Table of contents
1 Objective and Scope
1.1 Objective of this Procedure
1.2 Scope
2 Abbreviations
3 Responsibility
4 Budget approval and budgeting
4.1 Target process for Projects
4.2 Project Creation
4.2.1 The Standard Project definition
5 Projects types that could be managed for PF1 and WP1
6 Standard Project Definition Creation for PF1 only
6.1 Standard Project Definition (SPD) with country Specificities
7 Demolition Project Creation
7.1 Demolition Project Creation:
7.2 Changing Project – CJ02:
7.3 Project deletion
8 BUDGETING
8.1 Original Budget- CJ30
8.2 Transfer of Original Budget - CJ34
8.3 Change Supplement - CJ37
8.4 Change Return - CJ38
9 Project creation using transaction ZZJ01
9.1 Create PS projects before COLMAR-Start transaction ZZJ01
9.2 Complete the following fields :
9.3 Create Budget and Planned costs-Start transaction ZZJ01 for file before COLMAR
9.4 Complete the following fields :
10 Uploading COLMAR file format
10.1 Create PS projects for COLMAR-Start transaction ZZJ01
10.2 Complete the following fields :
10.3 Create/Change Authorized Budget for COLMAR-Start transaction ZZJ01
10.4 Complete the following fields :
11 Plan Versions only for PF1
12 Cost Planning - CJ40
13 Reports for Budget and Planned costs
13.1 Report CJE0 for PF1
13.2 Report S_ALR_87013558 for WP1
The purpose of this document is to describe the transactions related to the process of investment budget requirement and approval as well as depreciation planning
This operating procedure (OP) applies to the necessary transactions for approval and planning process of the current PF1 & WP1.
SU MAC - Service Unit - Management accounting
SPD - Standard Project Definition
PS - Project System (SAP module)
Capex/COLMAR Team - Department that manage and approve the Budget
BDG - Budget
SU MAC | Creation of new projects, insert and maintain Budget + Planned Cost |
Capex/COLMAR Team | Department that manage and approve the Budget and sent to SU MAC for creation/update |

SU MAC | SU MAC is responsible to create and maintain SPD – Standard Project Definition . |
IS |
|
Local Accountants | Local accountants have to validate the SPD created / modified by SU MAC |
Project types which could be managed are:
N: Normal
C : Current
M: Medium
J: Major
D: Demolition
P: Preliminary/Approach/Test
|
|

| ||||
Plant Code | Slash | Budget Size (C or S) | 0 | Business Area |
BWF | / | C | 0 | 7336 |
Note: For Germany, please refer to the Country Specificity topic, on this operational procedure.
|
The transactions for Standard Project Definitions are: | |
|
All |
We need to use SPD with a specific structure for the countries mentioned below (France, Belgium, Italy - exception for Spinetta and Bollate, Spain and Germany):
| |||||||||||||||||||||||||||
France |
| |||||||||||||||||||||||||||
Germany |
|
There are two situations that might occur with Demolition Project Creation:
The project update is performed in transaction CJ02.
Before update any project SU MAC has to check if there is any posting amount on WBS Project:
In case of:
If projects have been created by mistake and the status is still "Created" and neither budget nor planning values have been maintained, it is possible to delete such projects.
First step is always to check the project status and budgeting. Call up transaction CJ02, enter the project number and push "Enter":

Scroll to the right an check system status: |
Call up CJ02. Replace 550 by XXX and click on project definition button
:
Replace 550 by XXX like in WBS element:
Click on "Edit", "Status", "Deletion Flag":
Save your data
.
| |||
| |||
| |||
Function | Menu Path | ||
Delete WBS elements directly | Edit → Delete → Delete object or | ||
Provide the WBS element with a deletion flag. | Edit → Status → Deletion flag | ||
Canceling Deletion Flags | Edit → Status → Revoke deletion flag |
If you delete WBS elements or set a deletion flag for them, subordinate WBS elements, and assignments are also deleted or have a deletion flag set.
| | |
To be able to revoke the deletion flag, you must first show the WBS elements that have been flagged for deletion. To do this, choose Edit → Object → _Display deleted → Disp._ The WBS elements with deletion flags are highlighted in grey. You can now cancel the deletion flag for the required WBS elements.


