Status colour Green title STEP 1
Once a year, when the control IAC 01.09 is completed and uploaded in WP1WP2.
- Copy the result of the sheet "2d-Activity TOTAL" and paste the result in the tab "IAC 01.09"

Status colour Green title Step 2
Update the sheet "CC variance" and enter:
- the list of production cost centers
- the column "normal capacity (year)"
- the column "Budget (month)" - usually it is equal to the column "Normal capacity (month)"
- the column "standard capacity (h) (year)"

Status colour Green title Step 3
Each month, you have to update the actual costs & hours.
The price variance & the absorption variance will be automatically calculated

Status colour Blue title Step 4
For the monthly update use the transaction S_ALR_87013611
Enter
- the controlling area
- the period
- the group of production cost centers

Status colour Blue title Step 5
- Production cost centers
- Actual fixed costs
- Plan costs from IAC 01.09 (local currency)
- Actual hour
- Normal capacity from IAC 01.09 (h)

Status colour Blue title Step 6
Report the actual costs of each cost center per activity
![]()

Report the actual hours of each cost center per activity

Status colour Blue title Step 7
Once the file is completed, the price & absorption variance can be reported in the variance analysis template
Image Added