Purpose

The purpose of this document is to define the conversion approach to create Portfolio Item in S/4 HANA.

PPM Item: A PPM Item is a proxy of project in PPM which is used to plan, evaluate, and monitor Spend (Capex and Opex) within Syensqo’s portfolio. In SyWay, PPM Items are created under the lowest level bucket.



Conversion Scope

The scope of this document covers the approach for converting applicable active Projects to Portfolio Items from Legacy Source Systems into S/4HANA following the Portfolio Item Master Data Design Standard.

This is a completely new object for Syensqo, with the data being sourced using a DCT (Data Collection Template).

The DCT will contain transformed data from source system for Capital and Budget Managed Operating PS Project Definitions in scope for migration, extensive enrichment will be necessary to produce properly formatted data load sheets for S/4 HANA. 


Relevancy Criteria

The data from legacy system includes:

    1. Capital projects (e.g. Industrial, Facility, IT and R&I) open as at migration date with postings in the agreed migration time frame or has AUC balance.
    2. Budgeted Operating projects (e.g. Budgeted Maintenance, Marketing, Demolition projects) open as at migration date with postings in the agreed migration time frame
    3. Closed Capital Projects with postings within the agreed timeframe.
    4. Closed Budgeted Operating projects with postings within the  agreed timeframe. 
    5. Specifically also included are IT and R&I Projects (open as at migration date and (closed projects with postings the agreed timeframe) with postings agreed migration time frame 

The data from legacy system excludes

    1. Project Definition in out of scope Company Codes
    2. Project Definitions in out of scope Plants.
    3. Project which has deletion indicator set
    4. Project marked as closed and not included in C, D and E above.
    5. Non Budgeted maintenance Projects.

Also exclude, Operating Expense projects without budget, including the following proposed project profile in S/4:

                a. Open Project for Statistical Expenses - replaced by project definitions with profile ZPS0003 - Statistical Expense.

                b. Open Recharge Projects - replaced by project definitions with profile ZPS0004 - Intercompany Recharges.

                 c. Open Project definitions with profile ZPS0005 - Provisional Projects.

The migration for these excluded Operating Expense project without budget is dealt with in CNV-1024 Project Definition 


Additionally, there may be Items included in the DCT which does not have any existing Project Systems objects. as well as 

Direct Asset purchases for which an Item is created for GBU/Company Code/Plant combination 

Capital Spare for which an item is created for GBU/Company Code/Plant combination

Capital Lease for which an item is created for GBU/Company Code/Plant combination

Cluster Item

Budget Provision Item

  

List of source systems and approximate number of records 

SourceScope

Source Approx No. of Records

Target SystemTarget Approx

No. of Records

PF2Relevant PS ProjectsTBDS/4 HanaTBD
WP2Relevant PS ProjectsTBDS/4 HanaTBD
DCT

S/4 HanaTBD

Item is to be migrated into a single instance of S/4 Hana only with the determination of which instance dependent on the company code maintained in the area field of the item. Area will be maintained based upon the converted Company Code of the legacy Project Definition.

 For items the following scenarios with the PS Project definition with WBS element hierarchy is automatically created on loading of the PPM item be created for the.

  • Migration relevant project
  • Item type Capital Spares,
  • Item type Capital Leases
  • Item type Capital Purchases


Identification Logic

Capital project is a project that has any WBS elements with a Investment Profile. PRPS-IMPRF

Budgeted Opex is any other project that has any WBS elements with budget.  WBS has entry in BPGE for value type 41

IT Project is a project that has a WBS element one of the following criteria

  • in WP2 user field 1 starting with IT  PRPS-USR00
  • in PF2 user field 2 starts with IT    PRPS-USR01
  • has a WBS element Family is SBS IS

R&I Project is a project meeting one of the following criteria, 

  •  in PF2 Project ID starts with R-   PROJ-PSPID
  • in WP2 Project ID starts with RR   PROJ-PSPID
  • has a WBS element with WEGO ID field filled  PRPS-ZZ_WEGO_ID
  • has a WBS element family indicated as R&I or R&I Others

Industrial projects 

  • Capital project is a project that has any WBS elements with a Investment Profile. PRPS-IMPRF
  • Budgeted Opex is any other project that has any WBS elements with budget.  WBS has entry in BPGE for value type 41
  • has a WBS element family indicated as GEC, Regular,RegAffairs or Others

Facilities Projects

  • Capital project is a project that has any WBS elements with a Investment Profile. PRPS-IMPRF
  • Budgeted Opex is any other project that has any WBS elements with budget.  WBS has entry in BPGE for value type 41
  • has a WBS element family indicated as Facilities



Projects with Status closed.

Table JEST:

Field "Object number" = Key in the object numbers of Project 

Field "Status Inactive" = blank, 

Field Status = I0046 (Closed)

If status Closed is active further check for postings in the agreed timeframe)


Get All WBS elements 

Table PRPS

Field PSPHI For closed projects numbers, Result WBS numbers for closed projects.


Check for postings 

Table RPSCO / COSP:

Field "Object number" = Key in the object numbers of WBS

Field "Fiscal Year" = the agreed timeframe.

Result = Object numbers that have cost in agreed timeframe.

If count is greater than 0 then the project needs to be migrated.




Additional Information

Multi-language Requirement

All item names and texts will be maintained in a single language as entered, with no requirement for translation.

Document Management

Not applicable

Legal Requirement

Not applicable

Special Requirements

Not applicable

Target Design

The technical design of the target for this conversion approach.   If standard upload is used some system generated fields must be maintained in the transformation.

