| COEJT | ||||||||||
TKG003 | ||||||||||
TKGXXX | ||||||||||
Total Price per | ||||||||||
Unit of Measure in CO Area Currency | CURR | Length:23 and 2 Decimals | ||||||||
System Generated | ||||||||||
COEJT | ||||||||||
TKG004 | ||||||||||
TKGXXX | ||||||||||
Total Price per | ||||||||||
Unit of Measure in CO Area Currency | CURR | Length:23 and 2 Decimals | ||||||||
System Generated | ||||||||||
COEJT | ||||||||||
TKG005 | ||||||||||
TKGXXX | ||||||||||
Total Price per | ||||||||||
Unit of Measure in CO Area Currency | CURR | Length:23 and 2 Decimals | ||||||||
System Generated | ||||||||||
COEJT | ||||||||||
TKG006 | ||||||||||
TKGXXX | ||||||||||
Total Price per | ||||||||||
Unit of Measure in CO Area Currency | CURR | Length:23 and 2 Decimals | ||||||||
System Generated | ||||||||||
COEJT | ||||||||||
TKG007 | ||||||||||
TKGXXX | ||||||||||
Total Price per | ||||||||||
Unit of Measure in CO Area Currency | CURR | Length:23 and 2 Decimals | ||||||||
System Generated | ||||||||||
COEJT | ||||||||||
TKG008 | ||||||||||
TKGXXX | ||||||||||
Total Price per | ||||||||||
Unit of Measure in CO Area Currency | CURR | Length:23 and 2 Decimals | ||||||||
System Generated | ||||||||||
COEJT | ||||||||||
TKG009 | ||||||||||
TKGXXX | ||||||||||
Total Price per | ||||||||||
Unit of Measure in CO Area Currency | CURR | Length:23 and 2 Decimals | ||||||||
System Generated | ||||||||||
COEJT | ||||||||||
TKG010 | ||||||||||
TKGXXX | ||||||||||
Total Price per | ||||||||||
Unit of Measure in CO Area Currency | CURR | Length:23 and 2 Decimals | ||||||||
System Generated | ||||||||||
COEJT | ||||||||||
TKG011 | ||||||||||
TKGXXX | ||||||||||
Total Price per | ||||||||||
Unit of Measure in CO Area Currency | CURR | Length:23 and 2 Decimals | ||||||||
System Generated | ||||||||||
COEJT | ||||||||||
TKG012 | ||||||||||
TKGXXX | ||||||||||
Total Price per | ||||||||||
Unit of Measure in CO Area Currency | CURR | Length:23 and 2 Decimals | ||||||||
System Generated | ||||||||||
| COEJT | TKE001TKF001 | TKEXXXTKFXXX | Fixed Price Unit per Activity Price in CO Area Currency | NUMC | CURR | Length:23 and 2 Decimals5 | MandatoryCOEJT | |||
COEJT | TKE002TKF002 | TKEXXXTKFXXX | Fixed Price per Activity Price Unit in CO Area Currency | NUMC | CURR | Length:23 and 2 Decimals5 | Mandatory | |||
| COEJT | TKE003TKF003 | TKEXXXTKFXXX | Fixed Price per Activity Price Unit in CO Area Currency | NUMC | CURR | Length:23 and 2 Decimals5 | Mandatory | |||
COEJT | TKE004TKF004 | TKEXXXTKFXXX | Fixed Price per Activity Price Unit in CO Area Currency | NUMC | CURR | Length:23 and 2 Decimals5 | Mandatory | |||
COEJT | TKE005TKF005 | TKEXXXTKFXXX | Fixed Price per Activity Price Unit in CO Area Currency | NUMC | CURR | Length:23 and 2 Decimals5 | Mandatory | |||
COEJT | TKE006TKF006 | TKEXXXTKFXXX | Fixed Price Unit per Activity Price in CO Area Currency | NUMC | CURR | Length:23 and 2 Decimals5 | Mandatory | |||
COEJT | TKE007TKF007 | TKEXXXTKFXXX | Fixed Price per Activity Price Unit in CO Area Currency | NUMC | CURR | Length:23 and 2 Decimals5 | Mandatory | |||
COEJT | TKE008TKF008 | TKEXXXTKFXXX | Fixed Price Unit per Activity Price in CO Area Currency | NUMC | CURR | Length:23 and 2 Decimals5 | Mandatory | |||
COEJT | TKE009TKF009 | TKEXXXTKFXXX | Fixed Price per Activity Price Unit in CO Area Currency | NUMC | CURR | Length:23 and 2 Decimals5 | Mandatory | |||
