Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.


PMO Report Dashboard




Table of Contents

Document Information


Functional Analyst 

Abidemi Raji

VERSION

DATE

MODIFIED BY

DESCRIPTION

0.01

/10/

 

Abidemi Raji

Initial draft

0.02

/10/

 

Abidemi Raji

Updated
0.03

/11/

 

Abidemi Raji

Updated with list of requirements and alternative tables 
0.04

 

Abidemi Raji

  • Updated scope and requirements to include only SBS project portfolio dashboard 
  • Descoped 15 additional KPIs

1.0 Overview

Business Context and Application Overview

...

Domain: Programme Management / Finance

Main stakeholders:  Service Delivery Managers (SDM), Pool Leads, Product Managers, Program Managers, PMO, Leadership Team (LT)

Business objective/value:  Use data sourced from internal databases to create  KPIs, determine project financial or execution status and provide decision useful information to stakeholders eliminating the need for manual intervention . 

Main function: The dashboard is a visualization tool which provides authorized users with information on project financial and operational status. Various KPIs are also created using data sourced from Accolade and enriched with derived indicators to provide a complete overview to users.

The SBS Project Portfolio dashboard is used by the PMO team to monitor project deliverables, provide project financial summary and present any risks and issues. It provides a single source of information to the team and stakeholders on project KPIs, execution status, risk and issues over a specific period. e.g.

  • Project Status monitoring - Operational Burn Rate
  • Project Status monitoring - Status Update Frequency
  • Project Status monitoring - Carry Over not planned
  • Financial Status - Project Burn Rate
  • Financial Status - Project Close to Over Budget
  • Financial Status - Split Capex OTC
  • Financial Status - Project on Budget

Provide an overview of the app (e.g Domain, key processes, purpose of the app, etc)
Application User Profile

Describe the key User profiles that exist for the application. 

General role/Viewer role:

Approver role:

Target Users:

As examples: Controllers / Accountants

VERSION

DATE

MODIFIED BY 

DESCRIPTION

0.01

dd.mm.yyyy

<Insert name>

Initial draft










Application Type

 

Data Product Type 
  •  Dashboard
  •  Report
  •  Advanced analytics
  •  AI 
  •  Others <specify which one>
Technologies
  •  BW
  •  Tableau
  •  Qliksense
  •  Talend
  •  Dataiku
  •  Others <specify which one>

Data Sources 

Note: list of all applications and various environment

  •  SAP PF1 (Production environment)
  •  SAP WP1
  •  SAP PI1
  •  BW (versions)
  •  iCare CRM 
  •  CORE CRM
  •  Others <Accolade> 


Application Overview

Domain: Programme Management / Finance

Main stakeholders:  Service Delivery Managers (SDM

Application Contact Details

Role (if applicable)Name Department Email Product Owner 
  1. Claire Bazin
  2. Dominique de Gouberville
Technical Product Owner Users Service Delivery Managers (SDM

), Pool Leads, Product Managers, Program Managers, PMO, Leadership Team (LT)

Sign-Off / Approval

...

Business objective/value:  Use data sourced from internal databases to create  KPIs, determine project financial or execution status and provide decision useful information to stakeholders eliminating the need for manual intervention . 

Main function: The dashboard is a visualization tool which provides authorized users with information on project financial and operational status. Various KPIs are also created using data sourced from Accolade and enriched with derived indicators to provide a complete overview to users.

The SBS Project Portfolio dashboard is used by the PMO team to monitor project deliverables, provide project financial summary and present any risks and issues. It provides a single source of information to the team and stakeholders on project KPIs, execution status, risk and issues over a specific period.


Application Contact Details

Role (if applicable)Name Department Email 
Product Owner 
  1. Claire Bazin
  2. Dominique de Gouberville


Technical Product Owner 


Users Service Delivery Managers (SDM), Pool Leads, Product Managers, Program Managers, PMO, Leadership Team (LT)

Sign-Off / Approval

Role (if applicable)Name Department Email Sign-Off
Product Owner 

Claire Bazin




Product Owner

Dominique de Gouberville




Project ManagerMauricio NagahamaProject Manager • Delivery | DATA, ANALYTICS & AI PLATFORM_ECO mauricio.nagahama@solvay.com  
Technical Sign offFernando GiranteData Architect • Data & Analytics & AI Platform | DATA, ANALYTICS & AI PLATFORM_ECO fernando.girante@solvay.com  
Technical Sign offAnon KasemvilasData Engineer • Data architecture & engineering_ECO | DATA, ANALYTICS & AI PLATFORM_ECO anon.kasemvilas@solvay.com  
Technical Sign offMaxime MarboeufData science & AI_ECO | DATA, ANALYTICS & AI PLATFORM_ECOmaxime.marboeuf-ext@solvay.com

Application Access Rights 

Access to the PMO dashboard depends on the user's profile which ensures that the user is allowed to perform the requested action (e.g. Run reports and download results). The user profiles (“normal user” and “advanced user”) at the same time correspond to the privileges granted according to the Business Unit the user belongs to using Single Sign On functionality

Department

GBU Code

Role

Right

Comments


























Business Context

Scope: 

In-Scope

This document covers the requirements for the PMO Dashboard to be migrated onto Tableau

  • Main dashboard visualisation and filters
  • Access to data post corporate action (split)
  • Access to the dashboard

Out Of Scope

  • Data Sourcing requirements are out of scope of this document. 