CR359 - Custom Field name changes

TableFieldData ElementField DescriptionData TypeLengthRequirement
/RPM/ITEM_DEXTERNAL_ID/RPM/TV_EXTIDIDCHAR24System Generated
/RPM/ITEM_DPARENT_ID/RPM/TV_EXTIDParent Bucket IDCHAR24Mandatory
/RPM/ITEM_DPORTFOLIO_ID/RPM/TV_EXTIDPortfolio IDCHAR24Mandatory
/RPM/ITEM_DITEM_TYPE/RPM/TV_ITEM_IDItem TypeCHAR15Mandatory
CGPL_TEXTTEXT1CGPL_TEXT1NameCHAR40Mandatory
STXLCLUSTD (LTEXT for identification in Transformation))CLUSTDItem DescriptionCLUSTD512Conditional
/RPM/ITEM_DSTATUS/RPM/TV_STATUS_COMMONItem StatusCHAR5Mandatory
/RPM/ITEM_DPLANNED_STARTRPM_TV_PLAN_STARTPlanned StartDATS8Mandatory
/RPM/ITEM_DPLANNED_FINISHRPM_TV_PLAN_FINISHPlanned FinishDATS8Mandatory
/RPM/ITEM_DGEOGRAPHYRPM_TV_PROJECT_GEOGRAPHYCompany CodeCHAR4Mandatory
/RPM/ITEM_DCURRENCYRPM_TV_CURRENCYCURRENCYCUKY5System Generated
/RPM/ITEM_DUNITRPM_TV_UNITUnitUNIT3System Generated
/RPM/ITEM_DCAP_PERIODTYPE/RPM/TV_CAP_PERIOD_TYPECapacity Period BreakdownNUMC2System Generated
/RPM/ITEM_DPERIODTYPE/RPM/TV_PERIOD_TYPEFin Period BreakdownNUMC2System Generated
/RPM/ITEM_DINITIATIVE_IDINM_TV_EXTIDINITIATIVE IDCHAR24Conditional
/RPM/ITEM_DSYSPEND_RANGE
Spending RangeNUMC2System Generated
/RPM/ITEM_DSYGBU_MHIER
GBU Market HierarchyCHAR50Conditional
/RPM/ITEM_DSYCORP_HIER
Corporate HierarchyCHAR50Conditional
/RPM/ITEM_DSYINVST_REASON
Investment ReasonCHAR50Mandatory
/RPM/ITEM_DSYSUB_BUS_DRI
Sub Business DriverCHAR50System Generated
/RPM/ITEM_DSYMAIN_BUS_DRI
Main Business DriverCHAR50System Generated
/RPM/ITEM_DSYINVST_CAT 
Investment CategoryCHAR50System Generated
/RPM/ITEM_DSYCLUSTER/RPM/TV_EXTIDClusterCHAR24Conditional
/RPM/ITEM_DSYPROD_HIER
Product HierarchyCHAR50Conditional
/RPM/ITEM_DSYEXPO_CO
Export ControlNUMC2Mandatory
STXLZ04
Justification (Export Control)CLUST512Conditional
/RPM/ITEM_DSYNEED_KNOW
Need-to-knowCHAR3Mandatory
/RPM/ITEM_DSYPROJ_OWN
Project OwnerNUMC8Mandatory
/RPM/ITEM_DSYPFIN_CON
Project Financial ControllerNUMC8Mandatory
/RPM/ITEM_DSYSCOR_METH
Scoring MethodologyCHAR15System Generated
/RPM/ITEM_DSYST_RISK_MAG
Starting Risk MagnitudeNUMC2Conditional
/RPM/ITEM_DSYST_RISK_LIK
Starting Risk LikelihoodNUMC2Conditional
/RPM/ITEM_DSYRE_RISK_MAG
Residual Risk MagnitudeNUMC2Conditional
/RPM/ITEM_DSYRE_RISK_LIK
Residual Risk LikelihoodNUMC2Conditional
/RPM/ITEM_DSYRE_MAN_MAG
Regulatory Mandated MagnitudeNUMC2Conditional
/RPM/ITEM_DSYRE_MAN_LIK
Regulatory Mandated LikelihoodNUMC2Conditional
/RPM/ITEM_DSYRE_MAN_TIM
Regulatory Mandated Time Horizon (to start project)NUMC2Conditional
/RPM/ITEM_DSYCAP_DAT
Capitalization DateDATS8Conditional
/RPM/ITEM_DSYPRCTRPRCTRProfit CentreCHAR10Mandatory
/RPM/ITEM_DSYBUDG_PRO/RPM/TV_EXTIDBudget ProvisionCHAR24Conditional
/RPM/ITEM_DSYOPP_ID
Opportunity IDCHAR18Conditional
/RPM/ITEM_DSYARCHETY
ArchetypeNUMC2Conditional
/RPM/ITEM_DSYMUST_JUS
Must Do JustificationNUMC2Mandatory
/RPM/ITEM_DSYLEG_PRJIDPS_PSPIDLegacy Project IDCHAR24Conditional
/RPM/ITEM_DSYWERKSWERKS_DPlantCHAR4Conditional
/RPM/ITEM_DSYIDEAID
Idea IDCHAR7Conditional
/RPM/ITEM_DSY_ERDAT
Created OnDATS8System Generated
/RPM/ITEM_DSYSUBSIDY
SubsidyCHAR1Conditional
STXLZ03CLUSTDSubsidy RelevanceCLUSTD512Conditional
STXLZ01CLUSTDKey AssumptionsCLUSTD512Conditional
STXLZ02CLUSTDVariationsCLUSTD512Conditional
STXLZ05CLUSTDOther InformationCLUSTD512Conditional
STXKZ08CLUSTDLessons LearntCLUSTD512Conditional


Decision Point Table

TableFieldData ElementField DescriptionData TypeLengthRequirement
/RPM/DECISIONDECISION_ID/RPM/TV_EXTIDIDCHAR24Mandatory
/RPM/DECISIONITEM_ID/RPM/TV_EXTIDITEM_IDCHAR24Mandatory
CGPL_TEXTTEXT1
NAMECHAR40Mandatory
/RPM/DECISIONSTATUS/RPM/TV_STATUS_COMMONSTATUSCHAR5Conditional
/RPM/DECISIONPLAN_STARTRPM_TV_PLAN_START
Planned Start Date
DATS8Conditional
/RPM/DECISIONPLAN_FINISHRPM_TV_PLAN_FINISH
Planned Finish Date
DATS8Conditional
/RPM/DECISIONACTUAL_STARTRPM_TV_ACTUAL_STARTActual Start DateDATS8System Generated
/RPM/DECISIONACTUAL_FINISHRPM_TV_ACTUAL_FINISHActual Finish DateDATS8System Generated
/RPM/DECISIONSYVAR_REF
Variation ReferenceCHAR60Conditional

CR359 - Custom Field name changes END

 Item Authorizations (Required only where Need-to-know = yes)

TableFieldData ElementField DescriptionData TypeLengthRequirement
ACO_USERITEM_ID/RPM/TV_EXTIDIDCHAR24Conditional
ACO_USERACTIVITYACO_ACTVTActivityCHAR10Conditional
ACO_USERUSERACO_USER_IDUserCHAR12Conditional

Relationship between /RPM/ITEM_D and CGPL_TEXT is the field /RPM/ITEM_D-GUID one to one.


Relationship between /RPM/ITEM_D and /RPM/DECISION  is the field /RPM/ITEM_D-GUID one item to many decision points.

Relationship between /RPM/ITEM_D and ACO_USER is the field /RPM/ITEM_D-GUID one item to optional many users. 



Data Cleansing

This is a completely new object based on Projects and WBS information.   All cleansing requirements dealt with in CNV-1024 Project Definition and CNV-1026 WBS - CAPEX, OPEX, Statistical

IDCriticalityError Message/Report DescriptionRuleOutputSource System


Conversion Process

The high-level process is represented by the diagram below:

image-2025-10-13_15-16-37.png



Data Privacy and Sensitivity

Some projects are considered Need to Know and data is to be restricted to named users only.


Extraction

  1. Extract data from a source into Syniti Migrate. There are 2 possibilities:

    1. The data exists. Syniti Migrate connects to the source and loads the data into Syniti Migrate. There are 3 methods:
      1. Perform full data extraction from relevant tables in the source system(s).
      2. Perform extraction through the application layer.
      3. Only if Syniti Migrate; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
    2. The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate

    The agreed Relevancy criteria is applied to the extracted records as reference point to identify the records that are applicable for the data construction in the DCT.

Extraction Run Sheet

Req #Requirement DescriptionTeam Responsible
1Extract data from source system based on relevancy ruleSyWay Data Team


Selection Screen


Selection Ref ScreenParameter NameSelection TypeRequirementValue to be entered/set
Not Applicable




Data Collection Template (DCT)

Target Ready Data Collection Template will be created for Portfolio Item data with exception of some fields which require transformation as mentioned in the transformation rule.

Note: All rules specified below should be documented as a tooltip in the DC Page.

2 Groups of DCT's have been identified.  This is to deal with 


Portfolio Item SAP Legacy (for projects with SAP Legacy data)

DCT Rules

CR359 - Custom Field name changes

Field NameField DescriptionRule
SNROItem ID

Tooltip

The Project number from the legacy SAP system.

This number will be replaced by the new automatically generated Item ID.  The number will remain available in the legacy project ID field on the item.


Internal Controls

Display from Prep Report - PROJ-PSPID


GBULegacy GBU

Tooltip

GBU from Legacy SAP System.
Displayed for Context Only


Internal Control 

Display from Prep report - PROJ-ZZGBU

BULegacy Business Unit

Tooltip

Business Unit from Legacy SAP System.
Displayed for Context Only

Internal Control 

Display from Prep report - PROJ-ZZBU

PARENT_IDParent Bucket ID

Tooltip

Unique Identifier for the Item's parent Bucket. In SyWay it is the ID of the L3 bucket where item is assigned

The bucket represents the GBU and Function

This is a Required Field


Internal Controls

Dropdown list from the Buckets maintained in CNV_1113 Portfolio Bucket Hierarchy

It is a Required Field.

WBS_FAMILYLegacy WBS Family

Tooltip

WBS Family from Legacy System.
Displayed for Context only


Internal Controls

Display from Prep Report - PROJ-ZZFAMILY for PF2 or Calculated from PRPS-ZZ_FAMIL for WP2

ITEM_TYPE_ECCCalculated Item Type

Tooltip

The suggested item type based on mapping rules.

This suggested item type will be used if Item Type is not selected 

Internal Controls

Display from Prep Report - Based on Transformation Rules.

ITEM_TYPEItem Type

Tooltip

Item types define the structure and behaviour of the portfolio item.

In SyWay item types will be based on the function and number of phases of the project.

This is a required field when the Calculated Item type is blank. 

Internal Controls

Refer configuration table field /RPM/ITEM_TYPE- ITEM_TYPE for allowed values.

It is a Required Field if No Calculated Item Type: Preload Check to be done to confirm that this field is filled in the Data Collection Template

TEXT1Name

Tooltip

Short description of the PPM Item

No Update Required


Internal Controls

PrepReport - PROJ-POST1

It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

LTEXTItem Description

Tooltip

Long Description, this field is used to provide a concise description of the PPM Item. 