COEJT | TKF010 | TKFXXX | Fixed Price per Activity Price in CO Area Currency | CURR | Length:23 and 2 Decimals | Mandatory | ||||
COEJT | TKF011 | TKFXXX | Fixed Price per Activity Price | TKE010 | TKEXXX | Price Unit in CO Area Currency | NUMC | CURR | Length:23 and 2 Decimals5 | Mandatory |
COEJT | TKE011TKF012 | TKEXXXTKFXXX | Fixed Price per Activity Price Unit in CO Area Currency | NUMC | CURR | Length:23 and 2 Decimals5 | Mandatory | |||
COEJT | TKE012TKE001 | TKEXXX | Price Unit in CO Area Currency | NUMC | 5 | Mandatory | ||||
COEJT | LEDNRTKE002 | LEDNR | Ledger for Controlling Objects | CHAR | 2 | TKEXXX | Price Unit in CO Area Currency | NUMC | 5 | MandatoryOptional |
COEJT | OBJNRTKE003 | J_OBJNR | Object Number | CHAR | 22 | TKEXXX | Price Unit in CO Area Currency | NUMC | 5 | MandatorySystem Generated |
COEJT | GJAHRTKE004 | GJAHR | TKEXXX | Price Unit in CO Area CurrencyFiscal Year | NUMC | 45 | Mandatory | |||
COEJT | VERSNTKE005 | VERSN | Version | CHAR | TKEXXX | Price Unit in CO Area Currency | NUMC | 53 | Mandatory | |
COEJT | VRGNG | CO_VORGANG | CO Business Transaction | CHAR | 4 | System Generated | ||||
COEJT | REFBZ | CO_REFBZ | Posting Row of Reference Document | NUMC | 3 | System Generated |
Data Cleansing
For the purpose of the Object 9107- Activity rates, the data cleansing is not applicable. It is expected that relevant records will be provided in DCT by business.
Conversion Process
For activity rates the data will be collected in the DCT page. The conversion process will depend upon the DCT (Data Collection Template) which will be provided by the business. This DCT will be used for transformation and generation of the pre-load file. The activity prices will be uploaded via excel upload option in KP26. The conversion and transformation for activity rates will not happen via Syniti as the data will be provided by business in the DCT page.
Data Privacy and Sensitivity
None
TKE006 | TKEXXX | Price Unit in CO Area Currency | NUMC | 5 | Mandatory | |
COEJT | TKE007 | TKEXXX | Price Unit in CO Area Currency | NUMC | 5 | Mandatory |
COEJT | TKE008 | TKEXXX | Price Unit in CO Area Currency | NUMC | 5 | Mandatory |
COEJT | TKE009 | TKEXXX | Price Unit in CO Area Currency | NUMC | 5 | Mandatory |
COEJT | TKE010 | TKEXXX | Price Unit in CO Area Currency | NUMC | 5 | Mandatory |
COEJT | TKE011 | TKEXXX | Price Unit in CO Area Currency | NUMC | 5 | Mandatory |
COEJT | TKE012 | TKEXXX | Price Unit in CO Area Currency | NUMC | 5 | Mandatory |
COEJT | LEDNR | LEDNR | Ledger for Controlling Objects | CHAR | 2 | Optional |
COEJT | OBJNR | J_OBJNR | Object Number | CHAR | 22 | System Generated |
COEJT | GJAHR | GJAHR | Fiscal Year | NUMC | 4 | Mandatory |
COEJT | VERSN | VERSN | Version | CHAR | 3 | Mandatory |
COEJT | VRGNG | CO_VORGANG | CO Business Transaction | CHAR | 4 | System Generated |
COEJT | REFBZ | CO_REFBZ | Posting Row of Reference Document | NUMC | 3 | System Generated |
Note: Generally the activity prices in KP26 are entered as fixed prices. The variable price (i.e. plan price) is derived by the system when cost planning is used. However, the upload template provided by SAP has fields for both fixed price and variable price. The COST or COEJT tables do not have a field for variable price. The variable price is derived by deducting the fixed price from the total price i.e. Variable price = Total Price - Fixed Price.
