title

The Multilvel Pr. Determination step calculates Multi-Level Actual Prices, including roll-up of Price Differences and revaluation Amounts from Cost Centers & cost collectors

 

Click on the lock  to allow post closing 

 

 

 

 

Click on    in the column «Parameters»

 

 


  1. Select "Check Against Standard Price for Period"
  2. Delete flag in "background processing"
    Mark "Save log"

Go back by clicking 

 

 


Click on 

 

 


Click on  in column Execute»

 

 

 

 


The log is displayed.

Usually no further checks are necessary.

Go back by clicking 

 

 

 


Click on   below the frame

 

 


Click on 

 

 


There should be a green square   in the column «Status» and the number of materials successful selected in column «Successful».