The original budget is never changed with CJ30. To transfer amounts from project or to project or from year to year use CJ34. Call up CJ34 and enter "sender year", "receiver year" and "text".
Enter the "sender WBS element", the "receiver WBS element", "currency" and "amount to be transferred (always use the thousand format , for instance if the related amount is 30 K Eur, it should be inserted the amount 30.000,00 Eur)" and click on button "check (F9)" and save.
This transaction is used to increase the budget amount. Call up CJ37, make the required entry project definition:
Enter the amount to be added in the budget:
Click button "Annual Overview" and enter the annual amounts (only the value to be added in the budget):
Click button "Check (Shift + F4)" and "Save (Ctrl + S)".
This transaction is used to return unnecessary budget amounts. The screens are similar to CJ37.
For each Project to be created, the program selects the Standard Project created in the corresponding Company/Plant/Business Area, and uses it as template to create the WBS elements.
Notes:
Preliminary:
The file used by CAPEX/COLMAR to exchange data related to CAPEX budgets must be checked and converted to a format accepted by the program:
Example attached in Excel format:

You get the following screen:
Colmar file | DO NOT flag the checkbox |
Creation PROJECTS | Select the option "Create PROJECT" |
Input file | Use the button at the end of the field ( |
Session name | Give any name. (this name will be given to the batch input file that will be created by the program). |
Year | The year entered in this field is used by the program to select records to be treated. (check on column AK : "Approval Year").Note: the program also checks that the status of the project is REL. |
Test run | This flag allows to run the program in test mode, in order to check the content of the file. |
Click on
to start the program.
Output of the transaction:
1. If executed in test mode, the program will:
No SBDC is created.
2. If not run in "Test mode", the program will:
Check the list issued by the program; if the Projects and WBS are correct, then execute the SBDC session with transaction SM35 (background mode).
When the SBDC has finished to run, check its status and correct errors if any.
You get the following screen:
Colmar file | DO NOT flag the checkbox |
Creation BUDGET + PLANNED COSTS | Select the option "Creation BUDGET+PLANNED COSTS" |
Input file | Use the button at the end of the field ( |
Session name | Give any name. (this name will be given to the batch input file that will be created by the program). |
Year | The year entered in this field is used by the program to select records to be treated.Note: the program also checks that the status of the project is REL. |
Test run | This flag allows to run the program in test mode, in order to check the content of the file. |
Click on
to start the program.
Output of the transction:
If flag "Test run" not set, the program will:
Then, execute the SBDC sessions with transaction SM35 (background mode).
When the SBDC has finished to run, check its status and correct errors if any.
Remark: PS Projects created by the program, with their budget planned costs can be listed using transaction CN41 and PSIS report CJE0 – 12KST1A.
|
COLMAR format could be uploading only for the following three options:
A PS project will be created for each type of Project mentioned below that is accepted (status FA or AB) in an Approval Year.
If the PS Project already exists in SAP, the program will give Warning message that the Project already exists.
Project types which could be managed are:
N: Normal
C : Current
M: Medium
J: Major
D: Demolition
P: Preliminary/Approach/Test
For each Project to be created, the program selects the Standard Project created in the corresponding Company/Plant/Business Area, and uses it as template to create the WBS elements.
Notes:
Preliminary:
The file used should be downloading of proper Query in COLMAR application. It must be checked by BO team and converted to a format accepted by the program:
Notes:
Field Family Inv. Project (Column Y):
In the table below we have possible entries for field Family Inv. Project. As we have difference between values in COLMAR and PS PF1 system, we use table ZZS_T900 to make the mapping between both:
*in yellow color are entries in the table ZZS_T900
COLMAR | PS in PF1 | ||||
FAMILY | Family Name | PROJ-ZZFAMILY | Family Name | ||
FACILITIES | Facilities | FACILITIES | Facilities | ||
GEC | GEC | GEC | Group Engineering & Construction | ||
RI | R&I | R&I | Research & Innovation | ||
REGAFFAIRS | REGAFFAIRS | REGAFFAIRS | Regulatory Affairs | ||
RG | Regular | REGULAR | Regular | ||
SBS-DPS | SBS-DPS | SBS DPS | SBS - All services except IS | ||
SBS-IS | SBS IS | SBS IS | SBS - Informational System |
Field: Investment type – Scale
In the table below we have possible entries for field Investment type in COLMAR application which corresponds to field Scale in PS module. As we have difference between values in both systems, we use table ZZS_T900 to make the mapping between both.
COLMAR | PS in PF1 | ||
Investment type | Scale |
| |
CUR | Current | CN | Current |
STR | Major | ST | Major |
NRM | Medium | NM | Medium |
DEM | Demolition | BD | DEMOLITION BUDGET |
PRE | Preliminary | PR | Preliminary |
Field Responsible person: As in COLMAR we do not support the Responsible Persons numbers we can link another field called Forecaster User ID to the proper person in PS. To find the proper Responsible person code in PS module we have accurately to update current table to manage both fields.
Transaction: OPS6
Table: TCJ04, access with transaction SM30
System: PF1_020 
Example for all the options attached in Excel format:

You get the following screen:
Colmar file | Flag the checkbox |
Creation PROJECTS | Select the option "Create PROJECT + WBS Level 1" |
Input file | Use the button at the end of the field ( |
Session name | Give any name. (this name will be given to the batch input file that will be created by the program). |
Year | The year entered in this field is used by the program to select records to be treated. (check on column C : "Approval Year").Note: the program also checks that the status of the project is FA or AB. |
Test run | This flag allows to run the program in test mode, in order to check the content of the file. |
Click on
to start the program.
Output of the transaction:
1. If executed in test mode, the program will:
No SBDC is created.
2. If not run in "Test mode", the program will:
Check the list issued by the program; if the Projects and WBS are correct, then execute the SBDC session with transaction SM35 (background mode).
When the SBDC has finished, check its status and correct errors if any.
You get the following screen:
Colmar file | Flag the checkbox |
Create/Change Author. Budget | Select the option "Create/Change Author. Budget" |
Input file | Use the button at the end of the field ( |
Session name | Give any name. (this name will be given to the batch input file that will be created by the program). |
Year | The year entered in this field is used by the program to select records to be treated.Note: the program also checks that the status of the project is FA or AB. |
Test run | This flag allows to run the program in test mode, in order to check the content of the file. |
Click on
to start the program.
Output of the transction:
If flag "Test run" not set, the program will:
Then, execute the SBDC sessions with transaction SM35 (background mode).
When the SBDC has finished, check its status and correct errors if any.
As mentioned above the original budget in PS is only changed in a limited number of cases with special transactions. The tool for simulations, estimations and forecasts is the cost planning. To have a clear distinction, different plan versions are used. |
0 Initial cost estimate (SAP standard version for CO objects)
AFC Anticipated Final Cost (up to date best forecast) is the Solvay version for revision of plan data.
This transaction includes initial cost estimate as well as changes (supplements, returns etc.). Entries are possible on all levels of WBS element. Call up the transaction, enter a project definition or WBS element and select the wanted version:
CJ40
Similar to transactions for budgeting, entries for overall and annual overview are possible:
For Subsidies Projects, the values must be negative!
| |
The report includes the most important figures: plan, budget, actual cost and down payments, commitments, assigned and available amount
|
The report includes the most important figures: plan, budget, actual cost and down payments, commitments, assigned and available amount
End of document