INTRODUCTION
Objectives and scope of this procedure
This Operating Procedure explains how to create a Recurring PO (Order Type: ZFO for WP1) and Invoicing Plan (Order Type: NB for PF1) and send to the supplier for re-occurring services to be provided at the specified date and location.
Who uses this document? |
|---|
What is the nature of the need | ||||||
|---|---|---|---|---|---|---|
| What provisioning channel does this document concern? | |||||||
|---|---|---|---|---|---|---|---|---|
User / PR creator | Approver | LPR/ | PS | Goods | Services | e-catalogue |
Goods managed in |
Stock | Goods and services – spot buys | Goods on Contract | Services on Contract | Emergency cases | Urgent needs |
| X | X |
| X | X | X |
Applicable to system WP1 (RCS) and PF1 (PRS).
Material groups in scope
- The purchase orders in scope are related to: Industrial Services Only. Purchases under Contract or estimated as a annual budget, the expense can range from Utilities/ General Expense (Photocopy Rental/ House Rental)/ TG & TS
Process step described in this procedure and expected end product
End product : |
Abbreviations
Abbr. | Description | Abbr. | Description |
PR | Purchase Requisition | SC | Shopping Cart |
ZFO | Framework Order | PtP | Procure to Pay |
RFQ | Request for Quotation | PS | Provisioning Specialist |
ACK | Acknowledgement | GR | Goods Receipt |
...
STANDARD OPERATING PROCEDURE DESCRIPTION
Pre-requisities
In order to generate a ZFO (WP1), a proper PR must be created and available in ME57 ready for conversion.
A proper PR will consist of the following below:
- Attached with the selected vendor's quotation
- Correct duration and pricing being stated in the PR
- Vendor code being setup and ready to be tagged to the PO
PO Creation
Please go to transaction ME57.
...
# | Main activities | Key points | Tips / Best practices |
37 | Click on the droplist button at the Output Type |
|
|
38 | Select the proper Output Type from the droplist | Select "ZNE1" | Output Type for PF1 and other countries |
39 | Click on the droplist button at the Medium |
|
|
40 | Select the type of Medium from the droplist | Select "Simple Mail" |
|
41 | Click on the droplist button at the Function |
|
|
42 | Select the type of Function from the droplist | Select "MZ" | Function Type for PF1 and other countries |
43 | Click on the droplist button at the Language |
|
|
44 | Select the type of Language from the droplist | Select "EN" |
|
...
# | Main activities | Key points | Tips / Best practices |
45 | Click on the Continue Button | This error message pops up due to lack of email address to send out this PO. Hence, we will key in the email address manually. | Email address can be entered into the RCS system via mn05 to prevent this textbox from popping out. |
# | Main activities | Key points | Tips / Best practices |
46 | Enter the message into this textbox and it will appear in the body of the email |
|
|
47 | Enter all parties to receive this email |
|
|
48 | Click on the Back Button twice to return back to the initial page | If there are other attachment required to be send to the supplier, you may follow the steps below. |
|
# | Action | Key points | Tips / Best practices |
1 | Click on the Create Attachment Button |
|
|
2 | Select the file required to be attached and click on the Open Button |
|
|
...
# | Main activities | Key points | Tips / Best practices |
49 | Click on the droplist button for the selection of Dispatch Time |
|
|
50 | Select the mode of dispatch time required | Choice no.1 is preferred as it will help to lessen the load for the network as per advised by our IT professionals. |
|
51 | Click on the Back Button to return back to the initial page |
|
|
# | Main activities | Key points | Tips / Best practices |
52 | Click on the Check Button to see if there is any error in the PO at #52i | If there is no error in the PO, a text message will appear at the bottom at #52ii |
|
53 | Click on the Save Button |
|
|
After saving, the message of PO being created successfully will be displayed at the left bottom. The email will be sent to the respective parties stated at Step #36.
...
APPENDIX
INVOICING PLAN CREATION
# | Action | Key points | Tips / Best practices |
53 | Go to 'Invoice' Tab and uncheck GR-based IV | This enables the invoice to be posted without the GR |
|
54 | Go to 'Delivery' Tab and uncheck Goods Receipt | This allows no Confirmation to be created inside SRM7 |
|
anchor
# | Action | Key points | Tips / Best practices |
55 | Click on Invoicing Plan |
|
|
56 | Enter 'Start Date' of the Contract |
|
|
57 | Enter 'End Date' of the Contract |
|
|
58 | Select the appropriate code (51 – represents 'Monthly on Last of Month') | This affects the date of 'Account Settlement' (the date that the invoice is to be paid) |
|
59 | Select the appropriate code (52 – represents 'Horizon 1 Year') | This affects the 'Invoice Date' (the date of the invoice) |
|
60 | Check 'In Advance' | Invoice is created in advance |
|
REFERENCES
ATTACHMENTS
| View file | ||||
|---|---|---|---|---|
|
End of document