Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Status
colourBlue
titleStep 1

Step 1:  Open the ZWPP40A transaction

Click on Image Removed

file.


Choose the

variant /RCS-CO
  • Enter the plant
  • Enter the period
  • Execute Image Removed

     

    Image Removed

    authorization scope and the period / fiscal year

    SCOPE : SCO


    Image Added


    Status
    colourBlue
    titleStep 2

    Control that ZWPP40A the report BW = KE30

    If there is a discrepancy, you must investigate and open a user request to get the support of a SAP expert

     

    Image Removed

     

     

    :
    Total column P = D05
    Total column Q = E05
    Total column R = F05






    Status
    colourBlue
    titleStep 3

    You can change the lay-out

     

    Image Removed

     

     

    Status
    colourBlue
    titleStep 4

    Export the report in excel 

     

    Image Removed

     

     

    Status
    colourBlue
    titleStep 5

    List the products that generate the main variances 


     

     




    Status
    colourBlue
    titleStep 64

    Explain the main variances

     


    a. structure: Production version change / Raw material / Recycling / Others

    How to read this variance ? 

    • Material 53789 TY A 218 V30 BLACK 34NG XXXX was produced with a different production version than the one used for the costing
    • In the production version (B332) used for the costing, it is forecasted to produce one batch in 18,239 hours. But this material was produced in 17,90 h on an other production line.

    It creates the following variance on process order : 

    b. yield: RM consumption is higher or lower than std quantity 

    How to read this variance ?

    • The actual time (96 h) to produce material 64712 PA 66 MOLTEN POLYMER is higher than the standard time (84,261h)
    • It creates the following variance on process order : 

    c. purchased vs produced: material is purchased instead of produced or vice & versa 

    How to read this variance ?  

    • Material 63324 is supposed to be produced but it was purchased 
    • As it is purchased, the production cost = 100 % CP while in the costing the production cost is splited into CP / CNP / AMO

    d. subcontractor: Material is produced by a subcontractor instead of an internal production 

    How to read this variance ?

    • Same principle as the previous variance
    • When a material is produced by a subcontractor instead of an internal production

    e. others: to be commented



    Status
    colourBlue
    titleStep 75

    Fill in those information in « variance template » tab

     

    Image Removed


    Image Added




    Status
    colourBlue
    titleStep 6

    When there are recurring performance variances, they can be listed in the sheet "Perf. analysis"

    Image Added