2.0 Business Process

...

Capture the business process that the application supports . This can be describe through a process diagram or a business capability model.

The PMO team regularly monitors the overall financial and operational status of several programmes and projects within the organisation and provide update to stakeholders on project or programme status.  The team needs the capability to extract and transform data seamlessly for the required parameters that have been pre-defined as part of the reporting process.

Specifically, the PMO team objectives are: 

  • Portfolio Monitoring:  The team requires the capability to monitor projects and programmes that are Open or Closed within a defined time period in order to determine status, be aware of risks to project delivery and provide decision useful information to stakeholders.
  • Data sourcing: The PMO team sources project operational and financial data from Accolade (Solvay internal DB) and vshare.
  • Reporting: The PMO team requires the capability to create reports from the data extracted from Accolade/vshare, highlighting several defined KPIs to provide updates on project financial and operational status. 
  • Automation: The extraction, refresh and KPI update process are to be performed without manual intervention.


2.1 Challenge/Opportunities

Clearly articulate the specific problem or opportunity that the application is addressing within the business by leveraging from data. This should be a concise and well-defined statement that captures the essence of the challenge or opportunity that the application is trying to solve by providing insight from the data.   

The new PMO dashboard in Tableau will provide authorised users with the capability to leverage multiple data sources within Solvay to review Financial and Operational performance of programmes and projects within a 3.5 year rolling window and have instant access to KPIs, with automated data refresh, eliminating the need for any manual interference. 

  • E ffective presentation of data: The PMO team require the capability to present KPIs and project status information in an automated fashion, showing the most impactful metrics. 
  • Consolidated reporting: A single source pf reporting Financial and Operational status of projects and programmes including KPIs
  • Eliminate manual spreadsheets: The reporting process should not involve manual intervention


3.0 Application Feature Overview

...

Information about the existent features in the application.


Feature

Description

Latest uppdate in production (DD/MM/YYYY)











4.0 Business Objects

...

This section should contain a table with the business objects used in the reports with links to the business object definition in LeanIX.  The purpose is to ensure that all DA&AI Products adhere to a centrally maintained list of business objects and definitions to allow us to achieve our digital ambitions.  For any questions about business objects and LeanIX, contact Data Governance or the Enterprise Information Architect.

Data Domain

Business Object (in LeanIX)

Business Object Definition (only use when the object is not yet in LeanIX)

ex: Marketing & Salesex:   Customer  






Functional Description


Expand
titleDashboard

Dashboard 


Data Attributes and Mapping: https://docs.google.com/spreadsheets/d/1zaJ5Q87nML7v4CHXhNf3qcng_4EzJ0pKWVPr0OyzUCo/edit#gid=1844818474




Data Product Type 
  •  Dashboard
  •  Report
  •  Advanced analytics
Technologies
  •  BW
  •  Tableau
  •  Qliksense
  •  Talend
  •  Dataiku
  •  Others <specify which one>

Data Sources 

Note: list of all applications and various environment

  •  Accolade
  •  SAP PF1 (Production environment)
  •  SAP WP1
  •  SAP PI1
  •  BW (versions)  

Data Input

As-Is Data Sources (including the nature of the data and what is it needed for):

Currently the PMO Dashboard is implemented in Qlikview. Data is sourced from Accolade_SBS_Portal using two main queries (SGM_CUSTOM_VIEW,  SGM_CORE_Project Details) and a Stored Procedure ( RSP_QV_GetMergedMetricsForGroupID) which uses GROUPID_SYS as a parameter . 


Image Added


AS-IS Tables
 SGM_CUSTOM_VIEW
SGM_CORE_Project Details
SGM_PROJECTMETRICS_15
SGM_PROJECTMETRICS_62
SGM_PROJECTMETRICS_94
SGM_PROJECTMETRICS_108


As-Is Data Model: 

Image Added


Target State Data Model:

The target state data sourcing model will re-use existing data model (queries and Stored Procedures) as well as include additional calls to the Database using GroupID_SYS as shown below.



As-IsTo-BeComments
DatabaseAccolade_SBS_PortalAccolade_SBS_Portal
Stored ProcedureRSP_QV_GetMergedMetricsForGroupIDRSP_QV_GetProjectMetricsForGroupID
ParameterGroupID_SYSGroupID_SYS
Query/Tables SGM_CUSTOM_VIEW SGM_CUSTOM_VIEW / CRV_Initiative_V3
SGM_CORE_Project DetailsSGM_CORE_Project Details / CRV_ZGetProjectDetails

GroupID_SYS:

15, 62,94,108

GroupID_SYS:
15,62,94,103

Execute the stored procedure iteratively, with the different parameters to obtain the different results sets needed for the scope of the project

Query/Tables

Budget Arbitrated

Budget Arbitrated

*Results on this table empty. To be validated 

Target State Data Sourcing:


