OwnerAntonio Zappone
StakeholdersGilles Madjarian Tonda

Tondo

Issue

A key decision is required on when to deploy the new consolidations Consolidation tool.  Along with a multiphase ERP implementation comes options on when to deploy, whether in Phase Release 1, 2 or Xn.


Recommendation

New the The new Consolidation Tool will to be deployed in the later Phaselast Release.  The exact phase release timing will be concluded when the overall project Deployment Approach is finalised (estimated to be August 2024). 


Background & Context

BFC (Business Objects Financial Consolidation) is the current consolidations tool. This is an SAP system however it is not fully integrated with the EPRsSAP ERPs, rather data is loaded from the source EPRsSAP ECCs.  Data loads are via flat files that are produced with automation tools (RPA).

SAP is phasing out BFC and support will cease in 2030 (extended from 2027).

As-Is Systems Integration for Consolidations

Image AddedSyensqo existing license is until xxxxx.


Assumptions

Deployment:   S4HANA

  • S/4HANA will be
Deployment
  • Deployed over more than one
Phase
  • Release.  

Tools:   Group

  • Group Reporting is the current/latest SAP
Consolidations Module.  It is assumed that this will be implemented for Syensqo, however this decision will be made in detailed designed.    With the implementation of the new Consolidation tool to occur in the later Phase of the deployment come
  • tool for consolidation processes, and is on the SAP Roadmap for the future.
  • With the Syensqo consolidations tool implementation occurring in a later Release of the deployment comes additional time in the detailed design
phase.  As such, the suitability of Group Reporting for     Syensqo will be assessed in the next phase
  • Release. The final decision on the Consolidation tool will not be made at this stage, and is not
part of the Key Decision at this point in time
  • a key decision of this document.
  • Simplification and synergies can be gained utilizing a fully integrated SAP Module, and it is assumed Group Reporting will be utilized unless there are major gaps in the business requirements.

Risk.   As the organisations

  • Syensqo's financial statements
and reports
  • are produced from the Consolidations
, risk will be a major consideration in the the decision making process. 
  • tool.  A risk resides in presenting inaccurate numbers.  A key evaluation criteria will relate to the deployment approach which lowers this risk.

Design, Build and Test. 

  • The timing of when dedicated Consolidations resource will commence will be determined in line with the overall Deployment approach, taking into consideration transition to new a application, integration of design, and resource costs.
  • Design and build in the initial Release\s will support parallel testing of S4HANA Group Consolidations with the existing BFC tool. This will contribute to de-risking the deployment.


Constraints

BFC product support by SAP ends in 2030.  It is assumed to deployment will occur prior to SAP Group Reporting or alternative Consolidations tool will be deployed prior to this date.


Impacts

The Below are the major impacts on the decision are on the following:

Integration impacts: - Interfacing or data loading into the consolidation system.   There is an impact whether whether data is flowing into BFC or new Consolidation tool.  -

  • Aligned with the deployment decision
load packages loads
  • , loading data packages into BFC from the source system, being PF1, WP1, or S4HANA, will continue.


Data Conversion:  - Timing and complexity of data conversion impact.  -  Aligned

  • Aligned with the deployment decision, historical data loads will occur in the later
phase and and "one" load
  • Release. Conversion will be a one off activity upon deployment


Reporting:

 - Report produced via BFC

 -

Reports currently being produced from BFC.

  • Aligned with the deployment decision, existing Reports will continue to be produced from BFC until the new Consolidation tool is implemented in the later
phase
  • Release.





Business Rules

  • Existing BFC Rules will continue.
S4HANA
  • S/4HANA business rules relevant at this point in time will be largely
caverned to
  • governed by the Enterprise Structure Definition. More specific Consolidation Rules will come in detailed design.


Options considered

Option A:

 

Deferred Deployment

Continue with BFC in the initial phase\s Releases and deploy the new Consolidation tool in the later Phase

    Pros

          

Release

Orange Box and Arrows are new / added, the rest remains as is.

Image Added

Key Points:

  • System: BFC will stay in place until the last Release of the deployment.
  • IC Eliminations: All existing intercompany elimination, reporting and reconciliation processes remain.
  • Reporting: Existing Reports will continue from BFC.
  • Existing ECC entities: will continue to integrate with BFC in the same manner.
  • Entities transitioning to S4HANA: will transfer data in the same manner as the ECC system entities.  Data load output templates will remain largely the same, the data to fill the template will come from S4HANA.  Mapping of data will be required and tested. 






