Tasks to be completed when documenting an operation (from creation to publication)

 1. Enter the Title of the operation / page

2. Add the following Labels

    • Scope of applicability: ww, country_accounting 

    • Country or group of countries (if applicable): belux, china, france, italy, lam, nam, uk_ie, bulgaria, dach, netherlands, iberia, poland, latvia, australia, india, japan, south_korea, thailand, singapore, new_zealand, emea_transversal, apac_transversal

Unit and Domain according to the List of labels to be used in the Finance Service Line space

E.g. 1: WW Operation in Financial Accounting under domain "Central Finance Processes & Compliance":
Labels to be used: ww, financial_accounting, central_fin_proc_compliance
  • E.g. 2: France Operation in Financial Accounting:
    • Labels to be used: country_accounting, france, financial_accounting
      (for country operations, the Domain is always country_accounting)
  • 3. Fill in all fields as described above

    4. Name the title of each section using OPD methodology naming convention - Infinitive verb without the “to”, mainly action verb...something) - " I do something..."

    5. Once the description of the operation is completed, ensure it is approved and published by launching the SBS-Finance approval workflow 

    Panel
    bgColor#F7F7F7
    titleColor#ffffff
    borderWidth1
    borderStylenone
    Domain: Finance Data & ReportingSU Management Accounting
    Panel
    bgColor#F7F7F7
    borderWidth1
    borderStylenone

    Responsibility area: Maintain Costing Master Data

    Table of contents 

    Table of Contents
    maxLevel2


    Panel
    borderStylenone
    Scope

    Image RemovedImage Added
    ERP

    Image RemovedImage RemovedImage Removed

    Image RemovedImage Removed



    (to be completed)PF2  WP2

    Frequency

     Image RemovedImage Removed Image Removed Image Removed

     Image Removed Image Removed Image Removed

     (to be completed)

    Image Added

    References

    Forms

    Attachments


    I run the standard cost calculation for a material (except DO NOT cost material) <<

    Page_title
    >> Next OP

    1. Objective and Scope

    1.1. Objective of this Operation

    The purpose of this document is to describe the process to add addicional data to produced materials

    1.2. Scope

     This procedure is applied to all companies WW.

    2. Definitions

    See Finance - Glossary:

    3.

    ..

    Tasks description

    3.

    Tasks description

    WHAT and HOW - Main content of the operation

    The content should be mainly organized in 2 levels of Headings to ensure a proper link with the Table of Contents.

     Select the level of heading in the "Paragraph" option.

    3.1. I create the cost collector

    3.1.1. Step 1 of Task 1

    3.1.2. Step 2 of Task 1

    ...

    3.2. I update the standard hierarchy of cost objects

    3.2.1. Step 1 of Task 2

    3.2.2. Step 2 of Task 2

    ...

    3.3. I inform the requester

    End of document.

    1. I create the cost collector

    Start the transaction using the menu path or transaction code KKF6N - Display Product Cost Collector

    (only if there is a production version)

    Image Added

    In KKF6N fill the material and plant.

    Image Added

    Press Enter

    Image Added

    The plant shall appear on the left side click on it and then in the highlighted icon. The following screen should appear.

    Image Added

    The order type is always RM01. Select the production version from the list. Choose the Production Version mentioned in the template.

    Image Added

    Press enter and the following should appear.

    Image Added

    Click save.

    Image Added

    Click Yes and this shall appear.

    Image Added

    3.2. I update the standard hierarchy of cost objects

    Start the transaction using the menu path or transaction code KKPHIE

    (Only if there is a Cost Object Node)

    Image Added

    Enter the cost object node and proceed.


    Image Added

    This will appear and click on display change.

    Image Added

    Then click on assign single object. 

    Image Added

    Image Added

    This will appear and click on new entries.


    Enter the material, press enter, back and save.

    Image Added

    3.3. I create cost estimate and release cost

    Status
    colourBlue
    titleStep 1

    Start the transaction using the menu path or transaction code CK11N

    (Only if Do not cost is unflagged)



    Image Added

    Fill with the material, plant and cost Variant. Cost Variant for PF1 and QF1 – ZPC1, WP1 and WQ1 – ZFO.

    Press enter and the Transfer control will appear


    Image Added

    Press enter again.

    Image Added

    Change the Costing Date from (1st date), QTY structure date (3rd date) and valuation date (4th date) to the present date.

    Press enter and the cost estimate will appear. Save.

    Compare the Total Value with the Expected Price. If both are equal, you may proceed; if not, you have to screenshot this table and send it to the Controller asking how you should proceed. While waiting for an answer, block the material at MM02.

    Image Added

    Status
    colourBlue
    titleStep 2

    Start the transaction using the menu path or transaction code CK24

     (Only if Do not cost is unflagged)

    Image Added

    Fill the plant and Material and perform a test run by clicking execute.

    Image Added

    This screen will appear, stating if it was successful or if it had any errors. Click back to move to the next screen. 

    Image Added

    Always check if the fut.plnd price matches the one given in CK11N.

    If successful unmark the test run and execute again.

    Image Added

    After a successful execution click on release.

    Image Added

    Click on execute.

    Image Added

    The following screen should appear.

    Image Added


    Image Added