Business Concept

Database Object

Link to output specification

Comments

SGM_CUSTOM_VIEW

CRV_Initiative_V3

CUSTOMISED_VIEW_FILTERCON

<comment or description of the concepts in the table>

SGM_CORE_Project Details

CRV_ZGetProjectDetails

CORE_PROJECT_DETAILS_FILTERCON

SGM_PROJECTMETRICS_15

Exec RSP_QV_GetProjectMetricsForGroupID 15

SGM_PROJECTMETRICS_15_FILTERCON

SGM_PROJECTMETRICS_62

Exec RSP_QV_GetProjectMetricsForGroupID 62


SGM_PROJECTMETRICS_94

Exec RSP_QV_GetProjectMetricsForGroupID 94

SGM_PROJECTMETRICS_94_FILTERCON

SGM_PROJECTMETRICS_108

Exec RSP_QV_GetProjectMetricsForGroupID 103

SGM_PROJECTMETRICS_103_FILTERCON


Transformation Rules (for each of the data source in the previous point): 

In the target state, additional filters to the data extract are required to be implemented in the result of the SGM_CORE_Project Details / CRV_ZGetProjectDetails query

    1. Extraction rules and filters:
      1.   Project Closed Date >= 3.5yrs
      2.   Project Closed = 0
    2. Exception handling rules (how do we handle when data does not come in the format we need) : Normal exception handling rules apply
    3. Enrichments (normally joins) 
    4. Aggregation rules


Visualization


Graph name

Description 

Link 

Main DashboardSBS Project Portfolio: Project DetailsSBS_Project_Portfolio_Visualisation




PMO Dashboard AS-IS Visualisation:

Image Added


Dashboard filters:

- Roadmap

...

Claire Bazin

...

Dominique de Gouberville

...

Application Access Rights 

Access to the PMO dashboard depends on the user's profile which ensures that the user is allowed to perform the requested action (e.g. Run reports and download results). The user profiles (“normal user” and “advanced user”) at the same time correspond to the privileges granted according to the Business Unit the user belongs to using Single Sign On functionality

...

Department

...

GBU Code

...

Role

...

Right

...

Comments

Business Context

Scope: 

In-Scope

This document covers the requirements for the PMO Dashboard to be migrated onto Tableau

  • Main dashboard visualisation and filters
  • KPI dashboard visualisation and filters
  • Access to the dashboard

Out Of Scope

  • Data Sourcing requirements are out of scope of this document. 

Business process: 

The PMO team regularly monitors the overall financial and operational status of several programmes and projects within the organisation and provide update to stakeholders on project or programme status.  The team needs the capability to extract and transform data seamlessly for the required parameters that have been pre-defined as part of the reporting process.

Specifically, the PMO team objectives are: 

  • Portfolio Monitoring:  The team requires the capability to monitor projects and programmes that are Open or Closed within a defined time period in order to determine status, be aware of risks to project delivery and provide decision useful information to stakeholders.
  • Data sourcing: The PMO team sources project operational and financial data from Accolade (Solvay internal DB) and vshare.
  • Reporting: The PMO team requires the capability to create reports from the data extracted from Accolade/vshare, highlighting several defined KPIs to provide updates on project financial and operational status. 
  • Automation: The extraction, refresh and KPI update process are to be performed without manual intervention.

Challenge/Opportunity

The new PMO dashboard in Tableau will provide authorised users with the capability to leverage multiple data sources within Solvay to review Financial and Operational performance of programmes and projects within a 3.5 year rolling window and have instant access to KPIs, with automated data refresh, eliminating the need for any manual interference. 

  • Effective presentation of data: The PMO team require the capability to present KPIs and project status information in an automated fashion, showing the most impactful metrics. 
  • Consolidated reporting: A single source pf reporting Financial and Operational status of projects and programmes including KPIs
  • Eliminate manual spreadsheets: The reporting process should not involve manual intervention

Business Glossary

Terminology used in this application consider to be added in ->  Enterprise Data Governance

...

Description 

Application Feature List 

...

Functional Description

Data Input

As-Is Data Sources (including the nature of the data and what is it needed for):

Currently the PMO Dashboard is implemented in Qlikview. Data is sourced from Accolade_SBS_Portal using two main queries (SGM_CUSTOM_VIEW,  SGM_CORE_Project Details) and a Stored Procedure ( RSP_QV_GetMergedMetricsForGroupID) which uses GROUPID_SYS as a parameter . 

Image Removed

Expand
titleDashboard

Dashboard 

Data Attributes and Mapping: https://docs.google.com/spreadsheets/d/1zaJ5Q87nML7v4CHXhNf3qcng_4EzJ0pKWVPr0OyzUCo/edit#gid=1844818474

Data Product Type 
  •  Dashboard
  •  Report
  •  Advanced analytics
Technologies
  •  BW
  •  Tableau
  •  Qliksense
  •  Talend
  •  Dataiku
  •  Others <specify which one>

Data Sources 

Note: list of all applications and various environment

  •  Accolade
  •  SAP PF1 (Production environment)
  •  SAP WP1
  •  SAP PI1
  •  BW (versions) 
AS-IS Tables
 SGM_CUSTOM_VIEW
SGM_CORE_Project Details
SGM_PROJECTMETRICS_15
SGM_PROJECTMETRICS_62
SGM_PROJECTMETRICS_94
SGM_PROJECTMETRICS_108

As-Is Data Model: 

Image Removed

Target State Data Model:

The target state data sourcing model will re-use existing data model (queries and Stored Procedures) as well as include additional calls to the Database using GroupID_SYS as shown below.

