  • Prod: Quantity planned to be produced in the resource in that period (Planned orders & Process orders)
  • Stream (85%) : OEE which is 85 by default → the capacity is multiplied with Stream 
  • Capacity: number of hours available in the period
  • Cap. Con: The hours allocated on the resource
  • Capa cons %: % if capacity utilization 


Source of the DATA from SAP 

CM07 : Available capacity in SAP can be reviewed through the transaction 


Choose the Layout ZPLAN01_2  

Choose a workcenter and a plant 

Click on standard overview 

ZWPPT042 : 

The capacity planning query is fed by the table ZWPPT042.

Once a day the table is created as a snapchat of the planned orders and process orders.

Choose As MRP elmnt ind. :

PA should be chosen for Planned orders 

FE should be chosen for Process orders 

Choose the plant 

Choose the snapshot as DAY                               

Table lists all of the planned and process orders which feed the capacity planning reporting. 

The differences from SAP & report may come from the fact that the table is created once a day. If the orders are created afterwards, will not be reflected on the table. 

...