Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Status

Page Status

OwnerAntonio Zappone 
Stakeholders Gilles Madjarian, Selim Ulhasan

Issue

Decision A decision is required as the to when to deploy the new S4S/HANA 4HANA In-House-Bank that will replace the existing solution in the separate PI1 SAP system. 


Recommendation

Option E:

    

Defer the deployment of In-House Bank functionality for all GBUs and Entities until after the second group go-live.

Note

This Conceptual Design recommendation will be re-assessed during Detailed Design when more information will be available to support a decision. Options B, C, and E will form part of the reassessment. Any long lasting impacts on S/4HANA from the legacy interim IHB requirements will also be considered at this time. 

 

Example: (below is an indicative timeframe to illustrate the deployment option).

Image Added


This is the lowest-risk option in an area that is considered higher risk. Payments and cash collection are critical processes.  There are additional layers of complexity which include running an in-house-bank, and developing and proving the correctness of the complex custom solutions to support the internal factoring process.

The recommended option has a fallback and contingency option with the ECC/PI1 IHB, allows time for integrated process to stabilize, and also allows for production simulations. This is relevant for all entities.

Interim interfaces are required, which adds complexity, however these interim interfaces are required in most of the deployment options.  The interim interfaces in this option will be developed based on the existing interfaces from PF1/WP1 to PI1, hence they are not new design, although they will have to be adapted for the new S/4HANA system.  Where interim interfaces between PI1 and S/4HANA would have already been built for group 1, extending these interfaces for group 2 will be easily manageable.

Deferring the deployment requires project resources for a longer period of time, which equates to additional cost.   Required resources will be largely limited to IHB consultants and technical developers.  This cost may be mitigated to some extent, however this will be determined within the roadmap and overall project planning.  Any additional cost will be outweighed by the risk mitigated. 

Payments outside of IHB will go-live with the groups as per the release plan. These payments will continue via Bank Communication Management (BCM), and they will draw out any issues prior to the larger volume/value payments commence via IHB. 

Being outside of the go-live of the main group/s, it can be expected that the cut-over outage will be shorter, resulting is a shorter payment outage which will be easier to manage. 

Defer period of 3 to 6 months, alignment with the deployment roadmap and business available months will also be required.

Further details on this option, and how it compares to alternatives is available in the evaluation section.


Background & Context


This KDD is focused on the deployment approach for the new S/4HANA IHB.  The IHB processes and customization are in scope for the ERP rebuild project. These processes will be reviewed in the detailed design phase, with the aim to streamline and simplify where possible. 

For clarification purposes, the Treasury application Quantum is out of scope for the ERP rebuild project.  Where required, interfaces between S/4HANA and Quantum are in scope.


In-House Bank

The existing IHB within ECC resides in PI1, within the legal entities Syensqo SA (SSA), and Solvay Finance America (SFA)

Background & Context

In-House Bank

The existing IHB within ECC resides in PI1, within the legal entities SSA and SFA.  SSA and SFA entities also reside in PF1 for all non IHB processes.  Interfaces are current in place to link PF1 and WP1 to the IHB in PI1

All entities are mandated to participate in the IHB process, except where it's not legally possible .  For example, China is not part of the IHB due to legal restrictions.(for example China). 

Interfaces are currently in place to link PF1 and WP1 to the IHB in PI1. 

SSA also reside in PF1 for all non-IHB processes. 


Internal Factoring

A high level of complexity exists with IHB largely due to the internal factoring process. Internal factoring brings benefits in the way of; 

  • Tax cash advantage of ~3 m€ per year for Syensqo
  • Native centralisation of the cash flows onto Syensqo SA and SFA without the need to pool further
  • Centralisation of the FX exposures that enable centralised and efficient hedging over the largest exposures possible
  • Centralisation of the collection and credit risk allowing to streamline the CCT activities (Note: should be shared with CCT)

  • Centralisation of the vendor payments allowing the streamline the A/P and Payroll activities (Note: should be shared with A/P and HR-Payroll)
  • Internal factoring is not a common process and not supported by standard SAP, hence the current solution requires numerous complex custom developments.  To The "to-be" design will aim to streamline and simplify, however it is expected that some level of custom developments will still be required. 


    Risk

    Cash movements related to payments and receipts is a higher risk area of any ERP implementation. The internal factoring complexity increases the risk. 

    Risk is a major factor in the recommendation and decision of this KDD.


