Tasks to be completed when documenting an operation (from creation to publication)1. Enter the Title of the operation / page2. Add the following Labels :
3. Fill in all fields as described above4. Name the title of each section using OPD methodology naming convention - Infinitive verb without the “to”, mainly action verb...something) - " I do something..."5. Once the description of the operation is completed, ensure it is approved and published by launching the SBS-Finance approval workflow |
| Domain: Country Accounting |
Responsibility area: N/A |
The purpose of this document is to describe how to transfer transportation cost from cost center to order.
This procedure applies to company 0366 Solvay Peroxythai Ltd, Bangkok.
See Finance Glossary:
Every end of each month, company 0366 will allocate costs from cost center MT80061430 to Profit Center by Material codes.
Local will send an excel file to Finance Operations team.
The file is shown as below:
Before the posting, Finance Operations team will check the total amount of the cost center:
Fill in all details as below :


Total amount in screen should be equal to the total amount in excel file from local
If the value is different check again to correct with local
After checking the data, Finance Operations team will transfer the amount under cost center MT80061430 to material via an upload file.

Fill in all detail as below in upload file:
Upload file via transaction ZZF_POSTING_FILE and after posted TPT upload file, Report GR55 (cost center MT80061430) must be zero.
Check cost center via GR55 - ZCS1:



0366 & 6034 Accounting team : charoennawarat.suporn@solvay.com |
End of document.