Entered where information is available


Internal Controls

Long text from Project Definition

STATUSItem Status

Tooltip

Represents status of an item.

For ongoing projects the status is expected as Z002:Approved


Internal Controls

Refer configuration table field /RPM/ITEM_STATUS- STATUS against ITEM_TYPE for the allowed values of the selected Item Type.

It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

PLANNED_STARTPlanned Start

Tooltip

Baseline start date of the item/ project used for planning within the portfolio/ bucket.

Pre-Populated with Legacy System Project Planned Start Date

This is a required field

Format (YYYYMMDD)


Internal Controls

Display from PREP Report - PROJ-PLFAZ

It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

PLANNED_FINNISHPlanned Finish

Tooltip

Baseline End date of the item/ project used for planning within the portfolio/ bucket.

Pre-Populated with Legacy System Project Planned End Date

This is a required field

Format (YYYYMMDD)


Internal Controls

Display from PREP Report - PROJ-PLSEZ

It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

IZWEKLegacy Investment Reason

Tooltip

The Investment Reason from the Project defiintion in Legacy SAP System

Displayed for Context Only


Internal Controls

Display from PREP Report - PROJ-ZZ_IZWEK

IZWEK_DESCLegacy Investment Reason Description

Tooltip

The Investment Reason Description from the Project defintion in Legacy System.

Displayed for Context Only


Internal Controls

Display from PREP Report - Description of Investment

SYINVST_REASONInvestment Reason

Tooltip

In Syway, Investment Reason is level-3 category of investment.

This is a required field


Internal Controls


It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

GEOGRAPHYCompany Code

Tooltip

The Company Code from the Project Definition in Legacy System
This is display only


Internal Controls

Display from PREP Report - PROJ-VBUKR

CurrencyCurrency

Tooltip

he Currency form project definition in Legacy System

This is display only


Internal Controls

Display from PREP Report - PROJ-PWHIE

INITIATIVE_IDINITIATIVE ID

Tooltip

Internal ID of Initiative where Item must be linked to Initiative



Internal Controls

Dropdown list from the Initiatives maintained in CNV_1023 Portfolio Initiatives

This is an optional field

SYGBU_MHIERGBU Market Hierarchy

Tooltip

GBU Market Hierarchy is a GBU-led Market segmentation, applied to both customer and product combination.  Any level of the Global Hierarchy can be selected.

Applicable and mandatory for PPM Items linked to Buckets with function R&I or IS


Internal Controls

Values from Global Hierarchy.

Mandatory when PPM Item is linked to a bucket with Functions R&I & IS 

Preload Check to be done to confirm that this field is filled in the Data Collection Template when required

SYCORP_HIERCorporate Hierarchy

Tooltip

Corporate-led Market segmentation used for reporting. Any level of the Global Hierarchy can be selected.

Applicable to all PPM Item types but not mandatory


Internal Controls

Values from Global Hierarchy.


Preload Check to be done to confirm that this field is filled the Data Collection Template when required

PRJ_GROUPProject Group

Tooltip

Project Group from Project Definition in legacy system

Displayed as Context for Cluster and Budget Provision


Internal Controls

Display from PREP Report - PROJ-ZZGROUP

SYCLUSTERCluster

Tooltip

In SyWay, Used to group items together for reporting where a budget allocation is made at an aggregated level, and actuals are collected against individual related items.


Internal Controls

Selection of Items maintained in with item type Z016 - Cluster

SYPROD_HIERProduct Hierarchy

Tooltip

Reference to the product hiearchy node ( at any level) required for reporting,

Field can be maintained for PPM Items linked to Buckets with IS, R&I, Commercial and Strategy functions.


Internal Controls

Refer table HRRP_NODE- NODEVALUE where HRRP_NODE- NODETYPE = N and HRYTYPE = MD01"

SYEXPO_COExport Control

Tooltip

To identify if the PPM item is applicable for export control governance.

Mandatory for all PPM Items.


Internal Controls

This is a dropdown field from /SYQ/T_EXPORT_CNTL

This is a required field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

Z04Justification (Export Control)

Tooltip

This field captures the justification for the relevance of export control.

Not required if  Export Control is "Non Determined" option is selected.


Internal Controls

This is required field except if  SYEXPO_CO "Non Determined": Preload Check to be done to confirm that this field is filled in the Data Collection Template

SYNEED_KNOWNeed-to-know

Tooltip

This field indicates confidential projects.

Access will be restricted to named user maintained by Project owner if selection is "Yes


Internal Controls

Options are Yes or No

It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

SYPROJ_OWNProject Owner

Tooltip

This field stores the Position of the Project Owner for the PPM Item and is mandatory for all SyWay business functions. 

Pre-populated with Project Responsible person Position from Legacy SAP System

This is a required field

Internal Controls

From PREP report - PROJ-ZZ_POSIT

Refer configuration table field TCJ04-PS_VERNR for field validation.

Preload Check to be done to confirm that this field is filled in the Data Collection Template when required.

ASTNRLegacy Applicant No

Tooltip

Project Applicant from the Project Definition for Legacy SAP system

Displayed for Context only


Internal Controls

From PREP report - PROJ-ASTNR

ASTNALegacy Applicant Name

 Tooltip

Project Applicant from the Project Definition for Legacy SAP system

Displayed for Context only


Internal Controls

From PREP report - PROJ-ASTNA

SYPFIN_CONProject Financial Controller

Tooltip

This field stores Position of the Project Financial Controller of a project.

This is a required field


Internal Controls

Refer configuration table field TCJ05-ASTNR for field validation.

It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

SYST_RISK_MAGStarting Risk Magnitude

Tooltip

For the Risk managed project - this field define the risk magnitude at the start of project.

This field is required to be maintained if Scoring Methodology = Risk

Investment Reasons flagged as Risk
0011:B1 Equipment maintenance
0014:B4 Turnarounds
0019:F1 Comm. needs-bus risk rdctn
0022:A1 Health/Safety-best practice
0025:A3 Security - best practices
0028:A5 Compliance- Future regulatn
0032:F3C Climate  / Other
0033:F4A Nature / Water
0034:F4B Nature / Other
0039:R4 Equip. Maintenance/Replcmnt
0040:R5 Facilities/site maintenance
0043:R8 IAM & regulatory


Internal Controls

This field is required to be maintained if Scoring Methodology = Risk  

This is a dropdown field /SYQ/T_RISK_MAGNITUDE

Preload Check to be done to confirm that this field is filled in the Data Collection Template when required.

SYST_RISK_LIKStarting Risk Likelihood

Tooltip

For the Risk managed project - this field define the risk likelihood at the start of project.

This field is required to be maintained if Scoring Methodology = Risk


Internal Controls

This field is required to be maintained if Scoring Methodology = Risk

This is a dropdown field /SYQ/T_RISK_LKLHD

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYRE_RISK_MAGResidual Risk Magnitude

Tooltip

For the Risk managed project - this field define the risk magnitude at the start of project.

This field is required to be maintained if Scoring Methodology = Risk


Internal Controls

This field is required to be maintained if Scoring Methodology = Risk

This is a dropdown field  from /SYQ/T_RISK_MAGNITUDE

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYRE_RISK_LIKResidual Risk Likelihood

Tooltip

For the Risk managed ongoing approved project - this field defines remaining risk likelihood.

This field is required to be maintained if Scoring Methodology = Risk

Internal Controls

This field is required to be maintained if Scoring Methodology = Risk

This is a dropdown field from /SYQ/T_RISK_LKLHD

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYRE_MAN_MAGRegulatory Mandated Magnitude

Tooltip

IImpact of regulatory compliance on project delivery.

This field is required to be maintained if Scoring Methodology = Regulatory

Investment Reason flagged as Regulatory
0023:A1C Health/Safety - Compliance
0024:A2 Environment  - Compliance
0026:A3C Security - Compliance
0035:F5 SoC/SVHC replacement - ASA
0038:R3 HSE
0049:I6 Cybersecurity & Compliance


Internal Controls

This field is required to be maintained if Scoring Methodology = Regulatory

This is a dropdown field from /SYQ/T_REG_MAGNITUDE

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYRE_MAN_LIKRegulatory Mandated Likelihood

Tooltip

Probability of impact due to regulatory compliance.