    Assumptions

    IHB and internal factoring will continue in S4S/HANA4HANA.

    Entities not operating within the IHB will go-live with Bank Communication Management (BCM) in line with Overall project release\/s.


    Constraints

    Nil 


    Impacts

    Depending on the approach, The recommendation will require the creation of interfaces from S4S/HANA 4HANA to PI1 require consideration. If they are required, the existing interfaces from PF1 \ WP1 will need to be replicated for S4/HANA.the PI1 system that is hosting the legacy In-House Bank functionality. These interfaces are only required for the duration between the S/4HANA go-lives and the replacement of the IHB functions in PI1 with S/4HANA. Following the go-live of IHB in S/4HANA, these interfaces become obsolete and their code must be removed from S/4HANA. Their design and implementation must therefore be done in a way that facilitates clean removal. 

    The new Consolidations tool will go-live in with the last release.  This requires considerations second group. Considerations is required for the Consolidation of the entities and processes within PI1.


    Business Rules

    Participation in the IHB will continue to be mandatory unless not legally supported.


    Options considered

    Early deployment (prior to the main S4S/4 HANA releases) of IHB was considered, however due to the impact of extending the overall ERP project timeline, and earlier transfer of master data, this option was not review reviewed in this KDD.  

    IHB is a high risk, mitigating that risk is a critical factor as when compare options.

    Option A:

    Defer the deployment of IHB for all GBUs\Entities until after the second group go-live. 

    Defer by 3 to 6 months (need to align with deployment roadmap and business available months).

    Image Removed

    • Lowest risk option. IHB is a high risk \ high complexity process.  This option allows for a fall back \ contingency. 
    • Allows time to integrated process to stabalise.
    • Allows the option of production simulations.
    • Interfaces need to be built between the S4/HANA and PI1, although these will largely be replications of existing interfaces.
    • Additional cost expected with relevant resources required for an extended period.
    Option B: 

     Deploy IHB  for all GBUs/entities along with  the first group of the phased deployment.

    This option entails the new IHB being deployed for all entities, and execution with the first group of the release plan. 

    Example: (below is an indicative timeframe to illustrate the deployment option).

    Image Added

    Main Points (further details are in the evaluation section). 

    • Higher risk option, with no ECC/PI1 fall back / contingency option, no time for overall system and process stabilization and no opportunity for production simulations.
    • New interfaces required from ECC to S/4 HANA. These will be newly designed interfaces and not replication of existing interface functionality.    


    Option B: Deploy IHB   for live GBUs/entities in-line with the  groups of the phased deployment (Two IHBs).

    This option entails deploying the new IHB in-line with the groups in the release plan. One\/existing IHB in PI1 for entities still on ECC, and a second\/new IHB for GBUs\/entities that have transitioned to S4S/4 HANA.

    Example: (below is an indicative timeframe to illustrate the deployment option).

    Main Points (further details are in the evaluation section). 

    • Higher risk option, with no ECC/PI1 fall back / contingency option, no time for overall system and process stabilization and no opportunity for production simulations.
    • Running two IHB can will increase complexity and possibility of errors.
    • Additional business resources will be required

    Option C: Deploy IHB for all GBUs/entities along with the first group of the phased deployment.

    This option entails the new IHB being deployed for all entities, and execution with the first group of the release plan. 

    Image Removed

    • Highest risk option 

      

    • .   

      

    Option D:

    Option C: 

    Deploy IHB for all GBUs/entities along with  the second Group of the phased deployment.

    This option entails the new IHB being deployed for all entities, and execution with the second group of the release plan.

    Example: (below is an indicative timeframe to illustrate the deployment option).

    Main Points (further details are in the evaluation section). 

    • This was seen at the best as a viable alternative, however the recommended Option A E is preferred due to additional de-risking.
    • Risk mitigation (fall back contingency, overall system and process stabilization and production simulations are available for Group 1 Entities, but not the whole organization.
    • Payments via BCM will draw out issues prior to IHB deployment - this is limited to group 1 entities.


    Option

    E

    D:  Deploy IHB for all GBUs/entities along with  the All-in one deployment.

    This option entails the new IHC will be deployed at the same time as all GBUs\/Entities as part of the all-in one deployment approach.

    Example: (below is an indicative timeframe to illustrate the deployment option).

    Main Points (further details are in the evaluation section). 

