1 Objective and Scope
1.1 Objective of this Procedure
1.2 Scope
2 Reference Documents
3 Definitions
3.1 Responsibility
3.2 Abbreviations
4 Summary
5 capitalization of an asset
5.1 Check the form received from Project Manager.
5.1.1 Control-Check after the file arrive
6 How to Create/Change an Asset
6.1 To create an Asset Master Data
6.2 To change an Asset Master Data
7 Creation of settlement rules
7.1 Manual creation of a settlement rule
Enter in transaction CJIC , choose data profile as shown below:
7.2 Mass creation of a settlement rule
Download both tabs into a txt file and save.
8 Settlement of WBS for capitalization
8.1 Settlement
8.2 Checking the capitalization
9 Defining the (F) allocation rule
10 Acquisition with negative amounts
11 Cancelling a capitalization
12 Capitalizations Controls:
12.1 Evidence request for commissioning/divestments
12.2 Capitalizations/Divestments above 50k.
12.3 Archiving
13 Close/Technically Close a project
13.1 Set status Technically Closed (TECO)
13.2 Set status Closed (CLSD)

14. I&D Asset Creation Template (automatic option)


Objective and Scope

Objective of this Procedure

The purpose of this document is to describe how to put an Asset Under Construction (AUC) in service through a Fixed Asset (FXA).

Scope

This procedure applies to WP2 system since in PF2 this is automatically. 

Definitions

Responsibility


Project Managers are responsible to fill the form in excel file "Asset on Completion Form" ("Demande de mises en service d'immobilisations") and send it through a ticket.
GBS Service Center is responsible to create the asset, settle the WBS and make the necessary checks in order to ensure that what was requested was correctly booked in SAP.

Acronyms

PS - Project System (SAP module)

WBS - Work Breakdown Structure 

MC - Material Code

AUC - Asset Under Construction

FXA - Fixed Asset



Resume


Capitalization of an asset:

  1. Account balance from WBS to AUC (automatic creation of AUC in previous months). The AUC will have values to capitalize until the project is under construction. As soon as the project is finished and ready for its use, the AUC should be Capitalized as defined in IAS 16 - Property, plant and equipment.
  2. When the project is ready for its use, it is needed to create the fixed assets related and:

> Change the WBS rule to "full" or "partial" settlement with the definitive fixed asset number and the capitalization date;
> Select the option processing type "full" or "partial" in the settlement transaction;
> Account balance from AUC to fixed asset - Verify balance of the project;
> Change the status of project (closed) if requested.


Capitalization of an asset

Check the form received from Project Manager


Project Managers send a file to GBS Service Center with the necessary information to capitalize an asset. The following information needs to be checked in the form before starting to proceed with SAP (if some information is missing, please send back the file requesting for the missing information):

  • Sheet "ASSET CREATION FORM" please check if the Header description is ok and consistent:

Image Added

  • Sheet "ASSET CREATION FORM" confirm that all mandatory fields are correctly filled, namely:

Asset Class

Description

Depreciation term by default

Depreciation term if applicable (only if different from the first one "by default")

Reason for Depreciation Adjustment (only if different from the first one "by default")

Cost Center

Division/Site

Location

(If the form have more information detailed please complete the asset master data accordingly)

  • Sheet "WBS Detailed Costs" please check if column "Alloc Code Tx/Fx" is filled without blank cells for all WBS line items. All other columns are extracted from BW and automatically filled in SAP (CJI3);
  • Sheet "WBS Detailed Costs" please check the nature of the WBS, if it is tangible or intangible AUC. Because you can only capitalize if the nature is the same ( AUC tangible → FXA tangible and AUC intangible→ FXA intangible);

    Check WBS with transaction CJ03 (double click on the WBS):

    Image Added


    Check the Asset Class in the form sheet "Asset Creation Form" and check in sheet "ASSET CLASSES & DEP TERMS" if it is tangible or intangible:

Image Added


Image Added


  • In sheet "Cost Allocation" please check if the total amount allocated is equal to the Total Project Amount. For that, the sum of WBS amounts in sheet "WBS detailed costs" must be equal to the total project to be capitalized. If the cells will appear in RED in sheet "Cost Allocation" means that the splitting allocation is not correct (different from 100%).