As-IsTo-BeCommentsDatabaseAccolade_SBS_PortalAccolade_SBS_PortalStored ProcedureRSP_QV_GetMergedMetricsForGroupIDRSP_QV_GetProjectMetricsForGroupIDParameterGroupID_SYSGroupID_SYSQuery/Tables SGM_CUSTOM_VIEW SGM_CUSTOM_VIEW / CRV_Initiative_V3SGM_CORE_Project DetailsSGM_CORE_Project Details / CRV_ZGetProjectDetails

GroupID_SYS:

15, 62,94,108

GroupID_SYS:
18, 46, 109, 63, 64, 65, 66, 103, 104, 69, 111, 105, 106, 110, 124

Execute the stored procedure iteratively, with the different parameters to obtain the different results sets needed for the scope of the project

Target State Data Sourcing:

Business Concept

Database Object

Link to output specification

Comments

SGM_CUSTOM_VIEW

CRV_Initiative_V3

Tables, Stored Procedures and Data Mapping File

<comment or description of the concepts in the table>

SGM_CORE_Project Details

CRV_ZGetProjectDetails

SGM_PROJECTMETRICS_15

Exec RSP_QV_GetProjectMetricsForGroupID 15

SGM_PROJECTMETRICS_62

Exec RSP_QV_GetProjectMetricsForGroupID 62

SGM_PROJECTMETRICS_94

Exec RSP_QV_GetProjectMetricsForGroupID 94

SGM_PROJECTMETRICS_108

Exec RSP_QV_GetProjectMetricsForGroupID 108

SGM_PROJECTMETRICS_18

Exec RSP_QV_GetProjectMetricsForGroupID 18

SGM_PROJECTMETRICS_46

Exec RSP_QV_GetProjectMetricsForGroupID 46

SGM_PROJECTMETRICS_109

Exec RSP_QV_GetProjectMetricsForGroupID 109

SGM_PROJECTMETRICS_63

Exec RSP_QV_GetProjectMetricsForGroupID 63

SGM_PROJECTMETRICS_64

Exec RSP_QV_GetProjectMetricsForGroupID 64

SGM_PROJECTMETRICS_65

Exec RSP_QV_GetProjectMetricsForGroupID 65

SGM_PROJECTMETRICS_66

Exec RSP_QV_GetProjectMetricsForGroupID 66

SGM_PROJECTMETRICS_103

Exec RSP_QV_GetProjectMetricsForGroupID 103

SGM_PROJECTMETRICS_104

Exec RSP_QV_GetProjectMetricsForGroupID 104

SGM_PROJECTMETRICS_69

Exec RSP_QV_GetProjectMetricsForGroupID 69

SGM_PROJECTMETRICS_111

Exec RSP_QV_GetProjectMetricsForGroupID 111

SGM_PROJECTMETRICS_105

Exec RSP_QV_GetProjectMetricsForGroupID 105

SGM_PROJECTMETRICS_65

Exec RSP_QV_GetProjectMetricsForGroupID 106

SGM_PROJECTMETRICS_110

Exec RSP_QV_GetProjectMetricsForGroupID 110

SGM_PROJECTMETRICS_124

Exec RSP_QV_GetProjectMetricsForGroupID 124

Transformation Rules (for each of the data source in the previous point): 

In the target state, additional filters to the data extract are required to be implemented in the result of the SGM_CORE_Project Details / CRV_ZGetProjectDetails query

    1. Extraction rules and filters:
      1.   Project Closed Date >= 3.5yrs
      2.   Project Closed = 0
    2. Exception handling rules (how do we handle when data does not come in the format we need) : Normal exception handling rules apply
    3. Enrichments (normally joins) 
    4. Aggregation rules

KPI's Definitions 

Budget and Cost File: Budget & Cost File: 2F250000.xlsm

KPI NumberKPI NameCalculation Description        1Forecast accuracy rate (act+ planned total [year N] (-[year N]actual cost/(act+ planned total [year N])

Budget & Costs File:

(Act.+Planned CAPEX) + (Act.+Planned OTC) = Act.+Planned Total

Actual Planned Total for the current year -(Current year Actual Cost/Actual Planned Total for the current year)  

2Operational time total (in days)NETWORKDAYS(Requested Start Date (PMO Gate) -end date)

Budget & Cost File:

Number of working days between Requested Start Date (PMO Gate)  and End date

3Operational time to date vs total (in %)if(IFERROR(NETWORKDAYS(Requested Start date (PMO Gate) ;today())/operational time total)>1;1;IFERROR(NETWORKDAYS(Requested Start date (PMO Gate);today())/operational time total))

Budget & Cost File:

if the number of working days between Requested Start date (PMO Gate) and today  divided by Operational Time Total KPI (NUMBER 4). If a value is returned, display that value otherwise if it shows an error just display 1

4Burn rate budget [year N]actual cost/act+ planned total [year N]

Budget & Cost File:

Actual Cost for the current year divided by the Actual Planned Total for the current year

5Burn rate vs burn rate time (in %) burn rate/operational time to date vs total

Budget & Cost File:

Burn Rate divided by Operational Time total

KPI 4 / KPI 5

6Operational time burn rateif (burn rate vs burn rate time>50%, "1 - Ahead of Schedule >50%";IF(burn rate vs burn rate time>30%;"2 - Ahead of Schedule >30%";IF(burn rate vs burn rate time>-30%;"3 - Linear";IF(burn rate vs burn rate time>-50%;"4 - Below Schedule 30-50%";"5 - Below Schedule more than 50%")

Budget & Cost File: 

If KPI 5 is greater than 50 %  display 1 - Ahead of Schedule >50%"

If KPI 5 is greater than 30 %  display 1 - Ahead of Schedule 30%"

If KPI 5 is greater than -30 %  display "3 - Linear"

If KPI 5 is greater than -50 %  display "4 - Below Schedule 30-50%"

else display "5 - Below Schedule more than 50%"

7Project (planned, ongoing or went life) with no approved budget but with some actualson Budget&cost file (coming from Accolade): column DO "total approved" is empty whereas column CI "status" is equal to on-going or went-live

Budget and Cost File:

Display a list of projects where the Total Approved amount is BLANK and "Status" is "On-going" or "Went Live"

8Carry over not plannedon Budget&cost file: column CI status = closed whereas still increase of actuals month after month (column EG)
closed projects with actuals after the closure date

Budget and Cost File:

Display the list of projects (+ number) with an increase of the budget

9Projects not yet started with a start date in the pastIdea&prospective not migrated into project with a start date in the past10Status update frequencystatus update frequency in number of projects
if(project to be considered="no";"";if(days since Last update ="";"6.never updated";if(days since Last update <31;"1.Less than 30 days";if(days since Last update <61;"2.between 30 & 60 days";if(days since Last update <91;"3.between 2 & 3 month";if(days since Last update <181;"4.beetween 3 & 6 month";"5.more than 6 month"))))))

Budget and Cost File:

Display a histogram of projects showing how frequently their status has been updated. 

if the project to be considered field  = NO, and the days since last update is blank = 1; the status =6 Never Updated 

if the project to be considered field  = NO, and the days since last update is < 31 ; the status = 1. Less Than 30 days

if the project to be considered field  = NO, and the days since last update is < 61 ; the status = 2. Between 30 and 60 days

if the project to be considered field  = NO, and the days since last update is < 91 ; the status = 3. Between 2 and 3 months

if the project to be considered field  = NO, and the days since last update is < 181 ; the status = 4 Between 3 and 6 months

else display 5. more than 6 months

11Finance update frequencyFinance update frequency in number of projects
updated=countifs('project to be considered;"yes";'financial uptodate;"1")
not updated=countifs('project to be considered;"yes";'financial uptodate;"3")
no KFD=countifs('project to be considered;"yes";'financial uptodate;"")

Budget and Cost File:

Display the number of projects where the financial status of the project has been updated

if the project to be considered field  = yes and the financial up to date field = 1; the status = Updated

if the project to be considered field  = yes and the financial up to date fiekd = 3; the status = Not Updated

if the project to be considered field  = yes and the financial up to date filed = blank; the status = No KFD

12On BudgetProject forecasts vs approved budget
below, above, on track

Budget and Cost File:

Display a histogram of Project forecasts vs approved budget

Status: below, above, on track

If forecast budget is below ref approved: Below

If forecast budget if above approved ref:  Above

If forecast budget if equal to approved ref: On Track

13On Timeon time: =countifs('project to be considered;"yes";'on time;"1")
slightly delayed=countifs('project to be considered;"yes";'on time;"2")
delayed: countifs('project to be considered;"yes";'on time;"3")

Budget and Cost File:

Display a histogram of the number of projects that are "On Time", "Slightly Delayed" or "Delayed"

The value of On Time  = 1

The value of Slightly Delayed  = 2

The value of Delayed  = 3

14Project close to over budgetend date<month date

Budget and Cost File:

Display a histogram of the List of projects where end date<month date

15Split Capex / OTC Approved vs forecast

Budget and Cost File: 

Display a histogram of the list of projects comparing Approved vs forecast

Visualization

Data & KPI User Story Deck

Graph name

Description 

Main DashboardSBS Project Portfolio: Project DetailsFinance -
  1. Split Capex / OTC
  2. Finance Update Frequency
  3. Burn Rate Budget
  4. Forecast Accuracy Rate
Finance /OperationalBurn Rate vs Burn Rate Time Finance + OperationOperational 
  1. Operational Time Total (in days)
  2. Operational time to date vs total (%)
  3. Operational Burn Rate
  4. Project (Planned, ongoing, went live) with no approved budget but with some actuals
  5. Projects not yet started with a start date in the past
  6. Carryover Not Planned
  7. Status Update Frequency
  8. On Budget
  9. On Time
  10. Project Close to Over Budget

PMO Dashboard AS-IS Visualisation:

Image Removed

PMO Dashboard TO-BE Visualisation:

Main Dashboard

Image Removed

Main Dashboard filters:

- roadmap
- accountable (Business)
- Product Manager/ Service Delivery Manager
- Platform/product
- Objective
- Project Manager
- Status
- Program
- Financial Treatment
- Project prioritization
- Start Quarter
- Monthly status date
- Financial up-to-date

KPI Page

Image Removed




6.0 System view (Architecture)

...


