Versions Compared
compared with
Key
- This line was added.
- This line was removed.
- Formatting was changed.
Status colour Blue title Step 1
Start the transaction using the menu path or transaction code CK74N
Double-click

| Info |
|---|
Create additive costs: Initial Screen |

Status colour Blue title Step 2
- Enter the material code and the plant code
- Enter the costing variant ZFO variant and the costing version 1
and
Image Modified

Status colour Blue title Step 3
- Enter the Costing Date From : usually the date of the day or the first day of the coming month
- Enter the Valuation Date that is the same date as the Costing Date From
and Image Modified

Status colour Blue title Step 4
If the screen Date Overlap for Following Cost Estimates appears it means that a cost already but you can click on

Status colour Blue title Step 5
- Enter V in the column Category
- Enter the plant code
- Enter the quantity = 1 and the unit of measure
- Enter a Description
- Enter the price per unit in column Price - Total
- Enter the cost element 98150930 for the transport between plants
and Image Modified

Status colour Blue title Step 6
- The column Value - Total is updated with the unit price
- The total in local currency is updated
and save

Status colour Blue title Step 7
- If the result is correct, you can save
and the cost estimate is saved
- If there is a mistake, you can click
to come back and start again the creation of additive costs

| Viewtracker | ||
|---|---|---|
|