Option B: Upfront Deployment

Option B: 

Implement the new Consolidation Tool and discontinue BFC in Phase 1 of the Deployment.

Option C: 

Option D: 

Release 1 of the Deployment.

Orange text Boxes show what will change with an upfront deployment.

Image Added


Key Points:

  • System: BFC will be replaced by the new consolidation tool in the initial Deployment Release.
  • Intercompany Eliminations: All existing intercompany elimination will need to be designed and built in the new tool.  Existing ECC entities will need to adopt the new rules to integrate with the new tool.
  • Reporting: Reports from BFC will need to be replaced with new S4HANA equivalents. 
  • Existing ECC entities: will need to load data into the new consolidation tool, new templates and processes need to be developed.  Additional training also required for the interim.
  • Entities transition to S4HANA: Data from S4HANA will automatically be consumed by the new Consolidation tool. 


Evaluation


CriteriaOption A - Defer DeploymentOption B - Upfront Deployment

Risk

Pro

Low Risk. Existing tool continued to be utilized. Loading from the existing source system not initially transferring to S4HANA will continue as is.  Data from the entities transitioning to S4HANA will follow the same\existing approach to load into BFC.

Con

Higher Risk approach with high likelihood of business disruption for the initial closing periods.  Early deployment carries a higher likelihood of inaccurate data feeding into Consolidations and presenting in the Syensqo financial statements.

Stabilization at Deployment

Pro

Most of the new processes\modules have an impact on the Consolidated result.  Allowing time for the initial Release\s to stabilise will result in more accurate data being automatically consumed by Consolidation, and leading to more accurate financials.

Con

Most of the new processes\modules have an impact on the Consolidated result.  Upfront deployment will have higher probability on process and data issues from integrated process feeding into the final consolidated figures.


Simplicity

Pro

Data Loads:  Existing Data load process to continue for ECC entities that transition in later Release/s. 

Consolidation & Intercompany Elimination: rules to remain and continue for the transition period.

Reporting: will continue for both ECC and S4HANA Entities


Con

Data Loads: Data loads for tranisitioning entities to be developed, but to follow existing processes 

Con

Data Loads: New Process will need to be developed to integrate data from the ECC systems into the new Consolidations Tool.

Consolidation & Intercompany Elimination:  Consolidation & Elimination rules to be developed for ECC systems during the transition period.

Reporting: New Reports will need to be built in Release 1.

The above mentioned will require addition training for the transition period. 

Data Conversion Ease

Pro

Easier data conversation taking the historical data at one point in time.  A later deployment allows more time to manage\test\rehearse the historical data conversion. 

Con

Data conversion required earlier.  Less opportunity to test, rehearse, run in parallel.

Testing - Additional Parallel Testing Option

Pro

Allows the possibility of more robust parallel testing utilising actual data. Parallel testing entails testing consolidated results in the new system against the like for like results in BFC. This is relevant for the base consolidation as well as reports.

Con

Parallel Testing is not an Option, continue with Conventional Testing (Eg. Unit, Integration & User Acceptance Testing) 

Benefits Realisation

Con

Benefits from the new Consolidation Tool to be realised at a later stage.

Pro

Benefits (eg. integrated data, streamlined processes) from the new Consolidation Tool to be realised earlier.

CriteriaWeighting

Option A 

Deferred Deployment

Option B

Upfront Deployment

RiskVHLowHigh
Stabilization at DeploymentHMediumLow
SimplicityHHighLow
Data Conversion EaseHMediumLow
Testing - Additional Parallel Testing OptionMHighLow
Benefits Realisation Timing (Earlier Vs Later)HLowHigh
Overall Rating
HighLow


Preferred Option

Option A - Deferred Deployment is the recommended approach. 

Option A is a lower risk option for reporting financial results for the organisation, along with an easier transition period. Although the benefits coming from the new Consolidation system are deferred, they will still be realised, albeit at later date.

Evaluation

Option A

Option B
Option C
Option D
Criterion 1

(plus)Pro

(minus)Con

(plus)Pro

(plus)Pro

(plus)Pro

(minus)Con

(plus)Pro

(minus)Con

Criterion 2

(plus)Pro

(minus)Con

(minus)Con

(plus)Pro

(plus)Pro

(minus)Con

(minus)Con

Criterion 3(plus)Pro(minus)Con(minus)Con(plus)Pro


See also


Attachments
previewfalse
patterns^(?!.*\.(png|jpg|jpeg)$).*
sortOrderdescending

Change log

Change History

Workflow history

limit10
Workflow Report
parent@self
hideheadertrue
typeapprovals