Data Cleansing
For the purpose of the Object 9107- Activity rates, the data cleansing is not applicable. It is expected that relevant records will be provided in DCT by business.
Conversion Process
For activity rates the data will be collected in the DCT page. The conversion process will depend upon the DCT (Data Collection Template) which will be provided by the business. This DCT will be used for transformation and generation of the pre-load file. The activity prices will be uploaded via excel upload option in KP26. The conversion and transformation for activity rates will not happen via Syniti as the data will be provided by business in the DCT page.
Data Privacy and Sensitivity
None
Extraction
For object 9107 – Activity rates, the extraction is not applicable as this will be a DCT provided by business.
Selection Screen
Not Applicable
Data Collection Template (DCT)
Target Ready Data Collection Template will be created for 9107- Activity Rates data with exception of some fields which require transformation as mentioned in the transformation rule.
9107 – Activity Rates - DCT Rules
Field Name | Field Description | Rule |
KOKRS | Controlling area | This is a Mandatory field Enter the controlling area for which the rates belong. |
GJAHR | Fiscal Year | This is mandatory. Enter the Fiscal year for which the rates are being entered. |
PERBL | From Period | This is a Mandatory field Enter the from period |
PERBL | To Period | This is a Mandatory field Enter the To period |
VERSN | Version | This is mandatory Enter “0” |
KOSTL | Cost Centre | This is a Mandatory field Enter the cost centre for which the activity price is being maintained |
LSTAR | Activity Type | This is a Mandatory field Enter the Activity type for which the activity price is being maintained |
LSTXX | Activity Quantity | This is a Mandatory field Enter “1” |
SPRED | Distribution Key | This is a Mandatory field Enter “1” |
TKFXXX | Fixed Price | This field is optional Enter the fixed price if the activity price is based on fixed price basis |
SPRED | Distribution Key Fixed Price | This is a Mandatory field Enter “1” |
TKVXXX | Variable Price | This field is optional This field is generally used for planned prices entered in KP06. Enter the Variable price if the activity price is based on variable price basis. |
SPRED | Distribution Key Variable Price |
Extraction
For object 9107 – Activity rates, the extraction is not applicable as this will be a DCT provided by business.
Selection Screen
Not Applicable
Data Collection Template (DCT)
Target Ready Data Collection Template will be created for 9107- Activity Rates data with exception of some fields which require transformation as mentioned in the transformation rule.
