Purpose
The purpose of this document is to define the conversion approach to create Operative Project Definition in S/4 HANA.
In SAP PS, the project definition acts as a framework that provides a binding structure for organizational element of a project, such as Work Breakdown Structures. It serves as the top-level element for creating a project, defining default values for company code, plant, and responsible persons, and is essential for structuring, planning, and controlling all aspects of a project, from initiation to closure.
Conversion Scope
The scope of this document covers the approach for converting active Project Definition from Legacy Source Systems into S/4HANA following the Master Data Design Standard- Project Definition.
As per SyWay design, there are two ways to create an Operative Project definition based on the scenarios,
Scenario 1: PS Project definition with WBS element hierarchy (Level 1 & 2) can be automatically created from the approved PPM item once stage-gate 1 is approved. This process involves mapping the PPM item type to a a predefined PS template project (created as per CVN-1019 Template Projects) with the Decision Flow Management settings in the SAP system.
A project definition is automatically created for the specified PPM item types, using the corresponding project profile and applicable project coding mask. The conversion approach is dealt is defined with in CNV-1022 Portfolio Item.
All project definition (new project profile ZPS0001, ZPS0002) relevant to PPM item type linking will be created from PPM items and is excluded from this conversion scope.
Scenario 2: A project definition created manually independent of the PPM item, with the data being sourced using a DCT (Data Collection Template).
Conversion scope includes all projects that belong to Scenario 2, except statistical expense project. Statistical projects (with project profile ZPS0003 - Statistical Expense) are created as needed in S/4 Hana
Below project profiles are configured to allow the creation of a project definition directly in the Project System, without requiring integration with a Portfolio and Project Management (PPM) item.
| PS Project Profile | PRJID | PS Coding Mask | DCT | |
ZPS0004 - Intercompany Recharges | F | -000000- | ||
| PPM Item Type | PS Project Profile | PRJID | PS Coding Mask | Description |
| Z001 Industrial Project with Qualification | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects | Z002 Industrial Project | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-
| 00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects | Z003 Industrial Project - Simple ? | ZPS0001 - CAPITAL/ Operational Expense | A|
| One Project per CoCode | ||||
ZPS0005 - Provisional Expense | F | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects | |
| Z004 New Product Introduction | ZPS0001 - CAPITAL/ Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
| Z005 Product & Process Improvement | ZPS0001 - CAPITAL/ Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
| Z006 Customer and business support | ZPS0001 - CAPITAL/ Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
| Z007 OPD Opportunity Development | ZPS0002 - Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
| Z008 IT Full Lifecycle Project | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z009 IT Small Project | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects | Z010 Opex Project | ZPS0002 - Operational Expense | E |
| Z011 Turnaround Projects | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z012 Direct Asset Purchase | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z013 Capitalised Maintenance | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z014 Capital Lease | ZPS0001 - CAPITAL/ Operational Expense | A | -000000-00-00-XX-XX-XX | CAPITAL/ Operational Expense Projects |
| Z017-New Application Development | ZPS0001 - CAPITAL/ Operational Expense | R | -000000-00-00-XX-XX-XX | R&I Projects |
All project definition (new project profile ZPS0001, ZPS0002) relevant to PPM item type linking will be created from PPM items and is excluded from this conversion scope.
Scenario 2: A project definition created manually independent of the PPM item, with the data being sourced using a DCT (Data Collection Template).
These projects are:
- Statistical Expense Projects: Used for tracking non-capital costs. These are statistical project without Budget, created by GBS and no PPM item is required.
- Intercompany Recharges: Used for Inter company service recharge cost allocations. These are operational projects have billing WBS element without Budget, created by GBS and no PPM item is required.
- Provisional Expense: Used for expense provision. These are operational projects without Budget, created by GBS and no PPM item is required.
Conversion scope includes all projects that belong to Scenario 2.
The conversion will ensure all projects are aligned to the defined project coding mask and relevant Organizational Units as designed for the target S/4HANA landscape.
