This Metric shows 2 calculation, 1 for the past week, and 1 for the current week
To be defined by site
Past week: Number of Completed Work Orders issued from a Maintenance Plan / Total Number of Work Orders issued from a Maintenance Plan Current Week: Number of Call, Notifications or Work Orders issued from a Maintenance Plan with Planned Date between Monday and Sunday. |
|---|
Weekly
For every Work Order, Notification, or Call issued from a Maintenance Plan that should have been completed during the past week (Planned Date between Monday and Sunday), the system compares the earliest date that could be find on a Work Order on its several Closing status (GS45 or GS50 or GS55 or 6CMP or CNF or Reference date of the ECO )
- against the Required End date of the Notification
OR
- against the Planned Date of the Call if there is no Notification
| Field name | From | To | I/E | ||
| WO Status to declare a WO finished: GS45 or GS50 or GS55 or 6CMP or CNF or Reference date of the TECO of the WO | Monday (W-1) | Sunday(W-1) | I | ||
| Only Work Orders from Maintenance Plan | I | ||||