1. Objective and Scope
1.1. Objective of this Operation
To The objective of this procedure is to transfer the costs linked to the fine limestone to pdr XR32410900.
1.2. Scope
This LOP procedure is applied for the following companies:
- 0270: SOLVAY CHIMIC ITALIA
2. Definitions
See Finance Glossary:
.
3. Tasks description
3.1. Periodicity
This procedure should be performed by 3SFinance Operations, every month, before product costing run.
3.2. Responsibilities
Local responsibilitiesController responsibilities:
- Only check and assistance if need.
SBS Finance Operations' responsibilities: RtR
- Finance Operationswill perform all the operations detailed.
3.3. Define a title I transfer the costs linked to the fine limestone
During the closure before the Production Costing it's necessary to transfer costs linked to the fine limestone to Pdr XR32410900.
3.3.1.
Transaction GR55 Report Group ZIZZI run the SAP transaction KSB1
Launch transaction GR55 Report Group ZIZZ for the Profit Center D7250 with account value 6090300400
Note the total amount that you find to perform the follow document, for example in December 2010 the amount was 60.521,85 €
Attention: if
KSB1 with cost center XR84300025
Once inside insert field Material and filter material 40275
Transfer this amount to cost center XR32410900
| Warning | ||
|---|---|---|
| ||
If the amount is up to 150.000 € stop performing the |
procedure and contact |
Controller. |
3.3.2.
TransactionI run the SAP transaction FB01
Perform transaction FB01 putting the amount noted above as:
3.3.3.
CheckI check that the actual amount is zero
Launch again transaction GR55 Report Group ZIZZ KSB1 the same as in point 23.13.1. and check that the actual amount is zero.
3.4. Main Contacts
Paolo Pianezzoli
End of document.