Responsible : Physical inventory manager Frequency : Annual with a quarterly up-date Control : IAC.02.03 / control owner: FRA |
The annual planning includes : 1. A list of the inventory storage location - On site
- Off site: inventory on consignment, held in third parties facilities or by toll manufacturers
2. Frequency of cycle counts 3. A planning taking into account the following objectives A count of items representing 90% of the value of prior end inventory should be done as of 30th September, each year. A count of items representing 100% of the value of prior end inventory should be done as of 30th November, each year.
That planning must be communicated to FRA, who could organize/support the supervision by a third party without prior notification to PIM. Planning is proposed by PIM and validated by FRA before end of September with consideration for 2 periods : - October 1st to November 30th of current year : revision of on going calendar :
- Starting with actual inventory coverage rate as of October 1st (in theory 90%)
- Showing completion of 100% target as of November 30th
- Dec 1st of current year to November 30th of following year :
- That planning is detailed by material code and SAP plant where applicable
- Where SAP isn’t available, that planning is also used to follow progress of coverage inventory count
- FRA is responsible for recording that planning in the dedicated group repository and external auditor have access to that repository
|
|