General Description | |
|---|---|
The number and percentage of orders and lines with acknowledgement for previous month and it split as | |
critical (inside the total orders acknowledged) and purchase orders |
from VIP suppliers (inside the total orders acknowledged). |
Lead time details results can be analyzed by:
|
Date Reference: |
Schedule Line Delivery Date |
Refresh frequency:
Monthly
|
KPI Name | Calculation |
#Line Flagged for Acknow. | Total number of PO Lines Acknowledgement Flag |
#Acknow. Collected | Total number of PO Acknowledgement Flag |
%Acknow. |
Target:
100% for Critical and VIP PO
Number of Order Acknowledgement with Date of Acknowledgement < PO Line Schedule Date |
#Critical
# Critical | # of PO critical with an order acknowledgementDomain = Pack (2), Raw Mat (6) or; |
% Acknow. | Number of PO critical with with Acknowledgement |
#VIP
# VIP | # of VIP PO with an order acknowledgementvendor who had been flag as VIP in vendor master data. |
% Acknow.
|
Number of VIP PO with Acknowledgement |
| Source Information: BW (WP1 & PF1) | |
|---|---|
Core Query: | BW_QRY_MV_PROVG_0003 |
QV Query: | QVSBS_BW_QRY_MV_PROVG_0002 |
BW Filters | Purchasing document type = NB |
PO Requirement Urgency <> (98) RemediationOrder Acknowledgement Requirement = X (Yes) |
Specific Dimensions |
|---|
Dimension name
Comments
PO Item Created By | |
Flag Capex | For CAPEX (IM), the Project type assigned to the relevant WBS element is: II (Investment) type in WP1. |
PO Items Critical | Y/N
|
VIP Supplier | Y/N (Vendor Attribute = VIP Vendor => Y=VIP ; N=#) |
Internal Suppliers | Y/N (Vendor Attribute = Class => Y=G ; N=the rest) |
Purchasing Group | |
Purchasing Organization |