Image Added



Please check if:

  • The Total amount allocated is equal to the Total Project Amount
  • For that, the sum of each column regarding the split allocations must be 100%. If not, the cells will appear in RED, meaning that the splitting allocation is not correct.


In Asset on Complementation Form:


Image Added
In this form check if the amounts in column E (Total Amounts to post) are the same amounts inserted in the form In Cost Allocation.

In Asset Removal:
Image Added
This form is only necessary to Asset Removal. Unless it is required, it should be empty.

Anchor
_Toc488829750
_Toc488829750
How to Create/Change an Asset

Anchor
_Toc376857991
_Toc376857991
Anchor
_Toc488829751
_Toc488829751
To create an Asset Master Data

Anchor
_Toc376857992
_Toc376857992
Anchor
_Toc376858708
_Toc376858708

The Project Manager must send the excel file with all the information need and GBS Service Center perform the checks previously explained. After that, please follow the next steps.
Anchor
_Toc376857993
_Toc376857993
Anchor
_Toc376858709
_Toc376858709

Go to transaction AS01:
Image Added
With the information provided in the file sent from the Project Manager, please fill:

  • Asset Class
  • Company code*

*If no company code is described on the form, please check any of the WBS inside the form in CJ03 to check what company code it belongs.
Click Image Added
In TAB General, please fill:
Description – Name of the asset and the project number
Inventory number
Quantity

Image Added

In TAB Time-dependent, please fill:
Cost center
Plant
Location

Image Added


In TAB Allocations, the Evaluation Group is automatically fulfilled in line with the asset class.

Evaluation group 2 is mandatory for some asset classes. If the file does not contain any information regarding this field, we should contact the requester.   

Image Added

Evaluation Group 5 – It will be defined depending on the asset class.

User fields List is fulfilled by the system considering the cost center information. 


In TAB Origin, please fill:
Vendor (Not mandatory for RCS)
New/Used (Not mandatory for RCS)
Original Asset
WBS element – Fill in with the WBS inside the form that has the bigger amount
Flag the field Asset purch. new
Image Added
In TAB Net Work Tax, please fill:
Classification Key* 
It is to indicate what type of Tax should be paid (CFE or CVAE).
Normally the asset class matches with the following classification Key, but if not, we should accept which classification key that the system assumes, or in case of doubt, contact CAM.

  • AC215: FR90
  • AC211: FR30
  • AC213: FR30.

For French entities, if the classification key is F90, we can perform capitalizations since the beginning of the year. Otherwise, we can only do it for the quarter. 

Looking at the following picture, we can only accept capitalizations for the current quarter. 

Image Added



Property indicator - The code 1 comes by default depending on the category,

  • If blank, please contact the local accountant

    Image Added



    In TAB Deprec. areas see that:
    The depreciation (amortization code, duration) parameters are filled in by default, from the category, and by the asset class, normally if the use life is:
  • < 3 year  ZRH1
  • From 3 to 4 years  ZD12
  • From 5 to 6 years  ZD13
  • > 6 years  ZD14


Z000 means there is No depreciation.


Image Added

Click Image Added to confirm the entry;
Click Image Added to save the entry.
Image Added
A confirmation message appears at the bottom of the screen, where SAP returns the asset number created.

The Asset codification is XyyyyZZZZZZZ
X - '1 ' for Asset under construction / '2' for final assets.
yyyy - Company code
ZZZZZZZ – Automatic number
After the asset is created, fill in the form with its number
Image Added

Anchor
_Toc488829752
_Toc488829752
To change an Asset Master Data

Anchor
_Toc376857996
_Toc376857996
Anchor
_Toc376858712
_Toc376858712

The Project manager must send the excel file with all the information need and GBS Service Center perform the checks previously explained.

After that, access transaction AS02, and change the fields required.


