Responsibility area: Perform Costing Monthly Closing |
Guideline |
Before start processing the process orders costs you have to run cycle CCCCNA in real mode in order to settle the "process order variances statistics" from cost center CCCC-9201 (In some cases there are cost centers that start with PPPP-9201 for historical reasons). At this stage only small amounts should be on cost center (rounding amounts). In case of high amounts in the balance should be analysed the reason before doing the settlement. For threshold please consider 3K€. |
| If errors occurred in previous steps check the settlement rule and contact local responsible to correct it. |
|
I perform corrective action if there are some errors in the previous steps |
|
If all orders were balanced for closing month means that this task has been successfully executed. |