    • This option is low complexity but higher risk.
    • Interim interfaces are not required.
    • The robust de-risking options mentioned in this document are not available with this option. Alternative risk mitigation will need to be determined, for example additional testing.
    • No interim or alternate consolidation processes required for PI1.

    Option E: Defer the deployment of IHB for all GBUs/Entities until after the second group go-live.  

    Defer by 3 to 6 months (need to align with deployment roadmap and business available months).

    Example: (below is an indicative timeframe to illustrate the deployment option).

    Image Added


    Main Points (further details are in the evaluation section). 

    • Lowest risk option. This option has a fall back / contingency option with the ECC/PI1 IHB, allows time for integrated process to stabilize,and also allows for production simulations. Relevant for all entities.
    • Payments via BCM will draw out issues prior to IHB deployment - this is relevant for all entities.
    • Interfaces need to be built between the S/4 HANA and PI1, although these will largely be replication of the existing interface functionality, and adjusted for master data changes.
    • Interim interfaces between PI1 and S/4 HANA would have already been built for group 1, extending these interfaces for group 2 will be easily manageable. 
    • Additional cost expected with relevant resources required for an extended period. This cost is seen to be outweighed by the risk it mitigates.


    Evaluation


    LowHighLow

    Option A
    Deploy IHB for all GBUs/entities along with the first group of the phased deployment
    Option B
    Deploy IHB for live GBUs/entities in-line with the groups of the phased deployment (Two IHBs).
    Option C
    Deploy IHB for all GBUs/entities along with the second Group of the phased deployment.

    Option D
    Deploy IHB for all GBUs/entities along with the All-in one deployment.

    Option E

    Defer the deployment of IHB for all GBUs/Entities until after the second group go-live.

    Option A
    Option B
    Option C
    Option D
    Option E

    De-risk level

    • Strong Contingency \ Robust contingency / fallback option

    (plus) PI1 IHB will be available to as a contingency should there be significant issues with the S4/HANA IHB. (minus) PI1 not a possible fall back.

    (minus) PI1 is not a possible fall back.   

    (plus) Phased transitioned entails less entities go-live in first phase is a lower risk. if there is a significant issue, it will only impact the entities which have transitioned to S4S/HANA4HANA

    (minus) PI1 not a possible fall back.

    (plus) PI1 IHB will be available to as a contingency should there be significant issues with the S4S/HANA 4HANA IHB.  (only for group 1 entities)

    (minus) PI1 not a possible fall back.

    High

    Medium

    (plus) PI1 IHB will be available to as a contingency should there be significant issues with the S/4HANA IHB. 


    Low

    Medium

    Medium

    Low

    High


    De-risk Level

    • Stabilisation on Stabilization of integrated process (Sales\/Accounts Receivable, Payments\/Accounts Payables)
    (plus) Integrated processes will have had time to stabilise.(minus) No additional time for integrated process processes to stabilisestabilize, and higher probability of integration issues.

    (minus) No additional time for integrated

    process

    processes to

    stabilise

    stabilize, and higher probability of integration issues.

    (plus) Integrated processes will have had time to stabilisestabilize, (for GBUs\/Entities from group 1).(minus) No additional time for integrated process processes to stabilisestabilize, and higher probability of integration issues.(plus) Integrated processes will have had time to stabilize.LowLowMediumLowHigh

    De-risk Level

    • Payments outside of IHB will draw out issues
    (minus) IHB and BCM will go-live together. No opportunity for BCM to draw out issues in advance.

    (minus) IHB and BCM will go-live together. No opportunity for BCM to draw out issues in advance.

    (plus) Non-IHB payments via BCM will draw out issues prior to IHB deployment.  

    Relevant for group 1 entities.

    (minus) IHB and BCM will go-live together. No opportunity for BCM to draw out issues in advance.

    (plus) Non-IHB payments via BCM will draw out issues prior to IHB deployment.  

    Relevant for all  entities.

    LowLowMediumLowHigh

    De-risk level

    • Ability to run Productions Simulations
    (plus) Production simulation possible, for all entities, which contributes to lowering the risk.
    (minus) Unable to execute production simulations prior to go-live.(minus) Unable to execute production simulations prior to go-live.(plus) Production simulation possible, for group 1 entities, which contributes to lowering the risk.(minus) Unable to execute production simulations prior to go-live.(plus) Production simulation possible, for all entities, which contributes to lowering the risk.LowLowMediumLowHigh

    Less Complexity

    • Less Interfaces or lower complexity interfaces

    (minus) Requires interfaces to be built for integration of PI1 with S4/HANA. Interfaces are required for all GBUs\Entities.