Below project profiles are configured to allow the creation of a project definition directly in the Project System, without requiring integration with a Portfolio and Project Management (PPM) item.
| PS Project Profile | PRJID | PS Coding Mask | PS Coding Mask Description |
ZPS0003 - Statistical Expense | F | -000000-00-00-XX-XX-XX | Statistical/ Recharge & Provision Projects |
ZPS0004 - Intercompany Recharges | F | -000000-00-00-XX-XX-XX | Statistical/ Recharge & Provision Projects |
ZPS0005 - Provisional Expense | F | -000000-00-00-XX-XX-XX | Statistical/ Recharge & Provision Projects |
Scope include:
- Extracting existing active Project Definition from SAP ECC systems WP2 and PF2.
- Extracting existing active Internal order having status Created / Release from SAP ECC systems WP2 and PF2.
- Applying transformation and cleansing logic via Syniti to conform with the S/4HANA data model.
- Loading the transformed Project definition into SAP S/4HANA while ensuring data integrity, correct assignment to project profile as per the project scenarios.
The data from legacy system includes:
All the projects below will be migrated from legacy source systems (PF2 and WP2) into S/4HANA –
- Open Projects from in scope company codes
- Closed Project from in scope company codes with postings in migration relevant financial year (currently migration relevant is 2028). The postings technically does not occur directly against the project definition but against objects within the project therefore, postings against a WBS element is used as a proxy for determination of postings against the project.
Active internal order with status created / Release.
The data from legacy system excludes:
- Where the mapped project profile is ZPS0001 or ZPS0002 linked to PPM item type.
Logic:
- Proj elements not in closed status
Table PROJ
Key in field "Company Code" in scope.
Field project profile not in excluded project profile.
Result: Object numbers of WBS that are in company codes in scope.
Table JEST:
Field "Object number" = Key in the object numbers of WBS (from Step A)
Field "Status Inactive" = blank
Then filter object number that do not have status I0046 (Closed)
These Project Profile need to be migrated dependent on project profile mapping.
2. Closed Project that have WBS element with cost in current year must also be migrated.
Logic:
Table PROJ
Field "Company Code" in scope.
Field project profile in scope project profile.
Result: Object numbers of WBS that are in company codes in scope.
Table JEST:
Field "Object number" = Key in the object numbers of Project
Field "Status Inactive" = blank
Then filter object number that has status I0046 (Closed).
Result closed projects.
Table PRPS
Field PSPHI For closed projects numbers
Result WBS numbers for
Table RPSCO:
Field "Object number" = Key in the object numbers of WBS
Field "Fiscal Year" = Current year
Field "Value Type" = 4
Result = Object numbers that have cost in current year.
These WBS needs to be migrated.
In addition to the migration of existing Project definitions from ECC there are also some internal orders in ECC which will be migrated to WBS elements in S4 Hana. As the project definition is a requirement for the creation of WBS elements, project definitions which does not exist in ECC will be required, these Project definitions will be defined in a DCT.
List of source systems and approximate number of recordsSource Approx No. of Records
No. of Records
Additional Information
Multi-language Requirement
Project Definition description will be made available in English. Multi language is supported. Based on the user's login language, the project definition's description in that language will be displayed on the screen
Document Management
Not Applicable
Legal Requirement
Not Applicable
Special Requirements
Not Applicable
| One project per company code per GBU(profit centre) |
The conversion will ensure all projects are aligned to the defined project coding mask and relevant Organizational Units as designed for the target S/4 Hana landscape.
List of source systems and approximate number of records
| Source | Scope | Source Approx No. of Records | Target System | Target Approx No. of Records |
|---|---|---|---|---|
| DCT | S/4 Hana | TBD |
Additional Information
Multi-language Requirement
Project definition, should be maintained in if available:
- English (EN)
- French (FR)
- Italian (IT)
- Chinese (ZN)
Document Management
Not Applicable
Legal Requirement
Not Applicable
Special Requirements
Not Applicable
Target Design
The technical design of the target for this conversion approach.
Target Design
The technical design of the target for this conversion approach.
