If a request is received to change a project to Fixed Asset
Go to CJ02 and select the project

Select the WBS/Line where you want to create as final assets: Extras -> Create completed Asset

Go to the next screen and complete the missing information provided in the request: Asset Class and Cost center.

In the bottom of the SAP screen the following message will appear:

Go the settlement rule of the WBS to confirm you have a new line for the final asset.

Then go back
to the previous screen, in order to set up the project as Technically completed: Edit -> Status -> Technically complete.

Check if the status in WBS is ''TECO''.

The project can now be saved
.
Then, display again the project and settlement rule, in order to find the final asset number as below ( eg: 250000024135-0).