Anchor
_Toc488829753
_Toc488829753
Creation of settlement rules


Anchor
_Toc488829754
_Toc488829754
Manual creation of a settlement rule

Anchor
_Toc376857999
_Toc376857999
Anchor
_Toc376858715
_Toc376858715
Anchor
_Toc488829755
_Toc488829755
Enter in transaction CJIC , choose data profile as shown below:

Image Added
insert the WBS or the project and execute :
Image Added
The purpose is to allocate costs posted on the investment measure to completed fixed assets
Image Added
Click on the button "final settlement" and the following screen will appear:
Image Added
During this step the system creates the distribution rules, gives them a number (Distribution Group Rule) and assigns each of them to each investment measure line item that have been selected
After complete all the required fields, go back Image Added and check if the lines selected are now green :
Image Added

And press save Image Added .
Image Added

Anchor
_Toc488829756
_Toc488829756
Mass creation of a settlement rule


Anchor
_Toc376858001
_Toc376858001
Anchor
_Toc376858717
_Toc376858717
Inside the form sent by the project manager, there are two tabs named txt file: Image Added and Image Added .

Anchor
_Toc376858002
_Toc376858002
Anchor
_Toc376858718
_Toc376858718
Anchor
_Toc488829757
_Toc488829757
Download both tabs into a txt file and save.

Enter in transaction ZWFA060, fill in the company code and the address of both txt file following the name:

Image Added
Run first in test mode to check if all information are correct filled in SAP :
Image Added
Go back Image Added and unflag the test run. Run it in real mode to feed SAP. The program will show the same screen as in test mode, delivering the following message: Image Added .
Possible errors:
R1: File "X" (from selection field " Path and file name for distribution rules") cannot be read or is inconsistent.
R2: Some asset numbers are twice in the file "X" (from selection field " Path and file name for distribution rules"), please correct the file.
R3: Asset number "X" (to indicate the fixed asset number) doesn't exist in RCS database, please correct the file X (from selection field "Path and file name for distribution rules") => to list all fixed assets in as many line as error.
R4: Asset number "X" (to indicate the fixed asset number) is deactivated, please correct the file "X" (from selection field "Path and file name for distribution rules") => to list all fixed assets in as many line as error.
R5: some DRG from column D don't have the right structure, all of them should start by T + a numerical number
R6: In column D there is more than one line with the same DRG, please correct the file "X" (from selection field "Path and file name for distribution rules").
R7: Column "X" (indicate the column number for which there is an error) the total percentage is not = 100%, please correct the file "X" (from selection field "Path and file name for distribution rules").
R8: asset "XXXXXXXXXXX-Y" (to retrieve the asset number from the file) is not created in the same company as the one from the selection, please correct either the selection or the file "X" (from selection field "Path and file name for distribution rules").
R9: file "X" (from selection field " Path and file name for distribution rules assignment") cannot be read or is inconsistent
R10: DRG "X" (the DRG n°) doesn't exist in file "X" (from selection field "Path and file name for distribution rules"), please correct the file "Y" (from selection field "Path and file name for distribution rules assignment").
R11: the company code from line "X" is not the same as the one from the selection, please correct either the selection or the file "X" (from selection field "Path and file name for distribution rules assignment")
R12: EN: CO document number "X" doesn't exist, please correct the file X (from selection field "Path and file name for distribution rules assignment"). FR: le document CO "X' n'existe pas, veuillez corriger le fichier "X" SVP.
R13: WBS element "X" doesn't exist, please correct the file X

Authorizations & Roles

...

Author(s)

...

Verification

...

Approval

...

Diann Shiver
Organization Methods Document & Communication

...

Michel Berger
RTR WW Process Expert Invest & Divest

...

02/05/2016

...

03/05/2016

...

03/05/2016

...

Version

Date

Description

01

22/04/2014

New Document

02

24/03/2016

Update in chapter 12.1-Suppression signature for validation commissioning template

03

03/05/2016

Update in chapter 6.1 – LAM companies specific information
Added chapter 13 – Close/Technically Close a project

...

 

...

