Group requirement is to provide an annual planning and communicate locally an inventory procedure and preparation.

 

...

titleGood practice

...

Expand
title

...

a. Annual planning

...

Tip

Responsible :

...

Physical inventory manager
Frequency : Annual with a quarterly up-date
Control : IAC

...

.02.03 / control owner: FRA

For an example and a blank template of annual planning ==> 7. Example of documents to be used / a. Annual planning


Inventory Planning & Scheduling

Physical counts or cycle counts must be conducted at least once annually for all materials. With limited exception (see exceptions section) the sites that perform a Full Periodic (Wall-to-wall) inventory must complete them between July and November each year[1].  Cycle counts may be performed in addition to the annual Full Periodic counts.. 

FRA validates and publishes updated physical inventory planning prepared by PIM and considering that:

  • Recommended 90% of the physical inventory count (in value of items) be done by the end of September
  • 100% of the physical inventory count (in value of items) must be done by the end of November, including all external storage (Hard Closing)

Exceptions:

  • The period can be extended/ modified if requested by the external Audit team.  The need for date modification must be approved by the Group Controller.
  • Furthermore, for the sites that perform Cycle counting they must;
    • By November 30th, references counted must represent at least 80% of the total value of industrial supplies inventory.


The annual planning must include a list of all the inventory storage location (on site / off site), the frequency of cycle counts, a detailed planning taking into account the above objectives


[1] The site must maintain an auditable roll forward from the date of the inventory to the reporting period date. 

...

titleAnnual planning model

...


The annual planning includes :

1. A list of the inventory storage location

...

  • On site
  • Off site: inventory on consignment, held in third parties facilities or by toll manufacturers

2.

...

Frequency of cycle counts, if applicable

  • All storage locations divided by count date;
  • Inventory planning has to be prepared targeting 100% of Inventory counted at the end of reference period;

3. A planning

...

taking into account the following objectives

...


  • Cycle Counting - A

...

  • count of

...

  • items representing 100% of end inventory should be done as of 30th November (in value), each
    year (including external Storage)

  • Full Physical Counting - A count of items representing

...

  • 100% of

...

  • end inventory should be done as of

...

  • 31 December (in value),
    each year (including external Storage)


Specific for Industrial Suplies

  • By November 30th

...

  • , references counted must represent at least 80% of the total value of

...

  • industrial supplies inventory.
  • The rest 20% of references of the total value must be counted by either sampling counting method every year or cycle counting method every 3 years

That planning must be communicated to FRA, who could organize/support the supervision by a third party without prior notification to PIM. 

4.

...

Cycle Counts rules
 

  • Cycle counts have to start before July 1st of each year, otherwise Full Inventory count will have to be executed at the plant;
  • ABC Classification method has to be implemented for a complete cycle count model implementation for spare parts;


Warning

Planning is proposed by PIM and validated by FRA before end of September with consideration for 2 periods :

  1.  October 1st to November 30 November of current year : revision of on going calendar :
    1. Starting with actual inventory coverage rate as of October 1st (in theory 90%)
    2. Showing completion of 100% target as of November 30TH
  2.  Dec 1st of current year to November 30th of following year :
    1. That planning is detailed by material code and SAP plant where applicable
    2. Where SAP isn’t available, that planning is also used to follow progress of coverage inventory count 
    3. FRA is responsible for recording that planning in the dedicated group repository and external auditor have access to that repository
Expand
titleb. Local procedure
Tip

Responsible : Physical inventory manager
Frequency : Annual
Control : IAC.02.03 / control owner: FRA

 

Warning
titleRed lines

The site procedure is updated at least once a year before September 30th  by the PIM with validation by FRA. FRA is responsible for recording that procedure in the dedicated group repository. 

 

Site procedure

...

The site procedure has to include:

...

...

  • The name of the

...

  • finance responsible assigned (FRA) who is authorized to validate physical inventory discrepancies

...

  • and particularities linked to the segregation of duties

...



  • A reference to

...

  • applicable safety procedure

...



  • Triggering event to engage a second count : for each of the category of inventory (A31000, A34000, A37000), determination of a threshold for the value of discrepancies above which a second count must be performed. A 0.5 % threshold of the total amount of the inventory concerned is recommended, it will be applied as such if the site inventory procedure

...

  • doesn’t specify otherwise.

...

  • Specific scenarios in which recounts might not be required
    • Meter readings or print in continuous production environments
    • Scenarios specific to the site's activity


Warning
titleRed lines
  •  Determination of a threshold for the value of discrepancies for one stock count or one month of cycle count above in which

...

  • :
    the GCCO, the plant manager and

...

  • GBU supply chain director are

...

  •  informed
    ==> Maximum threshold is 1% of the value of counted inventory