This field is required to be maintained if Scoring Methodology = Regulatory


Internal Controls

This field is required to be maintained if Scoring Methodology = Regulatory

This is a dropdown field from /SYQ/T_REG_LKLHD

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYRE_MAN_TIMRegulatory Mandated Time Horizon (to start project)

Tooltip

Regulatory defined deadline by which a project must commence.

This field is required to be maintained if Scoring Methodology = Regulatory


Internal Controls

This field is required to be maintained if Scoring Methodology = Regulatory

This is a dropdown field from /SYQ/T_REG_TIME_HORIZON

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYCAP_DATCapitalization Date

Tooltip

Stores the capitalization date for the purpose of "Depreciation forecast".

This date is mandatory for the Capital Projects Item types.  
Z001:Industrial with Qualification
Z002:Industrial w/out Qualification
Z003:Industrial 2 Phases
Z008:IT Full Lifecycle Project
Z009:IT Small Project
Z011:Turnaround Projects

Format (YYYYMMDD)


Internal Controls

This date is mandatory for the Capital Projects Item types.  Item Types are  Z001,Z002, Z003, Z008, Z009, Z011

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYPRCTRProfit Center

Tooltip

Profit Centre represents the GBU/Plant where the project is performed., Profit centre on PPM item will be validated with the PC on the Parent Bucket to check they belong to the same group.  This will ensure PPM items are created under correct GBU bucket. If plant is maintained then Profit Center is derived from it.

Pre-populated with Profit Center from the Project Definition

No Update Required


Internal Controls

From Prep Report - PROJ-PRCTR

Refer master table field CEPC-PRCTR for Profit center list. the Data Collection Template,  

It is required only if Plant is not filled: Preload Check to be done to confirm that this field is filled, and is aligned with the PC on the Parent Bucket, first character of the Profit centers must match

SYBUDG_PROBudget Provision

Tooltip

Used to group those PPM Items where the budget is drawn from the Budget provision Item.


Internal Controls

Selection of Items maintained in with item type Z015 - Budget Provision

SYOPP_IDOpportunity ID

Tooltip

Stores the CRM opportunity ID where applicable.

This is an optional field.

SYARCHETYArchetype

Tooltip

This field represents the classification of the R&I projects as different archetypes.

Not applicable for Items linked to Buckets with IS, IT & Facility/ Others functions. 


Internal Controls

This is a dropdown field from /SYQ/T_ARCHETYPE

Preload Check to be done to confirm that this field is filled in the Data Collection Template when required.

SYMUST_JUSMust Do Justification

Tooltip

This field provides input to the ranking of items in the priortization dashboard and is relevant across all PPM item types.


Internal Controls

This is a dropdown field from /SYQ/T_MUST_DO

This is a required field


SYWERKSPlant

Tooltip

Plant represent a site of the PPM Item. Plant is maintained when available.

Pre-populated with Plant from the Project Definition

No Update Required


Internal Control

From Prep Report - PROJ-WERKS

Preload validation that plant exist, T001W and is maintained for the Company Code 

This is an optional field.

SYIDEAIDIdea ID

Tooltip

Field to store the Idea number where this is known.

This is an optional field for migration

SYSUBSIDYSubsidy

Tooltip

Use this field if the project is eligible for government or institutional subsidies.

This is an optional field for migration


Internal Control

This is a true / false field

Z03Subsidy Relevance

Tooltip

This field is used to provide a concise description of the Subsidy Relevance.  (This is a long text field)

Required If Subsidy field is selected.


Internal Control

Required If Subsidy field is selected.

Z01Key Assumptions

Tooltip

This field is used to provide key Assumptions related to projects.  (This is a long text field)

Conditional for Items where assumptions are to be maintained,

This is an optional field for migration

Z02Variations

Tooltip

This field is used to provide details about key project variations.  (This is a long text field)

Conditional for Items where assumptions are to be maintained,

This is an optional field for migration

Z05Other Information

Tooltip

This field is used to provide additional details about project.  (This is a long text field)

This is an optional field for migration

Z08Lessons Learnt

Tooltip

Long-text description, this field is used to record the project insights and key takeaways of a project

This is an optional field for migration

ACT_DPCPTActive Decision Point

Tooltip

Indicates the currently active Decision Point (Stage Gate) for the item.

Relevant for the following item types 

Z001      Industrial with Qualification

Z002      Industrial w/out Qualification

Z004      New Product Introduction

Z005      Product & Process Improvement

Z008      IT Full Lifecycle Project

Z017      New Application Development

To be maintained when item is not in initial phase


Internal Control

Drop down field from /RPM/ITEM_PHASE based on selected ITEM_TYPE


Portfolio ITEM Construct (Used for projects without SAP Legacy Project)

DCT Rules

Field NameField DescriptionRule
SNROItem Serial Number

This field is display only and is filled with a sequential number when user adds a item record

PARENT_IDParent Bucket ID

Tooltip

Unique Identifier for the Item's parent Bucket. In SyWay it is the ID of the L3 bucket where item is assigned

The bucket represents the GBU and Function

This is a Required Field


Internal Controls

Dropdown list from the Buckets maintained in CNV_1113 Portfolio Bucket Hierarchy

It is a Required Field.

ITEM_TYPEType

Tooltip

Item types define the structure and behaviour of the portfolio item.

In SyWay item types will be based on the function and number of phases of the project.

This is a required field

Internal Controls

Refer configuration table field /RPM/ITEM_TYPE- ITEM_TYPE for allowed values.

It is a Required Field

TEXT1Name

Tooltip

Short description of the PPM Item


Internal Controls

It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

LTEXTItem Description

Tooltip

Long Description, this field is used to provide a concise description of the PPM Item. 

Entered where information is available

STATUSItem Status

Tooltip

Represents status of an item

For ongoing projects the status is expected as Z002:Approved


Internal Controls

Refer configuration table field /RPM/ITEM_STATUS- STATUS against ITEM_TYPE for the allowed values of the selected Item Type.

It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

PLANNED_STARTPlanned Start

Tooltip

Baseline start date of the item/ project used for planning within the portfolio/ bucket.

This is a required field

Format (YYYYMMDD)


Internal Controls

It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

PLANNED_FINNISHPlanned Finish

Tooltip

Baseline End date of the item/ project used for planning within the portfolio/ bucket.

This is a required field

Format (YYYYMMDD)


Internal Controls


It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

CATEGORYInvestment Reason

Tooltip

In Syway, Investment Reason is level-3 category of investment.

This is a required field


Internal Controls

It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

GEOGRAPHYCompany Code

Tooltip

In SyWay, this field Represents Company code; the legal entity in which the Syway Project will be executed.


Internal Controls

Refer configuration table field V_DPR_AREA- AREA for the allowed values.

It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

INITIATIVE_IDINITIATIVE ID

Tooltip

Internal ID of Initiative where Item must be linked to Initiative



Internal Controls

Dropdown list from the Initiatives maintained in CNV_1023 Portfolio Initiatives

This is an optional field

SYGBU_MHIERGBU Market Hierarchy

Tooltip

GBU Market Hierarchy is a GBU-led Market segmentation, applied to both customer and product combination.  Any level of the Global Hierarchy can be selected.

Applicable and mandatory for PPM Items linked to Buckets with function R&I or IS


Internal Controls

Values from Global Hierarchy.

Mandatory when PPM Item is linked to a bucket with Functions R&I & IS 

Preload Check to be done to confirm that this field is filled in the Data Collection Template when required

SYCORP_HIERCorporate Hierarchy

Tooltip

Corporate-led Market segmentation used for reporting. Any level of the Global Hierarchy can be selected.

Applicable to all PPM Item types but not mandatory


Internal Controls

Values from Global Hierarchy.

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYCLUSTERCluster

Tooltip

In SyWay, Used to group items together for reporting where a budget allocation is made at an aggregated level, and actuals are collected against individual related items.


Internal Controls

Selection of Items maintained in with item type Z016 - Cluster

SYPROD_HIERProduct Hierarchy

Tooltip

Reference to the product hierarchy node ( at any level) required for reporting,

Field can be maintained for PPM Items linked to Buckets with IS, R&I, Commercial and Strategy functions.


Internal Controls

Refer table HRRP_NODE- NODEVALUE where HRRP_NODE- NODETYPE = N and HRYTYPE = MD01"

SYEXPO_COExport Control

Tooltip

To identify if the PPM item is applicable for export control governance.

