In this document, you will find when datas are imported or exported between Dynasys, SAP and reports.

You must read this following tables from left to right, for exemple we send data from DIP-PP (Input System) to BW (Output System) at 9:00

For exemple if you want to know when the datas are transferred between DP and DIP-PP, you look for the number (4 in our case) and you refer to the table on the right.

Image Added


Demand PlanningGBU
DP1TS/AROMA
DP3NOVECARE


Distribution
planning-PP

GBU
DIP1TS/AROMA
DIP3NOVECARE


DATA TRANSFERS


START Export END Import




Image Added



SAP to DP

Image Added


Import static and dynamic datas (every days)


StaticDynamic
DP100:25 CET10:10 CET

DP3

12:00 CET10:15 CET



SAP to DIP-PP

Image Added

Export static and dynamic datas to DIP-PP



start
SAP->DIP-PP00:30CET

Import static and dynamic datas to DIP-PP (every days)


StaticDynamic
DIP103:40 CET07:30 CET
DIP302:10 CET07:25 CET










Image Added






DP to SAP

Image Added

Export Forecast to SAP is now done from DIP








DP to DIP-PP

Image Added

Export Forecast  (every days)

DP1

03:00 CET

13:10 CET

17:10 CET

22:10 CET

DP3


01:20 CET

13:15 CET

17:10 CET

22:10 CET

Import  Forecast (every days)

DIP1

05:10 CET

14:10 CET

18:10 CET

23:10 CET

DIP3

03:20 CET

14:05 CET

18:00 CET

23:00 CET

DP to BW and Dashboards (QlikSense or others)

Image Added

Export datas (every days)

DP1

06:00 CET

13:00 CET

17:00 CET

22:00 CET

DP3

06:00 CET

13:00 CET

17:00 CET

22:00 CET

Import datas (every days)

BW

07:00 CET

14:00 CET

18:00 CET

23:00 CET









Image Added

Image Added










DIP-PP to DP

Image Added

(every days)

DIP1

For  AP Constraint Demand ETD

For TS, Independant requirement ETD

13:50 CET

17:20 CET

22:20 CET

DIP3

For CS, Independant requirement ETD

13:50 CET

17:45 CET

22:45 CET

(every days)

DP1

14:10 CET

18:10 CET

23:10 CET

DP3


14:15 CET

18:40 CET

23:25 CET

Import:

  • For  AP Constraint Demand ETD
  • For CS, TS Independant requirement ETD




DIP-PP to SAP

Image Added

DIP1

TS

every 1rst

every 6th / 3:30 CET

every Saturday / 20:00 CET

DIP3

CS

every Saturday / 18:00 CET





DIP-PP to BW report and Qlikview

Image Added

Export datas (every days)


DIP1

DIP3

10:00 CET

13:00 CET

17:00 CET

22:00 CET

Import datas (every days)


DIP1

DIP3

11:30 CET

14:30 CET

18:30 CET

23:30 CET

...

DIP1: 00:00 CET

DIP2 CET

DIP3 CET

...

14:30 CET

17:30 CET

22:30 CET

...