The purpose of this document is to describe the transactions related to the process of project structuring and creation of asset master data.

...

This operating procedure (OP) applies to RCS system.

...

 

PS

Project System (SAP module)

WBS

Work Breakdown Structure of a project in SAP PS

MC

Material Code

AuC

Asset under Construction

 

...

  • Account balance from WBS to AUC ( automatic creation of AUC in the first month )
  • End of project :

Creation of definitive asset (AS01)
After the account balance from wbs to AUC:
> Change the rule of wbs to "full" or "partial" settlement informing the definitive asset number and the capitalization date
> select the option processing type "full" or "partial" in the settlement transaction CJ88
> After the account balance from AUC to definitive asset ,
Verify balance of project
> change the status of project (closed)
R&D France : All WBS elements are settled into cost centers. Some of them go finally into G/L account «assets under construction» to be capitalized. The others go into P&L.

...

 

...

  • For all the forms, please check if the Header description is OK and consistency.

...

  • Column B to J are filled, with the exception of column F that only needs to be filled, when a justification is needed regarding differences between Depreciation term by default (IFRS) and Depreciation term applicable (columns D and E);

...

  • The Total amount allocated is equal to the Total Project Amount
  • For that, the sum of each column regarding the split allocations must be 100%. If not, the cells will appear in RED, meaning that the splitting allocation is not correct.

...

  • Asset Class
  • Company code*

...

  • The differences of capitalization between IFRS and local, can only be provided by the local accountant. Ask for this information when needed.
    Image Removed
    In TAB Origin, please fill:
    Vendor (Not mandatory for RCS)
    New/Used (Not mandatory for RCS)
    Original Asset
    WBS element – Fill in with the WBS inside the form that has the bigger amount
    Flag the field Asset purch. new
    Image Removed
    In TAB Net Work Tax, please fill:
    Classification Key*:
    It is to indicate what type of Tax should be paid (CFE or CVAE).
    Normally the asset class matches with the following classification Key, but if not, we should accept which classification key that the system assumes, or in case of doubt, contact CAM.
  • AC215: FR90
  • AC211: FR30
  • AC213: FR30.

...

After that, access transaction AS02, and change the fields required.

 

...

 

...

Enter in transaction ZWFA060, fill in the company code and the adress of both txt file following the name:

Image Removed
Run first in test mode to check if all information are correct filled in SAP :
Image Removed
Go back Image Removed and unflag the test run. Run it in real mode to feed SAP. The program will show the same screen as in test mode, delivering the following message: Image Removed .
Possible errors:
R1: File "X" (from selection field "Path and file name for distribution rules assignment") cannot be read or is inconsistent.
R2: Some asset numbers are twice in the file "X" R14: WBS element "X" is not assigned to the same company as the one from the selection, please correct either the selection or the file X (from selection field "Path and file name for distribution rules assignment"), please correct the file.
R3: Asset number "X" (to indicate the fixed asset number) doesn't exist in RCS database, please correct the file X (from selection field "Path and file name for distribution rules") => to list all fixed assets in as many line as error.
R4: Asset number "X" (to indicate the fixed asset number) is deactivated, please correct the file "X" (from selection field "Path and file name for distribution rules") => to list all fixed assets in as many line as error.
R5: some DRG from column D don't have the right structure, all of them should start by T + a numerical number
R6: In column D there is more than one line with the same DRG, please correct the file "X" (from selection field "Path and file name for distribution rules").
R7: Column "X" (indicate the column number for which there is an error) the total percentage is not = 100%, please correct the file "X" (from selection field "Path and file name for distribution rules").
R8: asset "XXXXXXXXXXX-Y" (to retrieve the asset number from the file) is not created in the same company as the one from the selection, please correct either the selection or the file "X" (from selection field "Path and file name for distribution rules").
R9: file "X" (from selection field " Path and file name for distribution rules assignment") cannot be read or is inconsistent
R10: DRG "X" (the DRG n°) doesn't exist in file "X" (from selection field "Path and file name for distribution rules"), please correct the file "Y" (from selection field "Path and file name for distribution rules assignment").
R11: the company code from line "X" is not the same as the one from the selection, please correct either the selection or the file "X" (from selection field "Path and file name for distribution rules assignment")
R12: EN: CO document number "X" doesn't exist, please correct the file X (from selection field "Path and file name for distribution rules assignment"). FR: le document CO "X' n'existe pas, veuillez corriger le fichier "X" SVP.
R13: WBS element "X" doesn't exist, please correct the file X (from selection field "Path and file name for distribution rules assignment").
R14: WBS element "X" is not assigned to the same company as the one from the selection, please correct either the selection or the file X (from selection field "Path and file name for distribution rules assignment").
R15: If status = 05 => CO document "X" is already assigned to a distribution rule, FR: le document CO "X" a déjà une règle de distribution. If status = either 06 or 09.
R16: The CO document xxxxxxxx has a WBS element (PRPS-PSPNR) different from the WBS element (WBS element from input file) on the input file C:\xxxxxx.txt. Please check

