excerptArea: Perform Costing Monthly Closing
previous Operation(s):
| Tip |
Rules & Glossary: Costing - Rules Costing - Glossary Costing - SAP Operation| Panel |
|---|
| bgColor | #f2f2f2 |
|---|
| titleColor | #ffffff |
|---|
| borderWidth | 1 |
|---|
|
Guideline |
| Expand |
|---|
| title | I verify that the previous dependent steps have been performed |
|---|
|
During the month several costs have been posted in PM orders that have an impact on the profit & loss statement and on the balance sheet for fixed assets. At this stage the settlement of these costs should be done under this Operation in order to ensure that all PM orders are settled properly at the month end. |
| Expand |
|---|
| title | I perform the settlement |
|---|
|
| Include Page |
|---|
| SAPCost:KO8G - Orders settlementSAPCost: |
|---|
| KO8G - Orders settlement |
|---|
|
|
| Expand |
|---|
| title | I verify that there is no error |
|---|
|
| Include Page |
|---|
| SAPCost:KO8G - Display errors in orders settlementSAPCost: |
|---|
| KO8G - Display errors in orders settlement |
|---|
|
| Warning |
|---|
If there are messages, inform the local PM contact that must solve the problem Once the local PM contact informs that the problem was solved, the settlement must be performed again |
|
| Expand |
|---|
| title | I check that orders are properly balanced |
|---|
|
| Include Page |
|---|
| SAPCost:S_ALR_87013127 - Check that orders are settledSAPCost: |
|---|
| S_ALR_87013127 - Check that orders are settled |
|---|
|
| Warning |
|---|
If some orders are not settled, a deeper analysis must be performed. If necessary orders must be settled again (it can also be done individually if there are few orders with KO88 - Individual orders settlement) |
|
| Expand |
|---|
| title | I check that the task has been executed |
|---|
|
If all PM order have been settled (all have zero balance) means that this operation was successfully done. |
Next Operation(s):
The settlement of WBS can be initiated - Refer to OP.005.