The purpose of this part is to describe the physical components that supports the functionalities of the product. From that point of view, this part should capture and visualizes the physical components of the data products such as backend, front end, data providers, libraries for ML models, etc. 


Functional Requirements


Requirement #RoleRequirement GroupRequirement TitleDescription/User StoryAcceptance Criteria
Data_Sourcing_1Data EngineerSourcingSource validated, complete and correct data from Accolade for the PMO dashboard visualisation

As an authorised SBS Dashboard user I want to have access to correct and complete data on the financial and operational status of SBS projects and programmes in the PMO Dashboard  

  • Data in the current state is migrated successfully to target state including all primary and secondary data
Visualisation_Dashboard_Main_2Visualisation and User Experience Create a Dashboard with Summary Table and Project Details (Main Dashboard)

As an authorised SBS Project Portfolio dashboard user , I need to see  the overview of financial and operational details of projects using multiple filters and by dimensions

  • The main dashboard shall display multiple visuals with:

    • The Programme/Project Manager Name
    • The Programme ID, Status, Number of Projects
    • The CAPEX by year, Total CAPEX
    • ....
  • Users shall be able to apply filters in the dashboard to see relevant year and details required


 

Visualisation_Filters_3Visualisation_Dashboard_KPI_1Visualisation and User ExperienceExperience - Dashboard Filter Implement filters to display relevant decision useful information for users  Create a KPI table/histogram for Project Forecast Accuracy Rate

As an authorised SBS

KPI dashboard

Dashboard user

,

I

need to see a table/histogram of projects with the forecast accuracy rate.
  • The SBS KPI dashboard shall display a table/histogram with:

    • A count of the number of projects
    • Column titled Months
    • Forecast Accuracy Rate
  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_KPI_2Visualisation and User ExperienceCreate a KPI table/histogram for Project Operational Time Total (Days) As an authorised SBS KPI dashboard user, I need to see a table/histogram of projects with the Operational Time in Days.
  • The SBS KPI dashboard shall display a table/histogram with:

    • Project ID
    • Program Name
    • Requested Start Date (PMO Gate) 
    • End Date 
    • Operational Time in days
  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_KPI_3Visualisation and User ExperienceCreate a KPI table/histogram for Project Operational Time to Date vs Total (in %)As an authorised SBS KPI dashboard user, I need to see a table/histogram of projects with the Operational Time total to date vs Total (in %)
  • The SBS KPI dashboard shall display a table/histogram with:

    • Project ID
    • Program Name
    • Requested Start Date (PMO Gate) 
    • Operational Time in days
    • Operational Time in days vs Total (in %)
  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_KPI_4Visualisation and User Experience

Create a KPI table/histogram for Burn Rate Budget

As an authorised SBS KPI dashboard user, I need to see a table/histogram of projects with the budget burn rate
  • The SBS KPI dashboard shall display a table/histogram with:

    • Project ID
    • Program Name
    • Budget Burn Rate
  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_KPI_5Visualisation and User ExperienceCreate a KPI table/histogram for Burn Rate vs Burn Rate Time (in %) As an authorised SBS KPI dashboard user, I need to see a table/histogram of projects with the budget burn rate vs Burn Rate Time (in %)
  • The SBS KPI dashboard shall display a table/histogram with:

    • Project ID
    • Program Name
    • Budget Burn Rate (in %)
  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_KPI_6Visualisation and User ExperienceCreate a KPI Histogram for Operational Time Burn Rate KPIAs an authorised SBS KPI dashboard user, I need to see a histogram of projects with operational burn rate
  • The SBS KPI dashboard shall display a histogram with:

    • Project ID
    • Program Name
    • Operational Burn Rate Time
  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_KPI_7Visualisation and User Experience

Create a KPI Histogram for Project (planned, ongoing or went life) with no approved budget but with some actuals

As an authorised SBS KPI dashboard user, I need to see a histogram of project (with Status) with no approved budget but with some actuals
  • The SBS KPI dashboard shall display a histogram with:

    • Project ID
    • Program Name
    • Operational Burn Rate Time
  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_KPI_8Visualisation and User Experience

Create a KPI Histogram for Project (planned, ongoing or went life) with no approved budget but with some actuals

As an authorised SBS KPI dashboard user, I need to see a histogram of project (with Status) with no approved budget but with some actuals

The SBS KPI dashboard shall display a histogram with

  • The Number of projects
  • Months
  • Total Actuals with No Approved Budget
  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_KPI_9Visualisation and User Experience

Create a KPI Histogram for Projects not yet started with a start date in the past

As an authorised SBS KPI dashboard user, I need to see a table of projects with a start date in the past that hasn’t began yet.
  • The SBS KPI dashboard shall display a histogram with:

    • Objective
    • Start Quarter
    • Platform Owner
    • Project Name/Name of Initiative
  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_KPI_10Visualisation and User Experience