...

-- The processing type:

* Partial Capitalization : The system will only capitalize costs which are assigned to a distribution group rule. At least one must be.

  • Full settlement:* Commissioning of the whole costs of investment measure

    -- The asset value date: corresponds to the capitalization date, it is used to determine the depreciation start date. If this field is blank, by default the system uses the last day of the settlement period, but we need to fill in with date described inside the form:

    Image Removed

...

After the partial or the capitalization settlement is performed, go to transaction AS03 to display the master data of the fixed assets that received the costs of the WBSs.

...

  1. If we have a F1 rule, we start to make a filter by WBS.

...

  • 60% in Asset 3  FXA 242740046378
  • 30% in Asset 4  FXA 242740046379
  • 10% in Asset 6  FXA 242740046381

...

 

...

R15: If status = 05 => CO document "X" is already assigned to a distribution rule, FR: le document CO "X" a déjà une règle de distribution. If status = either 06 or 09.
R16: The CO document xxxxxxxx has a WBS element (PRPS-PSPNR) different from the WBS element (WBS element from input file) on the input file C:\xxxxxx.txt. Please check

Anchor
_Toc488829758
_Toc488829758
Settlement of WBS for capitalization

Anchor
_Toc488829759
_Toc488829759
Settlement

Anchor
_Toc376858005
_Toc376858005
Anchor
_Toc376858721
_Toc376858721


In order to transfer the costs inside the WBS to a fixed asset, the full settlement or a partial settlement is required. For this procedure, enter in transaction CJ88 and fill in the following fields by using the form information:
Anchor
_Toc376858006
_Toc376858006
Anchor
_Toc376858722
_Toc376858722
– WBS element to settle to the completed fixed assets;
Anchor
_Toc376858007
_Toc376858007
Anchor
_Toc376858723
_Toc376858723

– settlement period and fiscal year;

-- The processing type:

* Partial Capitalization : The system will only capitalize costs which are assigned to a distribution group rule. At least one must be.

    • Full settlement:* Commissioning of the whole costs of investment measure

      -- The asset value date: corresponds to the capitalization date, it is used to determine the depreciation start date. If this field is blank, by default the system uses the last day of the settlement period, but we need to fill in with date described inside the form:

      Image Added
    • Check the box of test run and detail list to preview the results of the settlement before processing in real mode;
      Image Added
      Anchor
      _Toc376858008
      _Toc376858008
      Anchor
      _Toc376858724
      _Toc376858724

      Execute Image Added and the following screen will appear and inside, it can be checked if there is any error on red box below and also which will be the amount allocated by clicking in icon Image Added :
      Image Added

      Go back Image Added an run in real mode, by unchecking the test run box. The same scream will appear, but with "processing mode" Real mode.
      From an accounting point of view the system always capitalizes costs (from the investment measure) into the AuC and then transfers them (from AuC) to the completed fixed assets. Consequently when there are costs not yet capitalized into AuC at the commissioning time the system performs simultaneously the 2 steps. For this latter notice that in test run the system displays only the settlement result of the first step (settlement to AuC).