Mandatory for all PPM Items.


Internal Controls

This is a dropdown field from /SYQ/T_EXPORT_CNTL

This is a required field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

Z04Justification (Export Control)

Tooltip

This field captures the justification for the relevance of export control.

Not required if  Export Control is "Non Determined" option is selected.


Internal Controls

This is required field except if  SYEXPO_CO "Non Determined": Preload Check to be done to confirm that this field

SYNEED_KNOWNeed-to-know

Tooltip

This field indicates confidential projects.

Access will be restricted to named user maintained by Project owner if selection is "Yes


Internal Controls

Options are Yes or No

It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

SYPROJ_OWNProject Owner

Tooltip

This field stores the Position of the Project Owner for the PPM Item and is mandatory for all SyWay business functions. 

This is a required field

Internal Controls

From PREP report - PROJ-ZZ_POSIT

Refer configuration table field TCJ04-PS_VERNR for field validation.

Preload Check to be done to confirm that this field is filled in the Data Collection Template when required.

SYPFIN_CONProject Financial Controller

Tooltip

This field stores Position of the Project Financial Controller of a project.

This is a required field


Internal Controls

Refer configuration table field TCJ05-ASTNR for field validation.

It is a Required Field: Preload Check to be done to confirm that this field is filled in the Data Collection Template

SYST_RISK_MAGStarting Risk Magnitude

Tooltip

For the Risk managed project - this field define the risk magnitude at the start of project.

This field is required to be maintained if Scoring Methodology = Risk

Investment Reasons flagged as Risk
0011:B1 Equipment maintenance
0014:B4 Turnarounds
0019:F1 Comm. needs-bus risk rdctn
0022:A1 Health/Safety-best practice
0025:A3 Security - best practices
0028:A5 Compliance- Future regulatn
0032:F3C Climate  / Other
0033:F4A Nature / Water
0034:F4B Nature / Other
0039:R4 Equip. Maintenance/Replcmnt
0040:R5 Facilities/site maintenance
0043:R8 IAM & regulatory


Internal Controls

This field is required to be maintained if Scoring Methodology = Risk  

This is a dropdown field /SYQ/T_RISK_MAGNITUDE

Preload Check to be done to confirm that this field is filled in the Data Collection Template when required.

SYST_RISK_LIKStarting Risk Likelihood

Tooltip

For the Risk managed project - this field define the risk likelihood at the start of project.

This field is required to be maintained if Scoring Methodology = Risk


Internal Controls

This field is required to be maintained if Scoring Methodology = Risk

This is a dropdown field /SYQ/T_RISK_LKLHD

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYRE_RISK_MAGResidual Risk Magnitude

Tooltip

For the Risk managed project - this field define the risk magnitude at the start of project.

This field is required to be maintained if Scoring Methodology = Risk


Internal Controls

This field is required to be maintained if Scoring Methodology = Risk

This is a dropdown field  from /SYQ/T_RISK_MAGNITUDE

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYRE_RISK_LIKResidual Risk Likelihood

Tooltip

For the Risk managed ongoing approved project - this field defines remaining risk likelihood.

This field is required to be maintained if Scoring Methodology = Risk

Internal Controls

This field is required to be maintained if Scoring Methodology = Risk

This is a dropdown field from /SYQ/T_RISK_LKLHD

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYRE_MAN_MAGRegulatory Mandated Magnitude

Tooltip

IImpact of regulatory compliance on project delivery.

This field is required to be maintained if Scoring Methodology = Regulatory

Investment Reason flagged as Regulatory
0023:A1C Health/Safety - Compliance
0024:A2 Environment  - Compliance
0026:A3C Security - Compliance
0035:F5 SoC/SVHC replacement - ASA
0038:R3 HSE
0049:I6 Cybersecurity & Compliance


Internal Controls

This field is required to be maintained if Scoring Methodology = Regulatory

This is a dropdown field from /SYQ/T_REG_MAGNITUDE

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYRE_MAN_LIKRegulatory Mandated Likelihood

Tooltip

Probability of impact due to regulatory compliance.

This field is required to be maintained if Scoring Methodology = Regulatory


Internal Controls

This field is required to be maintained if Scoring Methodology = Regulatory

This is a dropdown field from /SYQ/T_REG_LKLHD

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYRE_MAN_TIMRegulatory Mandated Time Horizon (to start project)

Tooltip

Regulatory defined deadline by which a project must commence.

This field is required to be maintained if Scoring Methodology = Regulatory


Internal Controls

This field is required to be maintained if Scoring Methodology = Regulatory

This is a dropdown field from /SYQ/T_REG_TIME_HORIZON

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYCAP_DATCapitalization Date

Tooltip

Stores the capitalization date for the purpose of "Depreciation forecast".

This date is mandatory for the Capital Projects Item types.  
Z001:Industrial with Qualification
Z002:Industrial w/out Qualification
Z003:Industrial 2 Phases
Z008:IT Full Lifecycle Project
Z009:IT Small Project
Z011:Turnaround Projects

Format (YYYYMMDD)


Internal Controls

This date is mandatory for the Capital Projects Item types.  Item Types are  Z001,Z002, Z003, Z008, Z009, Z011

Preload Check to be done to confirm that this field is filled the Data Collection Template when required

SYPRCTRProfit Center

Tooltip

Profit Centre represents the GBU/Plant where the project is performed., Profit centre on PPM item will be validated with the PC on the Parent Bucket to check they belong to the same group.  This will ensure PPM items are created under correct GBU bucket. If plant is maintained then Profit Center is derived from it.

Required if the Plant field is not filled.


Internal Controls

Refer master table field CEPC-PRCTR for Profit center list. the Data Collection Template,  

It is required only if Plant is not filled: Preload Check to be done to confirm that this field is filled, and is aligned with the PC on the Parent Bucket, first character of the Profit centers must match

SYBUDG_PROBudget Provision

Tooltip

Used to group those PPM Items where the budget is drawn from the Budget provision Item.


Internal Controls

Selection of Items maintained in with item type Z015 - Budget Provision

SYOPP_IDOpportunity ID

Tooltip

Stores the CRM opportunity ID where applicable.

This is an optional field.

SYARCHETYArchetype

Tooltip

This field represents the classification of the R&I projects as different archetypes.

Not applicable for Items linked to Buckets with IS, IT & Facility/ Others functions. 


Internal Controls

This is a dropdown field from /SYQ/T_ARCHETYPE

Preload Check to be done to confirm that this field is filled in the Data Collection Template when required.

SYMUST_JUSMust Do Justification

Tooltip

This field provides input to the ranking of items in the prioritization dashboard and is relevant across all PPM item types.


Internal Controls

This is a dropdown field from /SYQ/T_MUST_DO

This is a required field


SYWERKSPlant

Tooltip

Plant represent a site of the PPM Item.

Plant is maintained when available.

Plants are restricted by Company Code


Internal Control

Preload validation that plant exist, T001W and is maintained for the Company Code 

This is an optional field.

SYIDEAIDIdea ID

Tooltip

Field to store the Idea number where this is known.

This is an optional field for migration

SYSUBSIDYSubsidy

Tooltip

Use this field if the project is eligible for government or institutional subsidies.

This is an optional field for migration


Internal Control

This is a true / false field

Z03Subsidy Relevance

Tooltip

This field is used to provide a concise description of the Subsidy Relevance.  (This is a long text field)

Required If Subsidy field is selected.


Internal Control

Required If Subsidy field is selected.

Z01Key Assumptions

Tooltip

This field is used to provide key Assumptions related to projects.  (This is a long text field)

Conditional for Items where assumptions are to be maintained,

This is an optional field for migration

Z02Variations

Tooltip

This field is used to provide details about key project variations.  (This is a long text field)

Conditional for Items where assumptions are to be maintained,

This is an optional field for migration

Z05Other Information

Tooltip

This field is used to provide additional details about project.  (This is a long text field)

This is an optional field for migration

Z08Lessons Learnt

Tooltip

Long-text description, this field is used to record the project insights and key takeaways of a project

This is an optional field for migration

ACT_DPCPTActive Decision Point

Tooltip

Indicates the currently active Decision Point (Stage Gate) for the item.