9107 – Activity Rates - DCT Rules
Field Name | Field Description | Rule | ||
KOKRS | Controlling area | This is a Mandatory field Enter the controlling area for which the rates belong. | ||
GJAHR | Fiscal Year | This is mandatory. Enter the Fiscal year for which the rates are being entered. | ||
PERBL | From Period | This is a Mandatory field Enter the from period“1” | ||
PERBLTKEXXX | To PeriodPrice Unit | This is a Mandatory field Enter the To period | ||
VERSN | Version | This is mandatory Enter “0” | ||
price unit for which the price is being maintained e.g. "1", "1000" etc. | ||||
WAERS | Currency | KOSTL | Cost Centre | This is a Mandatory field Enter the cost centre for currency in which the activity price is being rates are to be maintained |
LSTARSPREDActivity | Distribution Key Plan Activity | This is a Mandatory field Enter “1” | ||
VKSTA | Allocation Cost Element Type | This is a Mandatory field Enter the Activity type for which the activity price is being maintained | ||
LSTXX | Activity Quantity | This is a Mandatory field Enter “1” | ||
SPRED | Distribution Key | This is a Mandatory field Enter “1” | ||
TKFXXX | Fixed Price | This field is optional Enter the fixed price if the activity price is based on fixed price basis | ||
SPRED | Distribution Key Fixed Price | This is a Mandatory field Enter “1” | ||
TKVXXX | Variable Price | This field is optional This field is generally used for planned prices entered in KP06. Enter the Variable price if the activity price is based on variable price basis. | ||
SPRED | Distribution Key Variable Price | This is a Mandatory field Enter “1” | ||
TKEXXX | Price Unit | This is a Mandatory field Enter the price unit for which the price is being maintained e.g. "1", "1000" etc. | ||
WAERS | Currency | This is a Mandatory field Enter the currency in which the activity rates are to be maintained | ||
SPRED | Distribution Key Plan Activity | This is a Mandatory field Enter “1” | ||
VKSTA | Allocation Cost Element | This is a Mandatory field Enter the allocation cost element to be used for uploading the prices |
Extraction Dependencies
For object 9107 – Activity Rates, no extraction dependencies are applicable as this is a DCT.
allocation cost element to be used for uploading the prices |
Extraction Dependencies
For object 9107 – Activity Rates, no extraction dependencies are applicable as this is a DCT.
Transformation
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti to make the data Target ready:
- Perform value mapping and data transformation rules.
- Legacy values are mapped to the to-be values (this could include a default value)
- Values are transformed according to the rules defined in Syniti
- Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation
Transformation Run Sheet
Item # | Step Description | Team Responsible |
1 | Ensure all the fields that require value mapping, as stipulated Mapping tables, have the latest signed-off mapping files imported into Syniti | Data team |
2 | Ensure that signed off value mappings have been maintained in the Syniti | Syniti team |
3 | Confirm the value mappings are maintained in Syniti | Data team |
4 | Ensure that the relevancy rules for extraction are signed off by all relevant business stakeholders. If a DCT page is to be used then, ensure that Signed off DCT from business has been received and maintained in Syniti | Syniti/Data team |
5 | Execute transformation for the object | Syniti team |
6 | Monitor the transformation progress and ensure performance and completion is within allowed timeframe | Syniti/Data team |
7. | Generate Pre-Load reports. | Syniti team |
8. | Generate data load count. | Syniti team |
9. | Log errors as defects, if any and address resolutions. Close defects. | Syniti/Data team |
10. | Re-transform and re-validate the Pre-load reports if necessary. | Syniti/Data team |
11. | Validate the transformed file as part of pre-load validation, raise data defects or provide the pre-load sign-off. | Business |
12. | Analyse and resolve any pre-load defects logged by business. | Syniti/Data team |
13. | Repeat steps 5 to 11 if necessary | Syniti/Data team |
14. | Proceed to pre-load validations | Data team |
Transformation Rules
Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
01 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | KOKRS | Controlling Area | As per DCT |
02 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | GJAHR | Fiscal Year | As per DCT |
03 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | PEBRL | From Period | As per DCT |
04 |
Transformation
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow Syniti to make the data Target ready:
- Perform value mapping and data transformation rules.