      Anchor
      _Toc488829760
      _Toc488829760
      Checking the capitalization

      After the partial or the capitalization settlement is performed, go to transaction AS03 to display the master data of the fixed assets that received the costs of the WBSs.

      Insert the asset number and the company code and press Enter:
      Image Added
      The following screen will appear :
      The capitalized on date has been populated from the asset value date of the settlement parameter screen.
      Image Added


      The original asset field has been populated with the AuC number.
      Image Added
      Image Added

      By clicking on Image Added , it is possible to check the amount of the settlement inside the asset. Compare this amount with the form sent by the project manager in the tab Image Added .
      Image Added

      Anchor
      _Toc488829761
      _Toc488829761
      Defining the (F) allocation rule


      The (F) rule is a specific allocation rule, where an asset can be allocated by more then 1 allocation rule.
      Image Added
      Asset 3,4 and 6 will be allocated by the respective allocation rule, plus F1 rule.
  1. If we have a F1 rule, we start to make a filter by WBS.

We can see that the WBS PA.SF1294.0EEG is allocated by settlement rule F1
Image Added

The F1 rule is defined as below:

  • 60% in Asset 3  FXA 242740046378
  • 30% in Asset 4  FXA 242740046379
  • 10% in Asset 6  FXA 242740046381




So, the WBS PA.SF1294.0EEG rule will be defined in CJIC as:
Image Added
The allocation rule distributes for all the assets involved in the capitalization file, the costs of the WBS, which has a F rule as its allocation rule.

Anchor
_Toc488829762
_Toc488829762
Acquisition with negative amounts


The system does not allowed the posting on assets with negative values, because by default the asset is define to not accept negative values.
The general error is the following:
Image Added
To be able to do this kind of posting, we have to make changes in the the asset master data in TAB Image Added .
Then Double click in each line of the depreciation area board:
Image Added
You will get the following screen
Image Added
Then, activate the fuction Image Added
After that you can proceed with the settlement of the WBS





Anchor
_Toc488829763
_Toc488829763
Cancelling a capitalization


The need to cancel a capitalization normally occurs after the internal capitalization controls, there are some cases where the capitalization could be done in a wrong period, or by other reason that it was detected that it should be canceled.
The first step is to cancel the acquisition amount in the fixed asset:
Go to transaction AB08
Image Added
Select the line that you need to be cancel, and press Reverse
A new screen will appear automatically, concerning the CJ88 to cancel the settlement, choose reverse.
Image Added
Then go back to AB08
Image Added
This way you can check if the reverse was made in the asset.
Now you can proceed in order to capitalize the right way.
After, you can check in values of the asset (transaction AS03) the final result
Image Added
In this screenshot you can see that the second line is related to the reverse of the settlement (capitalization cancelation).
The third line concerns the capitalization posted after the reverse with the corrected data.








Anchor
_Toc488829764
_Toc488829764
Capitalizations Controls:


Anchor
_Toc488829765
_Toc488829765
Evidence request for commissioning/divestments


Just need a evidence for the commissioning.(Signatures are no longer required)
Project Managers, should send a request number by SYRA, with excel file template. See point number 5.1.1 of this Operational Procedure.

Anchor
_Toc488829766
_Toc488829766
Capitalizations/Divestments above 50k.


The Capitalizations/Divestments above 50k need to be tracked (Internal Control FXA.01.01 - Modification in the assets books)
Minimum frequency:  at each change/until D-3 of each month

Control owner function: GBS MAC SU 

Application level: Group - All assets (tangible & intangible) - Period of controls: each Month.
Process description:  Fixed asset creation respects the following steps: WBS definition (Work Breakdown Structure) – WBS creation in SAP – Purchase and expense allocation – WBS settlement on assets under construction – Technical project closure – Cost settlement to fixed assets register – Accounting project closure. Deletions of assets from assets register concern disposals, sales or retirement.