    Interfaces will be based on existing ECC
    • interfaces
    already in place.

    (plus) New interfaces are not required for PI1 to S4/HANA

    (minus) New interfaces are required for integration of ECC (WP1) with S4S/HANA4HANA, for GBUs\/Entities transitioning in Group 2. 

    New interfaces need to be designed and built for Group 2 entities in order to match ECC with the new S4S/HANA 4HANA design.

    (plus) New interfaces are not required for PI1 to S/4HANA


    (minus) New interfaces are required for integration of PI1 with S4S/HANA4HANA, for GBUs\/Entities transitioning in group 1. 

    Interfaces will be based on existing ECC interfaces already in place.

    (plus) New interfaces are not required for PI1 to S4/HANA

    Medium

    High

    Low

    to S/4HANA


    (minus) Requires interfaces to be built for integration of PI1 with S/4HANA. Interfaces are required for all GBUs/Entities.

    Interfaces will be based on existing ECC interfaces already in place.

    Interfaces for Group 1 would already be built, extension to Group 2 will be required. 

    Low

    High

    Medium

    High

    Medium


    Less Complexity

    • One IHB Operating is less complex than two IHB in operation 

    (plus) One IHB Operating

    Less complex, less chance or errors

    (minus) Two IHBs Operating

    More complex, high chance or errors

    (plus) One IHB Operating

    Less complex, less chance or errors

    (plus) One IHB Operating

    Less complex, less chance or errors

    (plus) One IHB Operating

    Less complex, less chance or errors

    High

    Low

    High

    High

    High


    No additional Resource Cost

    (minus) With the go-live of IHB deferred, relevant project resources will be required for an extended period.

    (plus) No additional project resoure resource costs.
    (plus) No additional project resoure resource costs.(plus) No additional project resoure resource costs.(plus) No additional project resoure resource costs.

    (minus) With the go-live of IHB deferred, relevant project resources will be required for an extended period.


    HighHighHighHighLow
    Lower business resource impact(plus) No additional\/adverse impact on business resources

    (minus) Additional resources likely required to run two IHBs. 

    (minus) Business resources will likely need to perform manual clearing to payment sub-ledgers.

    (plus) No additional\/adverse impact on business resources(plus) No additional\/adverse impact on business resources.(plus) No additional\/adverse impact on business resources.HighLowHighHighHigh
    Ease of Consolidation

    (minus) Consolidation of the entities on PI1 will require an interim solution, for new Consolidations Tool.

    Standard process to load into Consol are expected to be utilised

    (minus) Consolidation of the entities on PI1 will require an interim solution. Utilise existing approach into BFC Consolidation Tool.(plus) Consolidations will follow the normal "interim" process for BFC Consol.

    (minus) Consolidations will follow the normal "interim" process for BFC Consol.

    Challenge is that there are two IHB entities (PI1 and S/4HANA) to consolidate. This is similar to the existing process with PI1 & PF1.

    (plus) Consolidation will follow the new Consolidation process, no interim process required.

    (plus) Consolidation will follow the new Consolidation process, no interim process required

    (plus) Consolidations will follow the normal "interim" process for BFC Consol

    .

    (minus) Consolidation of the entities on PI1 will require an interim solution, or for the new Consolidations Tool  .

    Standand Standardized process to load into Cosnsol are Consolidation system expected to be utilised(plus) Consolidation will follow the new Consol process, no interim process required.utilized.

    Challenge is that SSA will existing in PI1 and S/4HANA

    HighMediumMediumHighHighMediumHigh
    Lower Cut-over impact (less payments outages).(plus) One payment outage as only one cut-over is required.(minus) Two payment outages to manage.(plus) One payment outage as only one cut-over is required.(plus) One payment outage as only one cut-over is required.

    (plus) One payment outage as only one cut-over is required.

    A shorter cut-over outage for payments.

    HighLowHighHighHigh

    See also


    Attachments
    previewfalse
    patterns^(?!.*\.(png|jpg|jpeg|svg)$).*
    sortOrderdescending

    Change log

    Change History
    limit10

    Workflow history

    Workflow Report
    parent@self
    hideheadertrue
    typeapprovals