Group requirement is to provide an annual planning and communicate locally an inventory procedure and preparation.
...
...
...
...
...
Physical inventory manager Frequency : Annual with a quarterly up-date Control : IAC |
|
...
.02.03 / control owner: FRA | For an example and a blank template of annual planning ==> 7. Example of documents to be used / a. Annual planning |
|
Inventory Planning & SchedulingPhysical counts or cycle counts must be conducted at least once annually for all materials. With limited exception (see exceptions section) the sites that perform a Full Periodic (Wall-to-wall) inventory must complete them between July and November each year[1]. Cycle counts may be performed in addition to the annual Full Periodic counts.. FRA validates and publishes updated physical inventory planning prepared by PIM and considering that: - Recommended 90% of the physical inventory count (in value of items) be done by the end of September
- 100% of the physical inventory count (in value of items) must be done by the end of November, including all external storage (Hard Closing)
Exceptions: - The period can be extended/ modified if requested by the external Audit team. The need for date modification must be approved by the Group Controller.
- Furthermore, for the sites that perform Cycle counting they must;
- By November 30th, references counted must represent at least 80% of the total value of industrial supplies inventory.
The annual planning must include a list of all the inventory storage location (on site / off site), the frequency of cycle counts, a detailed planning taking into account the above objectives
[1] The site must maintain an auditable roll forward from the date of the inventory to the reporting period date. |
...
| title | Annual planning model |
|---|
...
The annual planning includes : 1. A list of the inventory storage location |
...
- On site
- Off site: inventory on consignment, held in third parties facilities or by toll manufacturers
2. |
...
Frequency of cycle counts, if applicable - All storage locations divided by count date;
- Inventory planning has to be prepared targeting 100% of Inventory counted at the end of reference period;
3. A planning |
...
taking into account the following objectives |
...
...
...
items representing 100% of end inventory should be done as of 30th November (in value), each year (including external Storage) Full Physical Counting - A count of items representing
|
...
...
...
Specific for Industrial Suplies |
...
- , references counted must represent at least 80% of the total value of
|
...
- industrial supplies inventory.
- The rest 20% of references of the total value must be counted by either sampling counting method every year or cycle counting method every 3 years
That planning must be communicated to FRA, who could organize/support the supervision by a third party without prior notification to PIM. 4. |
...
Cycle Counts rules - Cycle counts have to start before July 1st of each year, otherwise Full Inventory count will have to be executed at the plant;
- ABC Classification method has to be implemented for a complete cycle count model implementation for spare parts;
| Warning |
|---|
Planning is proposed by PIM and validated by FRA before end of September with consideration for 2 periods : - October 1st to November 30 November of current year : revision of on going calendar :
- Starting with actual inventory coverage rate as of October 1st (in theory 90%)
- Showing completion of 100% target as of November 30TH
- Dec 1st of current year to November 30th of following year :
- That planning is detailed by material code and SAP plant where applicable
- Where SAP isn’t available, that planning is also used to follow progress of coverage inventory count
- FRA is responsible for recording that planning in the dedicated group repository and external auditor have access to that repository
|
|
| Expand |
|---|
|
| Tip |
|---|
Responsible : Physical inventory manager Frequency : Annual Control : IAC.02.03 / control owner: FRA |
| Warning |
|---|
| The site procedure is updated at least once a year before September 30th by the PIM with validation by FRA. FRA is responsible for recording that procedure in the dedicated group repository. |
|
...
The site procedure has to include: |
...
...
...
- finance responsible assigned (FRA) who is authorized to validate physical inventory discrepancies
|
...
- and particularities linked to the segregation of duties
|
...
...
- applicable safety procedure
|
...
- Triggering event to engage a second count : for each of the category of inventory (A31000, A34000, A37000), determination of a threshold for the value of discrepancies above which a second count must be performed. A 0.5 % threshold of the total amount of the inventory concerned is recommended, it will be applied as such if the site inventory procedure
|
...
- doesn’t specify otherwise.
|
...
- Specific scenarios in which recounts might not be required
- Meter readings or print in continuous production environments
- Scenarios specific to the site's activity
| Warning |
|---|
| - Determination of a threshold for the value of discrepancies for one stock count or one month of cycle count above in which
|
|
...
- :
the GCCO, the plant manager and
|
|
...
- GBU supply chain director are
|
|
...
- informed.
==> Maximum threshold is 1% of the value of counted inventory
|
|