Mandatory
Mandatory
| Table | Field | Data Element | Field Description | Data Type | Length | Requirement |
|---|---|---|---|---|---|---|
| PROJ | PSPID | PS_PSPID | Project definition | CHAR | 24 | Mandatory |
| PROJ | POST1 | PS_POST1 | Description | CHAR | 40 | Mandatory |
| PROJ | STSPR | PS_STSPR | WBS status profile | CHAR | 8 | System Generated |
| PROJ | VERNR | PS_VERNR | No. of Person Resp. | NUM | 8 | Mandatory |
| PROJ | ASTNR | PS_ASTNR | Applicant no. | CHAR | 25 | Mandatory |
| PROJ | VBUKR | PS_VBUKR | Company code | CHAR |
| 4 | Mandatory | |||||
| PROJ | VKOKR | PS_VKOKR | Controlling area | CHAR | 4 | System Generated |
PROJ | PRCTR | PRCTR | Profit Center | CHAR | 10 | Mandatory |
| PROJ | PWHIE | PS_PWHIE | Project Currency | CHAR | 5 | System Generated |
| PROJ | PLFAZ | PS_PLFAZ_CHG | Start date | DATS | 8 | Mandatory |
| PROJ | PLSEZ | PS_PLSEZ_CHG | Finish date | DATS | 8 | Conditional |
| PROJ | WERKS | WERKS_D | Plant | CHAR | 4 | Conditional |
PROJ | KALID | FABKL | Factory Calendar | CHAR | 2 | System Generated |
| PROJ | PROFL | PROFIDPROJ | Project Profile | CHAR | 7 | Mandatory |
| PROJ | BPROF | BP_BPROFIL | Budget Profile | CHAR | 6 | System Generated |
| PROJ | BESTA | PS_BESTAND | Project stock | CHAR | 1 | System |
Generated | ||||||
| PROJ- | XSTAT | PS_XSTAT | Statistical | CHAR | 1 | Conditional |
| PROJ | PPROF | BP_PPROFIL | Planning Profile | CHAR | 6 | System generated |
| PROJ | PLINT | PLINT | Integrated Planning | CHAR | 1 | System generated |
| PROJ | SLWID | SLWID | Field key | CHAR | 7 | System generated |
| PROJ | FUNC_AREA | FKBER | Functional Area | CHAR |
| 16 | Mandatory | |||||
| PROJ | USR00 | USRCHAR20 | Legacy Project ID | CHAR | 20 | Blank |
| PROJ |
| USR01 | USRCHAR20 | Item Type |
| CHAR | 20 |
Blank | |
| PROJ | USR02 |
| USRCHAR10 | Need-to-know | CHAR | 10 |
Blank |
Data Cleansing
Closing of projects| ID | Criticality | Error Message/Report Description | Rule | Output | Source System |
|---|---|---|---|---|---|
1024-001 | C1 | Active project in current year | Active projects in needs to be reflected in SAP S/4 | Active projects | WP2/PF2 | 1024-002 | C2 | Closed project that have cost in current year |
1024-003 | C3 | Old projects with no actuals / commitment | If the old projects do not have any actual (and/or) commitments in the past year, set the project to status CLSD (CJ20N) | Old project set to closed | WP2/PF2 |
1024-004 | C4 | Project with AUC that created <= 2017 there's no movement in FY2023 - FY2024 and haven't been capitalized for long period | - Review AUC asset that there's no movement (changes) for the year 2023-2024 - Review Project with WBS that linked to the asset. If there's no further cost expected, TECO WBS - Run settlement to capitalized AUC(CJ88) | Only genuine Project WBS with AUC is outstanding and no AUC not capitalized for closed/TECO Capex Project WBS | WP2/PF2 |
Conversion Process
The high-level process is represented by the diagram below:
Data Privacy and Sensitivity
Extraction
Extract data from a source into Syniti Migrate.
. There are 2 possibilities:
- The data exists. Syniti Migrate connects to the source and loads the data into Syniti Migrate. There are 3 methods:
- Perform full data extraction from relevant tables in the source system(s).