Relevant for the following item types 

Z001      Industrial with Qualification

Z002      Industrial w/out Qualification

Z004      New Product Introduction

Z005      Product & Process Improvement

Z008      IT Full Lifecycle Project

Z017      New Application Development

To be maintained when item is not in initial phase


Internal Control

Drop down field from /RPM/ITEM_PHASE based on selected ITEM_TYPE


Decision Point.   The list of decision points for an item is based on configuration table /RPM/ITEM_PHASE-PHASE_ID for ITEM_TYPE, when item is added to this DCT the full list of decision points for the item type must be added to the DCT.

Field NameField DescriptionRule
SNROItem Serial Number

Unique Identifier Item serial numbers

It is a dropdown of the Item numbers maintained in the main DCT

DECISION_IDDecision Point ID

Once the User selects the Item number the full list of Decision points relevant to the Item type is to be displayed.

System generated Parent ID of the Decision Point

This is a display only field

NAMEDecision Point Description

Name of the decision point, part of the customisation and can't be changed.

This is a display only field

PLAN_STARTDecision Point Planned Start DateThis field stores the plan start date of a decision point for the items where there is SG tracking required
PLAN_FINISHDecision Point Planned End DateThis field stores the plan finish date of a decision point where SG tacking is required
ACTUAL_STARTDecision Point Actual Start DateThis field stores the actual start date of a decision point derived from the initiation date of respective stage gate approval.
ACTUAL_FINISHDecision Point Actual End DateThis field stores the actual finish date of a decision point derived from the approved date of respective stage gate approval.
SYVAR_REFVariation ReferenceThis field stores the identifier and short description of Variation required to variation budget approval

CR359 - Custom Field name changes END

Authorization - For "Need-to-know" projects, named users will be added manually.

Field NameField DescriptionRule
SNROItem Serial Number

Unique Identifier Item serial numbers

It is a dropdown of the Item numbers maintained in the main DCT and marked as Need to Know.


USER_IDSAP User Name

Named user who should have read access to the Need to Know Item

In conjunction with DCT business user will be provided with Person Responsible / Applicant list for reference.

Extraction Dependencies

Item #Step DescriptionTeam Responsible


Transformation

The Target fields are mapped to the applicable Legacy field that will be its source,. This identifies the transformation activity required to allow Syniti Migrate
to make the data Target ready:

  1. Perform value mapping and data transformation rules.

    1. Legacy values are mapped to the to-be values (this could include a default value)

    2. Values are transformed according to the rules defined in Syniti Migrate

  2. Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation

Transformation Run Sheet

Item #

Step Description

Team Responsible

1

Obtain DCT Sign-off from Business

Data Team

2

Execute and Load and perform Transformation 

Data Team

3

Monitor the transformation progress and ensure performance and completion is within allowed timeframe

Data team

4

Review and Validate Error and Preload Reports

Data Team

5

Generate data load count.

Data team

6

Generate Load Files

Data Team

7

Log errors as defects, if any and address resolutions. Close defects.

Data team

8

Re-transform and re-validate the Pre-load reports if necessary.

Data team

9

Validate the transformed file as part of pre-load validation, raise data defects or provide the pre-load sign-off.

Business

10

Analyze and resolve any pre-load defects logged by business.

Data team

11

Repeat steps 7 to 10 if necessary

Data team

12

Proceed to pre-load validations

Data team


Transformation Rules

CR359 - Custom Field name changes

Rule #

Source system

Source Table

Source Field

Source Description

Target System

Target Table

Target Field

Target Description

Transformation Logic

1

DCT


PARENT_ID

Parent Bucket ID

S/4 Hana

/RPM/ITEM_D

PARENT_ID

Parent Bucket ID

Manually copy from Non ECC source

2





S/4 Hana

/RPM/ITEM_D

PORTFOLIO_ID

Portfolio ID

Global Default "SYENSQO"

3

WP2




S/4 Hana

/RPM/ITEM_D

ITEM_TYPE

Type

Apply first successful rule


If PROJ-PSPID start with RR* then capture in DCT.


If any WBS elements  PRPS-USER0 starts with IT then Z009


IF PROJ-ZZ_IZWEK = B4 Then Z011


IF PROJ-ZZ_IZWEK = B1, H1, or H2 Then Z013


IF PROJ-PSPID 4&5 Character of Project ID is /J: Then Z001


If PROJ-PSPID 4&5 Character of Project ID is /M: then Z002


f PROJ-PSPID 4&5 Character of Project ID is /C: then Z003


If no WBS elements is Capital, PRPS-IMPRF="" then Item type PRPS-Z010


4

PF2

PROJ



S/4 Hana

/RPM/ITEM_D

ITEM_TYPE

Type

Apply first successful rule only


If PROJ-PSPID start with R-then capture in DCT.


Investment Reason = H0 then Z009

IF PROJ-ZZ_IZWEK = B4 Then Z011

IF PROJ-ZZ_IZWEK = B1, B5, H1, or H2 Then Z013

IF PROJ-PSPID 4&5 Character of Project ID is /J: Then Z001

If PROJ-PSPID 4&5 Character of Project ID is /M: then Z002

f PROJ-PSPID 4&5 Character of Project ID is /C: then Z003


If no WBS elements is Capital, PRPS-IMPRF="" then Item type PRPS-Z010

5

DCT


ITEM_TYPE

Type

S/4 Hana

/RPM/ITEM_D

ITEM_TYPE

Type

Manually copy from Non ECC source

6

WP2/PF2

PROJ

POST1

Project Description

S/4 Hana

CGPL_TEXT

TEXT1

Name

Copy source to target

7

DCT


TEXT1

Name

S/4 Hana

CGPL_TEXT

TEXT1

Name

Manually copy from Non ECC source

8

WP2/PF2

STXL

LTEXT

Long Description

S/4 Hana

STXL

LTEXT

Description

Copy source to target

9

DCT


LTEXT

Item Description

S/4 Hana

STXL

LTEXT

Description

Manually copy from Non ECC source

10

DCT


STATUS

Item Status

S/4 Hana

/RPM/ITEM_D

STATUS

Item Status

Manually copy from Non ECC source

11

WP2/PF2

PROJ

PLFAZ

Project planned start date

S/4 Hana

/RPM/ITEM_D

PLANNED_START

Planned Start

Copy from source, format YYYYMMDD

12

DCT


PLANNED_START

Planned Start

S/4 Hana

/RPM/ITEM_D

PLANNED_START

Planned Start

Manually copy from Non ECC source

13

WP2/PF2

PROJ

PLSEZ

Project planned finish date

S/4 Hana

/RPM/ITEM_D

PLANNED_FINISH

Planned Finish

Copy from source, format YYYYMMDD

14

DCT


PLANNED_FINISH

Planned Finish

S/4 Hana

/RPM/ITEM_D

PLANNED_FINISH

Planned Finish

Manually copy from Non ECC source

15

DCT


SYINVST_REASON

Investment Reason

S/4 Hana

/RPM/ITEM_D

SYINVST_REASON

Investment Reason

Manually copy from Non ECC source

16





S/4 Hana

/RPM/ITEM_D

SYSUB_BUS_DRI

Sub Business Driver

Value Mapping: Investment Reason

Based on the SYINVST_REASON field

17





S/4 Hana

/RPM/ITEM_D

SYMAIN_BUS_DRI

Main Business Driver

Value Mapping: Investment Reason

Based on theSYINVST_REASON field

18





S/4 Hana

/RPM/ITEM_D

SYINVST_CAT 

Investment Category

Value Mapping: Investment Reason

Based on theSYINVST_REASON field

19

WP2/PF2

PROJ

VBUKR

Company code

S/4 Hana

/RPM/ITEM_D

GEOGRAPHY

Company Code

Value Mapping: Old to New Company Code

20

DCT


GEOGRAPHY

Company code

S/4 Hana

/RPM/ITEM_D

GEOGRAPHY

Company Code

Manually copy from Non ECC source

21

WP2/PF2

PROJ

PWHIE

WBS currency

S/4 Hana

/RPM/ITEM_D

CURRENCY

CURRENCY

Copy from Source

22

DCT


Currency

Currency

S/4 Hana

/RPM/ITEM_D

CURRENCY

CURRENCY

If Legacy Project ID field is empty then

Value Mapping: Currency From Company Code
Company Code Currency from T001-WAERS where BUKRS = Target Geography

23





S/4 Hana

/RPM/ITEM_D

UNIT

Unit

Default to "TAG"(Day)