Create a KPI Histogram for Project Status Update Frequency

As an authorised SBS KPI dashboard user, I need to see a histogram of projects showing how frequently their status has been updated.
  • The SBS KPI dashboard shall display a histogram with:

    • Project Count
    • Status Update Frequency
    • Month
  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_KPI_11Visualisation and User Experience

Create a KPI Histogram for Projects whose Finance Status is Up to Date

As an authorised SBS KPI dashboard user, I need to see a histogram of projects with finance status that is up to date.
  • The SBS KPI dashboard shall display a histogram with the below colour coded status:

    • No KFD
    • Not Updated
    • Updated
  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_KPI_12Visualisation and User Experience

Create a KPI Histogram for Project On Budget

As an authorised SBS KPI dashboard user, I need to see a histogram of projects with a project status is On Budget.
  • The SBS KPI dashboard shall display a histogram with the below colour coded status:

    • Forecast < Ref Approved
    • Forecast > Ref Approved
    • Forecast on track
  • The histogram shall have month-year on the X axis and % on the Y axis
  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_KPI_13Visualisation and User ExperienceCreate a KPI Histogram for Project is On TimeAs an authorised SBS KPI dashboard user, I need to see a histogram of projects with a the project status is On Time.
  • The SBS KPI dashboard shall display a table/histogram with:

    • Slightly Delayed
    • Delayed
    • On Time

The histogram shall have month-year on the X axis and % on the Y axis

  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_KPI_14Visualisation and User ExperienceCreate a KPI Histogram for Project Close To Over BudgetAs an authorised SBS KPI dashboard user, I need to see a histogram of projects with a project status is Close To Over Budget.
  • The SBS KPI dashboard shall display a table/histogram with:

    • Project ID, Name
    • Month
    • Platform Owner
    • Project Name/Name of Initiative
  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_KPI_15Visualisation and User Experience

Create a KPI Histogram for Project Split CAPEX OTC

As an authorised SBS KPI dashboard user, I need to see a histogram of projects split between CAPEX and OTC.
    • The SBS KPI dashboard shall display a table/histogram with:

      • Slightly Delayed
      • Delayed
      • On Time

    The histogram shall have month-year on the X axis and Amount on the Y axis

  • The Histogram will be split between CAPEX and OTC
  • The amount shall be displayed on the Histogram bars
  • Users shall be able to apply filters in the dashboard to see relevant year and details required
Visualisation_Dashboard_AuthorisationAccess and Authorisation

Restrict user access to dashboard

As an authorised SBS KPI dashboard Owner, I need access to the PMO dashboard and KPI dashboard restricted based on roles and business units.

Access to the dashboard shall be restricted using Single Sign On or any role specific authorisation protocol

Users are only able to see data relevant to their assigned profile

Non-functional Descriptions 

This part specifies criteria that describe the operation of the data product, rather than specific behaviours.  

Usability

Regulatory Compliance

...

  • The Dashboard will comply with Solvay’s regulations and compliance e.g., access only granted to authorized Users.
  • Maintenance data will be split between either SCO or ECO, and Users will only have authority to one Entity data

want to have the capability to display data and navigate the the SBS Project Portfolio dashboard using the following filters:

- Roadmap
- Accountable (Business)
- Product Manager/ Service Delivery Manager
- Platform/product
- Objective
- Project Manager
- Status
- Program
- Financial Treatment
- Project prioritization
- Start Quarter
- Monthly status date
- Financial up-to-date

 

Visualisation_Table_4Visualisation and User Experience - Dashboard Summary Table Display summary table of financial and operational status of projects and programmes

As an authorised SBS Dashboard user I want to have a summary table which contains the financial and operational status of projects/programmes, in the dashboard.

 

Visualisation_Filters_5Visualisation and User Experience - Additional Table Dimensions Create dimensions to filter project data

As an authorised SBS Dashboard user I want to have the capability to display data and navigate the the KPI Report Table on the SBS Project Portfolio dashboard using the following filters:

  • Activity
  • Applying Agile Methodologies
  • Controlling Allocation
  • Digital/IT Roadmap
  • GBU Function Ranking
  • Impact on SBS Recurrent
  • Impact on SBS recurrent amount
  • Impacted Teams
  • IS Relation Manager
  • PMO Classification
  • Program
  • Project Last Gate Decision
  • SBS Lead Team Operation
  • Secondary Activity
  • Sponsor

 

Visualisation_Filters_6Visualisation and User Experience - Additional Table Indicators Implement additional indicators filter for KPI Report Table

As an authorised SBS Dashboard user I want to have the capability to display data and navigate the the KPI Report Table on the SBS Project Portfolio dashboard using the following indicators:

  • CAPEX & Year (Today()-1)
  • CAPEX & Year (Today())
  • CAPEX & Year (Today()+1)
  • CAPEX & Year (Today()+2)
  • OTC & Year (Today()-1)
  • OTC & Year (Today())
  • OTC & Year (Today()+1)
  • OTC & Year (Today()+2)
  • TOTAL COSTS & Year (Today()-1)
  • ACTUAL COSTS & Year (Today()-1)
  • TOTAL COSTS

 

 