Control description: SU MAC I&D Key user or technical controllers (depending on organization) need a proof of authorization from Project Managers (commissioning) or Plant Manager or delegate (other modifications: retirement…) to make modifications > 50k€ to the assets register. For control in the scope of GBS, it is executed by GBS Finance Operation team and monitored by SU MAC I&D Key User (GBS)

useful link for this Internal Control

Anchor
_Toc488829767
_Toc488829767
Archiving


All assets created need to have a SYRA ticket number
All capitalizations need to be received via SYRA, since SYRA will be used as an archiving tool, linking the assets created and the capitalization request via the SYRA Case Nº. It is where you can find the requested form for capitalizations/retirements 

The transaction Z1A_ASSET_NOTE – ASSET MASTER DATA ATTACHMENT NOTE
is used to make sure that all assets created have a SYRA case Nº ,each ticket number has the capitalization form and annexes attached. These cases are sent by the engineers/project managers.
Image Added
This transaction will allow you to see if your assets created have a note or a sales force case linking to the Archive document under Note title
Image Added
In case of no case number, you can easily inserted by double click in the asset and inserted the Case number in the note created
Image Added
Image Added

Anchor
_Toc488829768
_Toc488829768
Close/Technically Close a project


*OBS: these steps are done only for LAM companies and only under request.
If the project manager did not request to close or technically close the project, there is no need to follow the instructions below.
When requesting the capitalization of a project, Project Managers could also request to close or technically close the related project.
If this is the case, we should perform the following steps:

Anchor
_Toc488829769
_Toc488829769
Set status Technically Closed (TECO)


*OBS: called "Encerramento Técnico" for LAM companies.
Enter in transaction CJ02 and insert the project to be technically closed
Image Added
Select all WBS elements that were capitalized and will be technically closed. After that, go to "Edit", Status, "Technically Complete"
Image Added
After that, click on Image Added and then go to "Edit", "Status", "Technically Complete"
Image Added
After that, all WBS elements and the project itself will be set as "Technically Complete" (TECO). Save the changes by clicking on Image Added .

Anchor
_Toc488829770
_Toc488829770
Set status Closed (CLSD)


*OBS: called "Encerramento Contábil" for LAM companies.
Firstly, you have to perform all the steps above to set the project status to "Technically Complete". However, before saving, do the following:
Image Added
"Edit", "Status", "Close".
After that, click on Image Added and then go to "Edit", "Status", "Close"
Image Added
After all these changes, all the projects and WBS elements are "Closed" (CLSD).
Save the changes by clicking on Image Added .

I&D Asset Creation Template (automatic option)


If there are several assets to be created, we can use “I&D Asset Creation Template”.  

Image Added

1) Copy to this file from the original assets file the following sheets (sheets need to be in english): 

Asset Creation Form

WBS Detailed Costs

Cost Allocation

Asset on Completion Form


2) Insert ticket number and verify the asset nature of the excel file is consistent with SAP (tangible vs intangible). Additionally, check if the WBS has not yet been capitalized. 

3) Be sure that the first SAP window open is WP2 and afterwards press the Start button and wait for the conclusion message. 

4) In sheet output, you can find the list of assets created with asset number and all the remaining information (capitalization date, plant, cost center, description, asset class, and useful life). In case of error, please check which mandatory field is missing. You can update sheet Instructions and press try again button.

5) When all assets are created, press the Distribution Rules icon to create and upload in SAP the distribution rules. After that, please check if all information in CJIC are green. 

6) The file does not perform the settlement of the WBS so, it's necessary to do CJ88/CJ8G manually.

7) To check if everything is correct, you can go to AR02 with asset numbers and check if the amounts are according to the Cost Allocation sheet. 

...

*OBS: called "Encerramento Contábil" for LAM companies.
Firstly, you have to perform all the steps above to set the project status to "Technically Complete". However, before saving, do the following:
Image Removed
"Edit", "Status", "Close".
After that, click on Image Removed and then go to "Edit", "Status", "Close"
Image Removed
After all these changes, all the projects and WBS elements are "Closed" (CLSD).
Save the changes by clicking on Image Removed .
End of document