24





S/4 Hana

/RPM/ITEM_D

CAP_PERIODTYPE

Capacity Period Breakdown

Default to "12"(Annually)

25





S/4 Hana

/RPM/ITEM_D

PERIODTYPE

Fin Period Breakdown

Default to "12"(Annually)

26

DCT


INITIATIVE_ID

INITIATIVE ID

S/4 Hana

/RPM/ITEM_D

INITIATIVE_ID

INITIATIVE ID

Manually copy from Non ECC source

28

DCT


SYGBU_MHIER

GBU Market Hierarchy

S/4 Hana

/RPM/ITEM_D

SYGBU_MHIER

GBU Market Hierarchy

Manually copy from Non ECC source

30

DCT


SYCORP_HIER

Corporate Hierarchy

S/4 Hana

/RPM/ITEM_D

SYCORP_HIER

Corporate Hierarchy

Manually copy from Non ECC source

31

DCT


SYCLUSTER

Cluster

S/4 Hana

/RPM/ITEM_D

SYCLUSTER

Cluster

Manually copy from Non ECC source

32

DCT


SYPROD_HIER

Product Hierarchy

S/4 Hana

/RPM/ITEM_D

SYPROD_HIER

Product Hierarchy

Manually copy from Non ECC source

33

DCT


SYEXPO_CO

Export control

S/4 Hana

/RPM/ITEM_D

SYEXPO_CO

Export Control

Manually copy from Non ECC source

34

DCT


Justification

Justification (Export Control)

S/4 Hana

STXL

Z04

Justification (Export Control)

Manually copy from Non ECC source

35

DCT


SYNEED_KNOW

Need-to-know

S/4 Hana

/RPM/ITEM_D

SYNEED_KNOW

Need-to-know

Manually copy from Non ECC source

36

WP2/PF2

PROJ

ZZ_POSIT

Position of the person responsible

S/4 Hana

/RPM/ITEM_D

SYPROJ_OWN

Project Owner

Value Mapping: Old Position ID  to New Position ID

37

DCT


SYPROJ_OWN

Project Owner

S/4 Hana

/RPM/ITEM_D

SYPROJ_OWN

Project Owner

Manually copy from Non ECC source

39

DCT


SYPFIN_CON

Project Financial Controller Position ID

S/4 Hana

/RPM/ITEM_D

SYPFIN_CON

Project Financial Controller Position ID

Manually copy from Non ECC source

41





S/4 Hana

/RPM/ITEM_D

SYSCOR_METH

Scoring Methodology

Value Mapping: Investment Reason

Based on the SYINVST_REASON field

42

DCT


SYST_RISK_MAG

Starting risk Magnitude

S/4 Hana

/RPM/ITEM_D

SYST_RISK_MAG

Starting risk Magnitude

Manually copy from Non ECC source

43

DCT


SYST_RISK_LIK

Starting risk Likelihood

S/4 Hana

/RPM/ITEM_D

SYST_RISK_LIK

Starting risk Likelihood

Manually copy from Non ECC source

44

DCT


SYRE_RISK_MAG

Residual risk Magnitude

S/4 Hana

/RPM/ITEM_D

SYRE_RISK_MAG

Residual risk Magnitude

Manually copy from Non ECC source

45

DCT


SYRE_RISK_LIK

Residual risk Likelihood

S/4 Hana

/RPM/ITEM_D

SYRE_RISK_LIK

Residual risk Likelihood

Manually copy from Non ECC source

46

DCT


SYRE_MAN_MAG

Regulatory Mandated Magnitude

S/4 Hana

/RPM/ITEM_D

SYRE_MAN_MAG

Regulatory Mandated Magnitude

Manually copy from Non ECC source

47

DCT


SYRE_MAN_LIK

Regulatory Mandated Likelihood

S/4 Hana

/RPM/ITEM_D

SYRE_MAN_LIK

Regulatory Mandated Likelihood

Manually copy from Non ECC source

48

DCT


SYRE_MAN_TIM

Regulatory Mandated Time Horizon (to start project)

S/4 Hana

/RPM/ITEM_D

SYRE_MAN_TIM

Regulatory Mandated Time Horizon (to start project)

Manually copy from Non ECC source

49

DCT


SYCAP_DAT

Capitalization Date

S/4 Hana

/RPM/ITEM_D

SYCAP_DAT

Capitalization Date

Manually copy from Non ECC source

50

WP2/PF2

PROJ

PRCTR

Profit Center

S/4 Hana

/RPM/ITEM_D

SYPRCTR

Profit Centre

Value Mapping:  Profit Center Old to New

51

DCT


SYPRCTR

Profit Centre

S/4 Hana

/RPM/ITEM_D

SYPRCTR

Profit Centre

Manually copy from Non ECC source

54

DCT


SYBUDG_PRO

Budget Provision

S/4 Hana

/RPM/ITEM_D

SYBUDG_PRO

Budget Provision

Manually copy from Non ECC source

55

DCT


SYOPP_ID

Opportunity ID

S/4 Hana

/RPM/ITEM_D

SYOPP_ID

Opportunity ID

Manually copy from Non ECC source

56

DCT


SYARCHETY

Archetype

S/4 Hana

/RPM/ITEM_D

SYARCHETY

Archetype

Manually copy from Non ECC source

57

DCT


SYMUST_JUS

Must Do Justification

S/4 Hana

/RPM/ITEM_D

SYMUST_JUS

Must Do Justification

Manually copy from Non ECC source

58

WP2/PF2

PROJ

PSPID

ID

S/4 Hana

/RPM/ITEM_D

SYLEG_PRJID

Legacy Project ID (For existing records this is the key for related DCT values) For additional Items not from source this will be empty.

Copy From Source


DCT


SNRO

Serial Number

S/4 Hana

/RPM/ITEM_D

SYLEG_PRJID

Legacy Project ID (For existing records this is the key for related DCT values) For additional Items not from source this will be empty.

Manually copy From Non ECC Source

59

WP2/PF2

PROJ

WERKS

Plant 

S/4 Hana

/RPM/ITEM_D

SYWERKS

Plant

Value Mapping: Old Plant to New

60

DCT


SYWERKS

Plant

S/4 Hana

/RPM/ITEM_D

SYWERKS

Plant

Manually copy from Non ECC source

61

DCT


SYIDEAID

Idea ID

S/4 Hana

/RPM/ITEM_D

SYIDEAID

Idea ID

Manually copy from Non ECC source

62

DCT


SYSUBSIDY

Subsidy

S/4 Hana

/RPM/ITEM_D

SYSUBSIDY

Subsidy

Manually copy from Non ECC source

63

DCT


Sub_Relevance

Subsidy Relevance

S/4 Hana

STXL

Z03

Subsidy Relevance

Manually copy from Non ECC source

64

DCT


Key_Assump

Key Assumptions

S/4 Hana

STXL

Z01

Key Assumptions

Manually copy from Non ECC source

65

DCT


Variations

Variations

S/4 Hana

STXL

Z02

Variations

Manually copy from Non ECC source

66

DCT


Other

Other Information

S/4 Hana

STXL

Z05

Other Information

Manually copy from Non ECC source


DCT


Lessons

Lessons Learnt

S/4 Hana

STXL

Z08

Lessons Learnt

Manually copy from Non ECC source

List of Custom Target Reports for this object is maintained here: Conversion Specification - Custom Reports Register.

The Standard template for the upload of Item that can be used for the upload of Items, this includes ability to upload of custom fields, into S/4 Hana:  Item Load File.xlsx - Google Sheets


In addition to the fields mapped to the target fields the following is required for the automatic creation of the PS projects if the standard upload program is used.


Rule #

Source system

Source Table

Source Field

Source Description

Target System

Target Table

Target Field

Target Description

Transformation Logic

66





S/4 Hana

Upload program 

CREATE_CPROJECT

Create Project

If the Legacy ID exists or if Item Type is Capital Lease, Direct Asset Purchase or Capital Spares,  then field is  X else it remains blank

67

S/4




S/4 Hana

Upload program 

CPRO_TEMPLATE

Project Template to be used

If CREATE_CPROJECT is active then field must be set.

Select PS_TEMPLATE from  /RPM/PSPTIT_MAP using ITEM_TYPE

68

S/4




S/4 Hana

Upload program 

PS_LOGSYSTEM

Logical System

If CREATE_CPROJECT is active then field must be set.

