Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

 

Status
colourBlue
titleStep 1
 

Enter Transaction CJ01.
  CJ01

Image Modified




Status
colourBlue
titleStep 2
 

Insert the project definition and choose the project profile according to the plant of the company. This information will be is available in the template received.

 

Info

The Project Profile should be always “ XXX_project R&D (BA XXXX)”.

 

 

 

 

Image Removed

 

Image Added



Image Added




Status
colourBlue
titleStep 3

In the next screen:

  • Include the Project Name send in the template 
  • Check if the Business Area is correctly filled.

 

 

 





Image Modified




Status
colourBlue
titleStep 4

 

Enter the Control tab in tab Control order to confirm that the object class is “Overhead”. 

  • Click on the WBS overview Image Added


Image Modified




Status
colourBlue
titleStep 5

  • Click on the WBS overview.
    Fulfill the level 1 1of the WBS by inserting in the WBS element and description accordingly with template received.

 

 
  • Description as per the received template.

Image Modified




Status
colourBlue
titleStep 6
 

  • Flag the "Acct" Column.
  • Column ''Typ'' is set by default to R1. Change it only if mention it's mentioned in the template file.



Image Added




Status
colourBlue
titleStep 7

  • Go to Details menu and enter in WBS element customer fields.

Image Added




Status
colourBlue
titleStep 8

Fill in the following fields, as per template:

  • Proj.

 

 

 

  • type
  • GBU
  • Sub-GBU
  • Product
  • Proj. Leader
  • Proj. Manager
  • Tax Cred. Local


Image Added


Note that the selection of the correct Project Type is very important when creating the WBS element, as it will have impact in some reports, namely CosTa and Capex ones.

In order to be considered Capex (both for CosTa and Capex Dashboard) the Project Type must be the one below:

Image Added




Status
colourBlue
titleStep 9

Click on Image Added, in order to define the settlement rule of the WBS.

Image Added




Status
colourBlue
titleStep 10

Click twice on the first line.



Image Added




Status
colourBlue
titleStep 11

Fill in the following fields:

  • Cost Center – (received in the template)
  • Number – Usually 1, this field should be adapt according to the number of receivers
  • Settlement type – PER
  • Percent – Usually 100% it’s variable according to the number of receivers
  • Valid from – month and year of the creation of the WBS

In the end go back by pressingImage Added until you arrive to the WBS first screen.


Image Added



Status
colourBlue
titleStep 12

Important fields of the master data that will have an impact for CosTa Dashboards. NOTE: The "responsible CC" is not mandatory for Projects or WBS levels WITHOUT a flag in the operative indicator of "Account Assignment Element".

Image AddedImage Removed




Status
colourBlue
titleStep 7

 

 

 

13

In order to release the WBS,  you have to go to Edit > Status > Release.

Check if the status is now REL and SETC.



Image Added




Status
colourBlue
titleStep 14

The WBS is now ready to be savedImage Added