- Perform extraction through the application layer.
- Only if Syniti Migrate; cannot connect to the source, data is loaded to the repository from the provided source system extract/report.
- The data does not exist (or cannot be converted from its current state). The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
Extraction Run Sheet
1
Confirm scope and extraction approach for each ECC source systems WP2, PF2 (direct DB or manual extract)
Data Team (I2M), Data Team (Syniti)
2
Establish and validate Syniti connectivity to both ECC source systems
Technical / Basis Team, Data Team (Syniti)
3
Perform full data extraction from relevant SAP PROJ from both source systems WP2, PF2
Data Team (Syniti)
4
Extract Project Definition via the application layer for additional validations for Manual Data Collection using DCTs
Data Team (I2M)
5
Apply agreed Relevancy Criteria to filter only applicable Project records for S/4HANA
Data Team (I2M), Data Team (Syniti)
6
In case of restricted access or connectivity issues, receive pre-extracted reports/files from source system team and upload to Syniti Migrate manually
Data Team (I2M), Data Team (Syniti)
7
Perform data quality checks on extracted records (e.g., missing fields, invalid dates, incorrect formats)
Data Team (I2M), Data Team (Syniti)
8
Review and approve extracted data sample sets from each source system before transformation begins
Business / Functional Team
| Rule | Output | Source System | |||
|---|---|---|---|---|---|
C2 | All active internal orders to be closed | Report | WP2/PF2 |
list of internal order from AUFK, order category =select 01 with status = CRTD, REL, or Investment profile not blank (exclude status = CLSD), get OBJNR from AUFK, pass in COBRB, check for account assignment cat = WBS, CTR, ORD, GL. get list of all such internal order.
Conversion Process
The high-level process is represented by the diagram below:
Data Privacy and Sensitivity
Not ApplicableExtraction
The data is manually collected by the business directly in Syniti Migrate. This is to be conducted using DCT (Data Collection Template) in Syniti Migrate
The agreed Relevancy criteria is applied to the extracted records to identify the records that are applicable for the Target loads
Extraction Run Sheet
| Req # | Requirement Description | Team Responsible |
|---|---|---|
1 | Ensure DCT is collected for Project Definition | Data Team (I2M), Data Team (Syniti) |
2 | Perform preliminary completeness check | Technical / Basis Team, Data Team (Syniti) |
3 | Raise issues as defects if Req # 1 to 2 are not met | Data Team (Syniti) |
4 | Repeat Req # 1 to 3 if required) | Data Team (I2M), Data Team (Syniti) |
Selection Screen
Not Applicable| Selection Ref Screen | Parameter Name | Selection Type | Requirement | Value to be entered/set |
|---|---|---|---|---|
| Not applicable |
Data Collection Template (DCT)
Target Ready Data Collection Template will be created for Project Definitions data with exception of some fields which require transformation as mentioned in the transformation rule.
DCT applicable to project created manually, with project profile, PROJ-PROFL
- Recharge Cost Collectors - Expense Project - Project profile ZPS0004
- Provision Cost collectors - Expense Projects - Project Profile ZPS0005
| Field Name | Field Description | Rule |
|---|---|---|
| PSPID | Project definition | Unique Identifier for the project definition via coding mask starting with "F-000000". 1. Recharge Cost Collectors - Expense Project wth Project profile ZPS0004 2. Provision Cost collectors - Expense Projects with Project Profile ZPS0005 It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template |
| POST1 | Description | Short description, Name of the Project It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template |
| STSPR | WBS status profile | Profile used to Control User Statuses. Automatically Inherited from the Project Profile. Change not allowed. |
| VERNR | No. of Person Resp. | Project Owner Position number Refer configuration table field TCJ04-PS_VERNR for data validation. |
| ASTNR | Applicant no. | This field represent the position of the Project Financial Controller. Refer configuration table field TCJ05-ASTNR for data validation. It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template |
| VBUKR | Company code | Represents legal entity . Refer configuration table field T001-BURKS for data validation. One project per company code per GBU(profit centre) for Provisional Project with profile ZPS0005 One project per company code for Recharge project with profile ZPS0004 It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template |
| PRCTR | Profit Center | Profit Center represent a plant or a site or generic for GBU. Refer master data table field CEPC-PRCTR for allowed values. |
| PLFAZ | Start date | Planned Start date of the Project. , It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template |
| PLSEZ | Finish date | Planned finish date of the Project, Conditional |
| WERKS | Plant | Plant represent a site of Project. Conditional |
| PROFL | Project Profile | The profiles contain default values and control parameters for processing objects and functions in the Project System. Allowed Project Profiles for creation of Project definition: It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template |
| FUNC_AREA | Functional Area | Refer configuration table field TFKB-FKBER for allowed values." It is a Required Field: Preload Check to be done to confirm that this is field in the Data Collection Template |
| Instance | Instance where the project definition is to be loaded. (Field required in DCT) |
In conjunction with DCT business user will be provided with Person Responsible / Applicant list for reference.