Select OBL_TYPE from  /RPM/PSPTIT_MAP using ITEM_TYPE


Decision Point

For items types with multiple decision points the active decision point must be updated as part of the item create.   If using the standard upload this is done using the Item Decision Point work sheet.

If using the standard upload program Decision Point sheet the active decision point can only be set by changing the statuses of the preceding decision points to end state and the active decision point to start state. 

In addition users may have maintained Decision point dates in the DCT, these updated dates are to be included in the requirement

The expectation is that there will be multiple records for each loaded item.

/RPM/ITEM_PHASE-PHASE_ID for ITEM_TYPE.

Determination of Preceding decision point

Preceding decision point determined /RPM/ITEM_PHASE-PHASE_ID for ITEM_TYPE.

Determination Decision Point Status

Decision point start status /RPM/DP_STATUS-START_STATUS = X for ITEM_TYPE and PHASE_ID
Decision point start status /RPM/DP_STATUS-END_STATUS = X for ITEM_TYPE and PHASE_ID 


Rule #

Source system

Source Table

Source Field

Source Description

Target System

Target Table

Target Field

Target Description

Transformation Logic

1





S/4 Hana

/RPM/DECISION 

ITEM

Item ID


2





S/4 Hana

/RPM/DECISION

DECISION_ID

Decision Point ID

The List of decision points for each item is based on the item type as per 

3





S/4 Hana

/RPM/DECISION

NAME

Decision Point Name

Decision Point Name from RPM/PHASE_T using ITEM_TYPE and DECISION_ID

4





S/4 Hana

/RPM/DECISION

STATUS

Decision Point Status

Decision point start status for preceding decision points /RPM/DP_STATUS-END_STATUS = X for ITEM_TYPE and PHASE_ID


Decision point start status for active decision point /RPM/DP_STATUS-START_STATUS = X for ITEM_TYPE and PHASE_ID 

5

DCT

Decision Point

PLAN_START

Decision Point Planned Start Date

S/4 Hana

/RPM/DECISION

PLAN_START

Decision Point Planned Start Date

Manually copy from Non ECC source

6

DCT

Decision Point

PLAN_FINISH

Decision Point Planned End Date

S/4 Hana

/RPM/DECISION

PLAN_FINISH

Decision Point Planned End Date

Manually copy from Non ECC source

7

DCT

Decision Point

ACTUAL_START

Decision Point Actual Start Date

S/4 Hana

/RPM/DECISION

ACTUAL_START

Decision Point Actual Start Date

Manually copy from Non ECC source

8

DCT

Decision Point

ACTUAL_FINISH

Decision Point Actual End Date

S/4 Hana

/RPM/DECISION

ACTUAL_FINISH

Decision Point Actual End Date

Manually copy from Non ECC source

9

DCT

Decision Point

SYVAR_REF

Variation Reference

S/4 Hana

/RPM/DECISION

SYVAR_REF

Variation Reference

Manually copy from Non ECC source

CR359 - Custom Field name changes END


Authorization

For items with Need to know flag set the authorization to display the item is restricted to named users only.   If using the standard upload this is done using the Item Authorization work sheet.

Rule #

Source system

Source Table

Source Field

Source Description

Target System

Target Table

Target Field

Target Description

Transformation Logic

1

DCT

Authorization

SNRO

Item Serial Number

S/4 Hana

ACO_USER

ITEM_ID

Object ID

Manually copy from Non ECC source

2





S/4 Hana

ACO_USER

ACTIVITY

Activity

Default to activity "READ"

3

DCT

Authorization

USER_ID

SAP User Name

S/4 Hana

ACO_USER

USER

User ID

Manually copy from Non ECC source

Transformation Mapping

Mapping Table Name

Mapping Table Description

Company Code

Value Mapping: Old to New Company Code

T001

Value Mapping: Currency From Company Code

HRP1000

Value Mapping: Position Name from Position

Value Mapping: Old Position ID  to New Position ID

Plant

Value Mapping: Old Plant to New

Profit Center

Value Mapping:  Profit Center Old to New

Investment Reason

Value Mapping:  Investment Reason to Other fields.

Investment Reason, Main Business Driver, Sub Business Driver, Investment Category, Scoring Methodology

Transformation Dependencies

List the steps that need to occur before transformation can commence

Item #

Step Description

Team Responsible

1

Ensure all the fields that require value mapping, as stipulated. Mapping tables, have the correct values mapped and imported into tool.

Data Team 


Pre-Load Validation

Project Team

Completeness

TaskAction
Verify Record CountSyWay I2M Data Team to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets.

Accuracy

TaskAction

Conversion Accuracy

SyWay I2M Data Team to verify that all fields below meet pass the checks:

  1. Mandatory Fields
  2. Field and Value Mapping Correctness
  3. Null Checks
  4. Text Length Checks

Review Error Reports

Review and correct the errors.  Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source (DCT) data.


Business

Completeness

TaskAction

Verify Record Count

Business Data Owner/s to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets.


Accuracy

TaskAction

Conversion Accuracy

Business Data Owner/s to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules (and signed-off DCT data).


Load

The load process includes:

  1. Execute the automated data load into target system using load tool or product the load file if the load must be done manually
  2. Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation

Load Run Sheet

Item #Step DescriptionTeam Responsible
1Load using transaction RPM_DX_ITEMSyWay Data Team
2Load 3 records for < > to validate if data is loaded successfully without errorsSyWay Data Team
3Load 3 records for < > to validate if data is loaded successfully without errorsSyWay Data Team
4Proceed with full load if steps 2 and 3 are validatedSyWay Data Team
5Validate few records loaded by accessing Portfolio Item AppSyWay Data Team
6Validate few records loaded by accessing PS Project AppSyWay Data Team
7

 Generate post load report if step 5 is validated

SyWay Data Team
8

Business to validate the post load files as part of post-load validation, raise data defects or provide the post-load sign-off.

Business


Load Phase and Dependencies

Configuration

Key Configuration requirement

Item #Configuration Item
1Override Default Global Settings  (Master Switches  0002   Switched off - Item will have manual ID)
2Define Currency Units
3Item Types
4Item Type Status
5Configure Fields for Mass Import
6Category
7Sub-Category
8Technology Type
9Group
10Area
11Object Link
12Plant
13DFM Object Links
14Map Item Types to PS Project

Conversion Objects

Object #Preceding Object Conversion Approach
1113Portfolio Bucket Hierarchy

1073

Profit Centre

1019

Template Projects

Error Handling

Error TypeError DescriptionAction Taken

Invalid Data

Invalid Portfolio

Validate DCT content

Invalid Data

Invalid Bucket ID (Parent ID does not exist)

Validate DCT content

Invalid DataInvalid Item TypeValidate Transformation rules and DCT values
Invalid DataInvalid datesValidate format of the date fields.
Invalid DataMore that one Item per GBU/Company Code/Plant for Capital Lease Item TypeRemove Duplicate values from DCT
Invalid DataMore that one Item per GBU/Company Code/Plant for Direct Asset Purchase Item TypeRemove Duplicate values from DCT
Invalid DataMore that one Item per GBU/Company Code/Plant for Capital Spares Item TypeRemove Duplicate values from DCT


Post-Load Validation

Project Team

Completeness

TaskAction

Verify Count

SyWay I2M Data Team to verify the record count created in target S/4 HANA by accessing post load reports or standard reports from S/4 HANA.

Verify Logs

Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.).


Accuracy

TaskAction

Conversion Accuracy

Verify that the Portfolio Item in target S/4 HANA were loaded correctly via Standard Portfolio Item display and table /RPM/ITEM_D

Conversion Accuracy

Verify that the Project Definition in target were created correctly as per project template and that the project status has been set to released using transaction CN41n

Conversion Accuracy

Verify that the WBS Structure  in target were created correctly as per project template WBS status has been set to released using transaction CN41n


Business

Completeness

TaskAction
Verify Count

Extract Item details from Item App in S/4 Hana

Verify Count

Extract Project Definitions from Project Definitions App in S/4 Hana,  to be same as Item count


Accuracy

TaskAction
Verify AccuracyExtract Item details from Item App in S/4 Hana and compare

Extract Project details from Project in S/4 Hana and compare to expected results


Key Assumptions

  • Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
  • Portfolio Item is in scope based on data design and any exception requested by business.
  • Item types to be maintained by business where it cannot be determined based on transformation rules, this includes R&I where split between the new item types not possible.


See also