You are attempting to cost material x in plant p. The BOM for this material has a status that does not allow costing

Example 

You are attempting to cost material 85151 in plant 7971. The BOM for this material has a status that does not allow costing

 




Procedure

Enter a status Z1 in the view costing of the master data of the material code with transaction MM02 until the BOM is updated

 

 


STEP 1

  • Use transaction MM02
  • Enter the material code and 

 

 

 

 


STEP 2

  • Select the view "Costing 1" and 

 

 


STEP 3

  • Enter the plant code and 

 

 

 


STEP 4

  • Enter the status Z1 in the field Plant-sp.matl status and save 
  • A message confirms the change 

 

 

 

What happens if the issue is not solved and the costing released ?

  • The field BOM is blank
  • As there is no valid BOM, the raw material 85151 is the same as the finished product 85151