The system established that, in the MRP view for material x in plant p, the quantity structure should be selected through the production versions. When the material was costed, entries were made for the BOM and/or routing. However, the system could not determine either a suitable or a valid production version |
Example
The system established that, in the MRP view for material 97861 in plant 7991, the quantity structure should be selected through the production versions
When the material was costed, entries were made for the BOM and/or routing. However, the system could not determine either a suitable or a valid production version
Procedure
| Enter a status Z1 in the view costing of the master data of the material code with transaction MM02 until the production version is created or updated |
What happens if the issue is not solved and the costing released ?

=> In this example the costing is not complete: there is only one a raw material but no activities. The costing is not correct.