Visualisation_Table_7Visualisation and User Experience - KPI Report Table Implement colour coded visualisation display on KPI report table

As an authorised SBS Dashboard user I want to have the capability to display colour coded traffic light KPIs (Red, Amber Green) on the KPI Report Table:

  • On Budget
  • On Time
  • Financials Up To Date

 

Visualisation_Table_8Visualisation and User Experience - Dashboard Search Functionality Create search field to support dashboard filter

As an authorised SBS Dashboard user I want to have a search capability on the dashboard, to support the main filters 

  • SBS Lead Team Project
  • SBS Lead Team Operation
  • Impacted Teams
  • Impacted BUs
  • Start Quarter

 

Attribute_Change_9Data Maintenance - Attribute Correction Rename data fields on Dashboard

 

 


7.0 Non-functional Descriptions 

...

Please populate the relevant section and delete those that are not applicable.


7.1 Usability

Usability is about the ease with which a User can learn to start using the solution and the ease with which they can use the system.  In addition to ease of learning and ease of use, usability also includes areas such as ease of recall, error avoidance and handling, accessibility among others e.g., 99% of metadata entry Users who have use the Maintenance Dashboard should be able to change filters, extract etc., when required.  Maintenance data will be centrally stored in the Google Cloud platform, which will be available to other applications e.g., and Dashboards if needed.



7.2 Regulatory Compliance

Software systems must comply with legal and regulatory e.g., GDPR requirements, this can change depending on country, organisation industry and / or region.  The software systems must be secure from unauthorized access.  The Maintenance Dashboard will comply with Solvay’s regulations and compliance e.g., access only granted to authorized Users.

  • The Dashboard will comply with Solvay’s regulations and compliance e.g., access only granted to authorized Users.
  • Maintenance data will be split between either SCO or ECO, and Users will only have authority to one Entity data


7.3 Security

Security refers to essential aspects that assure a solution and its components will be protected against unauthorized access or malware attacks.  Important considerations related to security aspects of a system are User authentication, User authorization or User access privileges, data theft, malware attacks, data encryption, and maintaining audit trails, e.g., only Users with administrator access shall be able to create new accounts and assign data access privileges to the new accounts e.g.,

  • All data will be encrypted in the dashboard
  • Only authorised Users / Administrative Users will be able to access data.
  • Maintenance data will be split between either SCO or ECO, and Users will only have authority to one Entity data.


7.4 Performance

Performance defines how fast a software system or a particular section of it responds to certain User actions under a certain workload.  In most cases, this metric explains how long a User must wait before the target operation happens e.g., the page renders, a transaction is processed, etc., given the overall number of Users now.  Performance requirements may describe background processes invisible to Users, e.g., backup and speed of data transfers. 



 

7.5 Reliability

Reliability is the ability of a solution or its component to perform its required functions without failure under predefined conditions for a specified time / period.  Reliability can possibly be specified in terms of average time system runs before failure occurs, percentage of operations completed successfully within a time / period, maximum acceptable failure probability, or number of failures within a period.  Reliability aspects are in reference to (but not limited to) evaluation of the system to be considered as reliable, classification of reliability defining failures vs. regular failures, and the impact of failure on business operations.  The Maintenance Dashboard will display data from the previous refresh of data.   



 

7.6 Scalability

Scalability refers to the degree to which a solution can evolve to handle increased amounts of work.  The increased amount of work could be in terms of the user base, transactions, data, network traffic, or other factors e.g., the system should be able to handle an additional load of a maximum of 5,000 Users every month for the next 6 months without any noticeable performance impacts.  



7.7 Compatibility

Interoperability is the degree to which the solution is compatible with other components.  It is a measure of how effectively the system interoperates with other software systems and how easily it integrates with external hardware devices.

Interoperability aspects to be discussed during elicitation are in reference to (but not limited to) software systems to be interfaced with along with data / messages to be exchanged and any standard data formats, hardware components to be integrated with, and any standard communication protocols to be followed e.g., Order Management system will push the order file into a secured file transfer protocol server from where it will be loaded into the system through a daily job.  To guarantee between Google Cloud platform and SAP BW Queries e.g., BW_QRY_MVPMOR01_0002, Solvay has introduced a new tool called Xtract (Xtract).



 

7.8 Availability

Availability is the degree to which the solution is operable and accessible when required. It is a measure of time during which the system is fully operational e.g., available for use and sometimes included as a Service Level Agreement (SLA) considering its criticality to the business, e.g., the system shall be at least 99% available on weekdays between 09:00 to 18:30 Central European Time (CET).



7.9 Refresh of the Data

Frequency, data, and time of the data refresh in the data product. 

Data shall be sourced from the Accolade database 4 times per day (CET) => 6am, 12am, 6pm and 12pm

Tableau refresh in PREPROD and PROD => 4 times per day (CET) => 6:15am, 0:15am, 6:15pm and 12:15pm

Performance

 

Reliability

 

Scalability

Compatibility

 

Availability

Refresh of the Data

Data shall be sourced from the Accolade database 5 times per day



Storage of the Data

  1. The final copy of the sourced data shall be stored on a daily basis
  2. Stored data shall be made available on request by an authorised user within the PMO team with appropriate permissions.

...