Quantity of production lost because of breakdowns or production stoppages caused by maintenance (OEE C2 and C4)
The set of strategic indicators has three main objectives:
- Verification of the effectiveness of maintenance processes
- Comparisons between plants independently from the business
- Comparisons with external organizations
Direct impact of maintenance on industrial performance (in TO) = OEE category 2 losses + OEE category 4 losses
Depend of the plant
Manual input of OEE losses from production report
(Site template > Yearly tab)
| Causes categories | RCS | Solvay | ||
| RCS | PF1 | |||
| OEE Losses C2 | 2 - Planned Maint. | |||
| OEE Losses C3 | 4 - Unplanened Maint. | |||
| Theoretical Production | Maximum demonstrated Capacity (MDC) | |||