Status colour Blue title Step 2
On the Execute Actual Distribution screen, make the following entries:
| Field name | User action and values | Comment | |
|---|---|---|---|
| 0 | Controlling Area (dialog box) | Enter controlling area | Only needed if dialog box displays. |
| 1 |
| Periods | Enter one number in each field, for example, from 1 to 1 | Jan =1, Dec=12 | |
| 2 | Year | Current year | |
| 3 | Test run | Use test run until the run is error-free | |
| 4 | Detailed lists | x | |
| 5 | Cycle | Enter the cycle code => the Start Date comes when you click Enter | You can execute several cycles in one execution |
| Expand | ||||||
|---|---|---|---|---|---|---|
| ||||||
|
| Viewtracker |
|---|
Status colour Blue title Step 6
Check that all cost centers are balanced
- Display cost centers report (for instance S_ALR_87013611)
- Enter the group of cost centers that must be balanced
- Execute
|