Versions Compared
Key
- This line was added.
- This line was removed.
- Formatting was changed.
Status colour Blue title Step 1
Use transaction code : KSU7
| Info | |
|---|---|
|
Image Modified
Status colour Blue title Step 2
Enter the cycle code (=PPPPBU => PPPP is the plant code)
and the starting date (1st day of the coming year) and Image Modified
Image Modified
Status colour Blue title Step 3
- Enter the validity date (to last day of the year)
- Enter the description of the cycle (PPPP Plant name - Budget)
- Check the Indicator "Iterative"
- Check the Field Groups "Object Currency"
Image Modified
Status colour Blue title Step 4
Click Image Modified
Image Modified
Status colour Blue title Step 5
Enter the segment code (cost center code) and description (cost center code & name)
Image Modified
Status colour Blue title Step 6
Update the tab "Segment Header" :
- Enter the allocation structure or the assessment cost element if there is no allocation structure available
- Sender values:
- Sender rule = Posted amounts
- Share in % = 100 %
- Receiver tracing factor :
- Fixed percentage
Image Modified
Status colour Blue title Step 7
Go to the tab "Senders/Receivers"
Image Modified
Status colour Blue title Step 8
Update the tab "Senders/Receivers"
- Enter a cost center or a group of cost center (group in the standard hierarchy)
- Enter a group of cost element ZRCS-CNP (for fixed costs) or ZRCS-AMO (for depreciation). It is not necessary when an allocation structure is used
- Enter the receiving cost center or group of cost centers (PPPP-1)
Image Modified
Status colour Blue title Step 9
Go to the tab "Sender Values"
Version = 0
Image Modified
Status colour Blue title Step 10
Go to the tab "Receiver Tracing Factors"
=> Enter the allocation key per receiving cost center
| Info |
|---|
Total = 100 |
Image Modified
Status colour Blue title Step 11
Create a new segment by clicking Image Modified
Status colour Blue title Step 12
Save Image Modified
| Viewtracker | ||
|---|---|---|
|