Start the transaction using the menu path or transaction code CK75N

Double-click 




 

Change additive costs : Initial Screen

 

 


  1. Enter the material code and the plant code 
  2. Enter the costing variant ZFO and the costing version 1

and 

 

 


  1. The current price is 10 SGD / kg 
  2. Click on   to change the price

 



 

 

 


The following screen appears

Update the additive cost in the column Price – total. It can be zero (0,00)

Save the new cost  and we return to the main screen 

 

 

 

 

The cost is updated in the column TOTAL value

 If it is correct, you must save it  and a message confirms the cost estimate is saved