- Legacy values are mapped to the to-be values (this could include a default value)
- Values are transformed according to the rules defined in Syniti
- Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation
Transformation Run Sheet
Item # | Step Description | Team Responsible |
1 | Ensure all the fields that require value mapping, as stipulated Mapping tables, have the latest signed-off mapping files imported into Syniti | Data team |
2 | Ensure that signed off value mappings have been maintained in the Syniti | Syniti team |
3 | Confirm the value mappings are maintained in Syniti | Data team |
4 | Ensure that the relevancy rules for extraction are signed off by all relevant business stakeholders. If a DCT page is to be used then, ensure that Signed off DCT from business has been received and maintained in Syniti | Syniti/Data team |
5 | Execute transformation for the object | Syniti team |
6 | Monitor the transformation progress and ensure performance and completion is within allowed timeframe | Syniti/Data team |
7. | Generate Pre-Load reports. | Syniti team |
8. | Generate data load count. | Syniti team |
9. | Log errors as defects, if any and address resolutions. Close defects. | Syniti/Data team |
10. | Re-transform and re-validate the Pre-load reports if necessary. | Syniti/Data team |
11. | Validate the transformed file as part of pre-load validation, raise data defects or provide the pre-load sign-off. | Business |
12. | Analyse and resolve any pre-load defects logged by business. | Syniti/Data team |
13. | Repeat steps 5 to 11 if necessary | Syniti/Data team |
14. | Proceed to pre-load validations | Data team |
Transformation Rules
Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic | |
01 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | KOKRSPEBRL | Controlling AreaTo Period | As per DCT | |
0205 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | GJAHRVERSN | Fiscal YearVersion | As per DCT | |
0306 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | PEBRLKOSTL | From PeriodCost Centre | As per DCT | |
0407 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | PEBRLLSTAR | To PeriodActivity Type | As per DCT | |
0508 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | VERSNLSTXX | VersionActivity Quantity | As per DCT | |
0609 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | KOSTLSPRED | Cost CentreDistribution Key | As per DCT | |
0710 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | LSTARTKFXXX | Activity TypeFixed Price | As per DCT | |
0811 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | LSTXX | SPRED | Distribution Key Fixed PriceActivity Quantity | As per DCT |
0912 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | SPREDTKVXXX | Distribution KeyVariable Price | As per DCT | |
1013 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | TKFXXXSPRED | Fixed Distribution Key Variable Price | As per DCT | |
1114 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | SPREDTKEXXX | Distribution Key Fixed Price Unit | As per DCT | |
1215 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | TKVXXXWAERS | Variable PriceCurrency | As per DCT | |
1316 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | SPRED | Distribution Key Variable PricePlan Activity | As per DCT | |
1417 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | TKEXXX | VKSTA | Allocation Cost ElementPrice Unit | As per DCT |
15 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | WAERS | Currency | As per DCT | |
16 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | SPRED | Distribution Key Plan Activity | As per DCT | |
17 | DCT | NA | NA | CONSTRUCT | S4HANA | COEJT | VKSTA | Allocation Cost Element | As per DCT |
Transformation Mapping
Below value mapping tables should be constructed in Syniti
Mapping Table Name | Mapping Table Description |
Controlling Area | Controlling area should be configured and be available in value mapping or as default if only one controlling area is being used |
Ledger | Ledger(s) should be configured and should be available. |
Version | Version should be configured and should be available. |
Transformation Dependencies
List the steps that need to occur before transformation can commence
Item # | Step Description | Team Responsible |
1 | Ensure all the fields that require value mapping, as stipulated Mapping tables, have the latest signed-off mapping files imported into Syniti | Data team |
2 | Ensure that signed off value mappings have been maintained in the Syniti | Syniti team |
3 | Confirm the value mappings as maintained in the Syniti | Data team |
4 | Ensure that Signed off DCT from business has been received and maintained in Syniti | Syniti/Data team |
5 | Confirm on the extracted values | Syniti, Data and business |
Transformation Mapping
Below value mapping tables should be constructed in Syniti
Mapping Table Name | Mapping Table Description |
Controlling Area | Controlling area should be configured and be available in value mapping or as default if only one controlling area is being used |
Ledger | Ledger(s) should be configured and should be available. |
Version | Version should be configured and should be available. |
Transformation Dependencies
List the steps that need to occur before transformation can commence
Item # | Step Description | Team Responsible |
1 | Ensure all the fields that require value mapping, as stipulated Mapping tables, have the latest signed-off mapping files imported into Syniti | Data team |
2 | Ensure that signed off value mappings have been maintained in the Syniti | Syniti team |
3 | Confirm the value mappings as maintained in the Syniti | Data team |
4 | Ensure that Signed off DCT from business has been received and maintained in Syniti | Syniti/Data team |
5 | Confirm on the extracted values | Syniti, Data and business |
Pre-Load Validation
Project Team
The Pre Load validations are performed by Project Team
Completeness
Task | Action |
Generation of | Mandatory field check.