Extraction Dependencies
| Item # | Step Description | Team Responsible |
|---|---|---|
Not Applicable | Data Team |
Transformation
Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation
Transformation Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Obtain DCT Sign-off from Business | Data Team |
2 | Execute and Load and perform Transformation | Data Team |
3 | Monitor the transformation progress and ensure performance and completion is within allowed timeframe | Data Team |
4 | Review and Validate Error and Preload Reports | Data Team |
5 | Generate data load count. | Data Team |
6 | Generate Load Files | Data Team |
7 | Log errors as defects, if any and address resolutions. Close defects. | Data Team |
| 8 | Re-transform and re-validate the Pre-load reports if necessary. | Data Team |
| 9 | Validate the transformed file as part of pre-load validation, raise data defects or provide the pre-load sign-off. | Business |
| 10 | Analyze and resolve any pre-load defects logged by business. | Data Team |
| 11 | Repeat steps 7 to 10 if necessary | Data Team |
| 12 | Proceed to pre-load validations | Data Team |
Transformation Rules
| Rule # | Source system | Source Table | Source Field | Source Description | Target System | Target Table | Target Field | Target Description | Transformation Logic |
|---|---|---|---|---|---|---|---|---|---|
| DCT | PSPID | Project definition | S/4 | PROJ | PSPID | Project ID | Mapping from source | ||
| DCT | USR00 | Legacy Project ID | S/4 | PROJ | USR00 | Legacy Project ID | Blank | ||
| DCT | USR01 | Item Type | S/4 | PROJ | USR01 | Item Type | Blank | ||
| DCT | USR02 | Need-to-know | S/4 | PROJ | USR02 | Need-to-know | Blank | ||
| DCT | POST1 | Description | S/4 | PROJ | POST1 | Description | Copy from source | ||
| DCT | S/4 | PROJ | STSPR | WBS status profile | Inherit from Project Profile | ||||
| DCT | VERNR | No. of Person Resp. | S/4 | PROJ | VERNR | No. of Person Resp. | Copy from source | ||
| DCT | ASTNR | Applicant no. | S/4 | PROJ | ASTNR | Applicant no. | Copy from source | ||
| DCT | VBUKR | Company code | S/4 | PROJ | VBUKR | Company code | Mapping from source: Company Code Old to new | ||
| DCT | S/4 | PROJ | VKOKR | Controlling area | Default from project profile | ||||
| DCT | PRCTR | Profit Center | S/4 | PROJ | PRCTR | Profit Center | Mapping from source: Profit Center Old to new | ||
| DCT | S/4 | PROJ | PWHIE | Project Currency | Mapping from Company Code | ||||
| DCT | PLFAZ | Start date | S/4 | PROJ | PLFAZ | Start date | Copy from source | ||
| DCT | PLSEZ | Finish date | S/4 | PROJ | PLSEZ | Finish date | Copy from source | ||
| DCT | S/4 | PROJ | KALID | Factory Calendar | Mapping from Plant | ||||
| DCT | PROFL | Project Profile | S/4 | PROJ | PROFL | Project Profile | Copy from source | ||
| DCT | S/4 | PROJ | BPROF | Budget Profile | Inherit from Project Profile | ||||
| DCT | S/4 | PROJ | BESTA | Project stock | Inherit from Project Profile | ||||
| DCT | S/4 | PROJ | PPROF | Planning Profile | Inherit from Project Profile | ||||
| DCT | S/4 | PROJ | PLINT | Integrated Planning | Inherit from Project Profile | ||||
| DCT | FUNC_AREA | Functional Area | S/4 | PROJ | FUNC_AREA | Functional Area | Copy from source |
List of Custom Target Reports for this object is maintained here: Conversion Specification - Custom Reports Register.
