| Tip |
|---|
Responsible : Physical inventory manager Frequency : Annual with a quarterly up-date Control : IAC.02.03 / control owner: FRA | For an example and a blank template of annual planning ==> 7. Example of documents to be used / a. Annual planning |
|
Inventory Planning & SchedulingPhysical counts or cycle counts must be conducted at least once annually for all materials. With limited exception (see exceptions section) the sites that perform a Full Periodic (Wall-to-wall) inventory must complete them between July and November each year[1]. Cycle counts may be performed in addition to the annual Full Periodic counts.. FRA validates and publishes updated physical inventory planning prepared by PIM and considering that: - Recommended 90% of the physical inventory count (in value of items) be done by the end of September
- 100% of the physical inventory count (in value of items) must be done by the end of November, including all external storage (Hard Closing)
Exceptions: - The period can be extended/ modified if requested by the external Audit team. The need for date modification must be approved by the Group Controller.
- Furthermore, for the sites that perform Cycle counting they must;
- By November 30th, references counted must represent at least 80% of the total value of industrial supplies inventory.
The annual planning must include a list of all the inventory storage location (on site / off site), the frequency of cycle counts, a detailed planning taking into account the above objectives
[1] The site must maintain an auditable roll forward from the date of the inventory to the reporting period date.
The annual planning includes : 1. A list of the inventory storage location - On site
- Off site: inventory on consignment, held in third parties facilities or by toll manufacturers
2. Frequency of cycle counts, if applicable - All storage locations divided by count date;
- Inventory planning has to be prepared targeting 100% of Inventory counted at the end of reference period;
3. A planning taking into account the following objectives
Cycle Counting - A count of items representing 100% of end inventory should be done as of of 30th November (in number of itemsvalue), each year (including external Storage) For Cycle counting Full Physical Counting - A count of items representing 100% of end inventory should be done as of of 31 December (in number of itemsvalue), each year (including external Storage) For Full Physical Couting.
Specific for Industrial Suplies - By November 30th, references counted must represent at least 80% of the total value of industrial supplies inventory.
- The rest 20% of references of the total value must be counted by either sampling counting method every year or cycle counting method every 3 years
That planning must be communicated to FRA, who could organize/support the supervision by a third party without prior notification to PIM. 4. Cycle Counts rules - Cycle counts have to start before July 1st of each year, otherwise Full Inventory count will have to be executed at the plant;
- ABC Classification method has to be implemented for a complete cycle count model implementation for spare parts;
| Warning |
|---|
Planning is proposed by PIM and validated by FRA before end of September with consideration for 2 periods (cycle count) : - October 1st to November 30 November of current year : revision of on going calendar :
- Starting with actual inventory coverage rate as of October 1st (in theory 90%)
- Showing completion of 100% target as of November 30
- Dec 1st of current year to November 30th of following year :
- That planning is detailed by material code and SAP plant where applicable
- Where SAP isn’t available, that planning is also used to follow progress of coverage inventory count
- FRA is responsible for recording that planning in the dedicated group repository and external auditor have access to that repository
Planning is proposed by PIM and validated by FRA before end of July (Full Physical Count) : - january 1st to Dezember 31th of current year : revision of on going calendar :
- Showing completion of 100% target as of Dezember 3130TH
- Dec 1st of current year to November 30th of following year :
- That planning is detailed by material code and SAP plant where applicable
- Where SAP isn’t available, that planning is also used to follow progress of coverage inventory count
- FRA is responsible for recording that planning in the dedicated group repository and external auditor have access to that repository
|
|