|
Record Count | Record Count Confirm the record counts in preload summary report
Invalid Records: |
Business Confirmation | Data team after the initial validation of Pre-Load validation based on the pre agreed validation checklist To send the Pre-Load file to the Business Representatives for all plants/valuation area in scope for conversion Business Representatives to validate the pre-load file Agree with data team on the next steps for erroneous records |
Accuracy
Task | Action |
Mandatory field mapping and transformation | Obtain a list of the fields to be populated with values from mapping files and ensure all these fields contain S/4HANA values.
|
Business Value Checks | The total values as per the relevancy /DCT and pre-load value are matching for the fields containing the limit amounts |
Records in Errors | Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source data. |
Business
The following pre-load validations will be performed by business.
Completeness
Task | Action |
Check Data load register count | Business Data Owner/s to verify that the total number of relevant records to be converted as per relevancy / DCT is equal to the total number of records in the Preload file. |
Accuracy
Task | Action |
Conversion accuracy | To check and validate the load files with all the transformation and mapping rules, to be signed off. |
Note: Generally the activity prices in KP26 are entered as fixed prices. The variable price (i.e. plan price) is derived by the system when cost planning is used. However, the upload template provided by SAP has fields for both fixed price and variable price. The COST or COEJT tables do not have a field for variable price. The variable price is derived by deducting the fixed price from the total price i.e. Variable price = Total Price - Fixed Price
Pre-Load Validation
Project Team
The Pre Load validations are performed by Project TeamCompleteness
Task | Action |
Generation of | Mandatory field check.
|
Record Count | Record Count Confirm the record counts in preload summary report
Invalid Records: |
Business Confirmation | Data team after the initial validation of Pre-Load validation based on the pre agreed validation checklist To send the Pre-Load file to the Business Representatives for all plants/valuation area in scope for conversion Business Representatives to validate the pre-load file Agree with data team on the next steps for erroneous records |
Accuracy
Task | Action |
Mandatory field mapping and transformation | Obtain a list of the fields to be populated with values from mapping files and ensure all these fields contain S/4HANA values.
|
Business Value Checks | The total values as per the relevancy /DCT and pre-load value are matching for the fields containing the limit amounts |
Records in Errors | Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source data. |
Business
The following pre-load validations will be performed by business.
Completeness
Task | Action |
Check Data load register count | Business Data Owner/s to verify that the total number of relevant records to be converted as per relevancy / DCT is equal to the total number of records in the Preload file. |
Accuracy
Task
Action
Conversion accuracy
.
Load
The load process includes:
- Execute the automated data load into target system using load tool or produce the load file if the loading of records to be done via a custom program <TBC>, as LTMC for this object is not available as of now.
- Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation with side by side check of each fields in scope of the objects with fields to be displayed as XXXX_ECC, XXXX_S4HANA, XXXX_MATCH ( As TRUE or FALSE) with an additional column denoting fields not matching and status of loading in S/4HANA as LOADED_IN_S4HANA ( As TRUE or FALSE)
- Load Template for activity rates
View file name Activity Price Template SY.xlsx height 250
Load Run Sheet
Item # | Step Description | Team Responsible |
1 | Go to load file and pick 5 data records, load manually without any tool. See what happens. If all okay, proceed with the next step. | Data team |
2 | Go to load file and pick 10 records and load them with the tool. No action if the previous step has fallen. If not, then continue to load 10 records with the tool. Check if everything went okay. | Data team |
3 | Proceed with the full load if steps one and two were succeed else fix the issue with records | Data team |
4 | Validate few records loaded by accessing standard transactions from S/4HNA e.g. KP27 to check the activity prices. | Data team |
5 | Generate post load report if step 5 is validated | Data team |
6 | Log errors as defects, if any and address resolutions. Close defects. | Data team |
7 | Resolve defects by reupload and re-generate post load reports if necessary. | Data team |
8 | Business to validate the post load files as part of post-load validation, raise data defects or provide the post-load sign-off. | Business |
9 | Repeat steps 1 to 5 if necessary. | Data team |
Load Phase and Dependencies
The load phase for this object is ideally relevant for pre-cutover Phase 4
Configuration
Below configurations must exist to facilitate the conversion of this object.
Item # | Configuration Item |
01 | Controlling Area (Check Table: TKA01) |
02 | Company code (Check Table: T001) |
03 | Activity types (Master Data) |
04 | Version (Check Table: TKA09) |
05 | Price Indicatory (Check Table: TKA10) |
Conversion Objects
Object # | Preceding Object Conversion Approach |
CNV-1074 | Cost Centre(s) |
CNV-1071 | Activity types |
CNV-1072 | Exchange Rates |
Error Handling
The table below depicts some possible system errors for this data object during data load. All data load error is to be logged as defect and managed within the Defect Management
Error Type | Error Description | Action Taken |
Activity price | Activity price wrong conversion with regards to price unit | Ensure that the price unit is correctly picked |
Fiscal Year | Enter correct fiscal year | Correct fiscal year |
Activity type | Cost centre and activity type combination does not match | Ensure to maintain the correct cost centre and activity type match. |
Post-Load Validation
Project Team
The following post load validations will be done by Project Team
Completeness
Task | Action |
Reconciliation of Record Count | Record Count - Count and check how many records were loaded vs. Records in the load file (Each mock has its own data record count) Check for logs from Load and fix erroneous records, if any. |
Accuracy
Task | Action |
Check values in key fields for accuracy | Post-load reports will have the same structure as the load file and some additional columns as required to facilitate the post load validation. Leverage on tool to create a Post Load report that reports S/4HANA loaded records along with the legacy values side-by-side to allow for 100% check of all these fields in the shortest possible time. Any mismatch will be reported under the Post Load - Error report. |
Business
The following post load validations will be done by business.
Completeness
Task | Action |
Record Count Check | Review the record count report from the Data Team and ensure it is correct by cross-checking with the record count confirmed during Pre-load Business Validations Business may also run transaction code KP27 to cross check the Activity Prices |
Accuracy
Task
Action
Field Checks
Check the fields to ensure that Activity Prices have been properly maintained
Value Check
be done by business.
Completeness
Task | Action |
Record Count Check | Review the record count report from the Data Team and ensure it is correct by cross-checking with the record count confirmed during Pre-load Business Validations Business may also run transaction code KP27 to cross check the Activity Prices |
Accuracy
Task | Action |
Field Checks | Check the fields to ensure that Activity Prices have been properly maintained |
Value Check | Check the activity prices against activity types and corresponding cost centres. |
Note: Generally the activity prices in KP26 are entered as fixed prices. The variable price (i.e. plan price) is derived by the system when cost planning is used. However, the upload template provided by SAP has fields for both fixed price and variable price. The COST or COEJT tables do not have a field for variable price. The variable price is derived by deducting the fixed price from the total price i.e. Variable price = Total Price - Fixed Price.
Key Assumptions
- Relevancy rules has been thoroughly validated and signed off by business.
- Activity types and cost centre combination has been validated.