The standard upload template to be used for Project Definition (Project Details template) upload in S/4 Hana.
Transformation Mapping| Mapping Table Name | Mapping Table Description |
|---|---|
| Company Code | Value Mapping: Old to New Company Code |
| T001 | Value Mapping: Currency From Company Code |
| Plant | Value Mapping: Old Plant to New |
| Profit Center | Value Mapping: Profit Center Old to New |
Person Responsible / Applicant | New Position to person name |
Transformation Dependencies
List the steps that need to occur before transformation can commence| Item # | Step Description | Team Responsible |
|---|---|---|
| Ensure all the fields and values are imported into ADM Construction page correctly | Data Team | |
| Profit centers has been created (CEPC) |
Pre-Load Validation
Project Team
Completeness
| Task | Action |
|---|---|
| Generation of Pre-load report | Check all the required fields |
Verify Record Count | SyWay I2M Data Team to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets. |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | SyWay I2M Data Team to verify that all fields below meet pass the checks:
|
Review Error Reports | Review and correct the errors. Achieve a zero-error record count as much as possible. Raise defects for data remediated and requiring a correction in the source (DCT) data. |
Business
Completeness
| Task | Action |
|---|---|
Verify Record Count | Business Data Owner/s to verify that the total number of relevant records from the DCT is equal to the total number of records in the Preload and Load Sheets. |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | Business Data Owner/s to verify that all the data in the load table/file is accurate as per endorsed transformation/mapping rules (and signed-off DCT data). |
Load
The load process includes:
- Execute the automated data load into target system using load tool or product the load file if the load must be done manually
- Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation
Load Run Sheet
| Item # | Step Description | Team Responsible |
|---|---|---|
1 | Load using transaction CNMASSCREATE or Migration cockpit | Data Team |
2 | Load 3 records for < > to validate if data is loaded successfully without errors | Data Team |
3 | Load 3 records for < > to validate if data is loaded successfully without errors | Data Team |
4 | Proceed with full load if steps 2 and 3 are validated | Data Team |
5 | Validate few records loaded by accessing CN41N report | Data Team |
6 | Generate post load report if step 5 is validated | Data Team |
Load Phase and Dependencies
Configuration
| Item # | Configuration Item |
|---|---|
| 1 | Controlling Area |
| 2 | Company Code |
| 3 | Factory Calendar |
| 4 | Currency Code |
| 5 | Project Profile |
| 6 | Budget Profile |
| 7 | Planning Profile |
| 8 | Functional Area |
| 9 | Profile for WBS scheduling |
| 10 | Project Coding Mask |
| 11 | Settlement Profile |
Conversion Objects
| Object # | Preceding Object Conversion Approach |
|---|---|
| 1073 | Profit Centre |
Error Handling
| Error Type | Error Description | Action Taken |
|---|---|---|
| Invalid Data | Project Definition already exist | Correct upload data |
| Invalid Data | No. of Person Resp. does not exist | Correct upload data |
| Invalid Data | Applicant no. does not exist | Correct upload data |
| Invalid Data | Profit Centre does not exist | Correct upload data |
| Invalid Data | Company Code does not exist | Correct upload data |
| Invalid Data | Functional area does not exist | Correct upload data |
| Invalid Data | Two projects per company code not allowed for project with project profile ZPS0004 - Intercompany Recharges | Correct upload data |
Post-Load Validation
Project Team
Completeness
| Task | Action |
|---|---|
Verify Count | SyWay I2M Data Team to verify the record count created in target S/4 HANA by accessing post load reports or standard reports from S/4 HANA. |
Verify Logs | Check if there is data that failed to load and perform the necessary actions (e.g. register as post load issue or attempt to load the record again, etc.). |
Accuracy
| Task | Action |
|---|---|
Conversion Accuracy | Verify that the Project Definition in target S/4 HANA were loaded correctly via Project Builder display and table PROJ |
Business
Completeness
| Task | Action |
|---|---|
| Verify template Project data - Project Definition | Extract data from PS report CN41N in S/4 Hana |
Accuracy
| Task | Action |
|---|---|
| Verify template Project data - Project Definition | Extract data from PS report CN41N in S/4 Hana |
Selection Screen
Not ApplicableData Collection Template (DCT)
Target Ready Data Collection Template will be created for Project Definitionsdata with exception of some fields which require transformation as mentioned in the transformation rule.
