> Planned delivery time from MRP2 : this is the initial value taken into account to determine the "Procurement LT for P&I". It takes the Pld Delivery time from SAP MRP2 view. For more information about MRP2 Pld Delivery time, please refer to: SAP Purchase LT


> Planned Delivery time from PIR: If available, this value becomes prioritary to the one above from MRP2. This LT coming from the Purchase Info Record. For more information about PIR Pld Delivery time, please refer to: SAP Purchase LT


> Proc LT override: user can override the value (Optional, not mandatory).

...