Project Definition DCT Rules
Separate MDS for Project Templates. Ones created via PPM item will inherit its number from PPM item
If Created via PPM Item, this field will be copied from PPM item
Inherited if created Project is created via PPM item field Person Responsible Position ID
Inherited if the project is created via PPM item field - Project Financial Controller Position ID.
Inherited if created Project is created via PPM item field Area
Inherited if Project is created via PPM item field Profit Centre
Inherited if created Project is created via PPM item field Plant
ZPS0003
ZPS0004
ZPS0005
Inherited from Template if created Project is created via PPM item
This field determines the behavior of the stock for Project. The Field will be automatically determined from Project Profile. Once set it cannot be changed.
No Project Stock will be used
Refer configuration table field TFKB-FKBER for allowed values."
Default from Template where applicable
Inherited if created Project is created via PPM item
This field automatically inherits the PPM Item Type from the associated PPM Item. It remains blank when the PS project is created manually for Project Profiles ZPS0003, ZPS0004 & ZPS0005
Blank.
Extraction Dependencies
1
Ensure DCT is collected for Project Definition
Data Team
2
Perform preliminary completeness check
Data Team
3
Raise issues as defects if Req # 1 to 2 are not met
Data Team
4
Repeat Req # 1 to 3 if required
Data Team
Transformation
The Target fields are mapped to the applicable Legacy field that will be its source, this is a 3-way activity involving the Business, Functional team and Data team. This identifies the transformation activity required to allow to make the data Target ready:
- Perform value mapping and data transformation rules.
- Legacy values are mapped to the to-be values (this could include a default value)
- Values are transformed according to the rules defined in
- Prepare target-ready data in the structure and format that is required for loading via prescribed Load Tool. This step also produces the load data ready for business to perform Pre-load Data Validation
Transformation Run Sheet
1
Obtain DCT Sign-off from Business
Data Team
2
Execute and Load and perform Transformation
Data Team
3
Monitor the transformation progress and ensure performance and completion is within allowed timeframe
Data team
4
Review and Validate Error and Preload Reports
Data Team
5
Generate data load count.
Data team
6
Generate Load Files
Data Team
7
Transformation Rules
Transformation Mapping
Transformation Dependencies
List the steps that need to occur before transformation can commencePre-Load Validation
Project Team
Completeness
Accuracy
Business
Completeness
Accuracy
Load
The load process includes:
- Execute the automated data load into target system using load tool or product the load file if the load must be done manually
- Once the data is loaded to the target system, it will be extracted and prepared for Post Load Data Validation
Load Run Sheet
Load Phase and Dependencies
Configuration
Conversion Objects
Error Handling
Post-Load Validation
Project Team
Completeness
Accuracy
Business
Completeness
Accuracy
| Task | Action
|---|
Key Assumptions
- Master Data Standard is up to date as on the date of documenting this conversion approach and data load.
- Project Definition is in scope based on data design and any exception requested by business.
- The DCT should validate the project coding mask numbering as per the SAP instance config.
- Validation / substitution might required to switched off at the time of load