WBS - “A work breakdown structure defines all the things a project needs to accomplish, organized into multiple levels, and displayed graphically.”  


Domain: SU Management Accounting

Responsibility area: Maintain Costing Master Data

Table of contents 

By default the table of contents displays Heading 1 & Heading 2 (other levels can be added)


Scope

3. Remove the icon when not applicable

ERP

4. Remove the icon(s) when not applicable

PF2 / WP2

Frequency

5. Remove the icon(s) when not applicable

 

References

CJ20N

CJB2

Forms

Attachments



 I receive a request to update/create a WBS element settlement rule



1. Objective and Scope

1.1. Objective of this Operation

The purpose of this document is to describe the process of creating a WBS (OPEX/Expense).

1.2. Scope

This document applies to all the processes of creating a WBS to process expense costs (non capitalized).

2. Definitions

See Finance - Glossary

3. WBS Creation

3.1. I receive the request to create a WBS

I receive a request to create a WBS, some mandatory fields are necessary such as:

  • WBS Code
  • Description
  • Cost Center
  • SRM7 Code (Position of person approving shopping carts)


3.2. I search an existing Project


After the project code is provided and details to introduce into the WBS we can enter the project using CJ02 or CJ20N, in this case we will use "R8.PU05SP" and T-Code CJ20N in WP2.







The Project Structure has Project R8.PU05SP in first line, WBS level 1 R8.PU05SP in second line and WBS level 2 R8.PU05SP.xxx in third line.



3.3. I create the WBS element


In this case we will create a new WBS Element (level 2) R8.PU05SP.305 inside Level 1 WBS R8.PU05SP.
By selecting WBS Level 1, right click mouse to view options and select Create > WBS Element.


The new line in the project was now created but with several empty fields in tab Basic data that will need to be edited:

WBS Element Code: R8.PU05SP.305
WBS Element Description: Energy CO2 Operations
Proj. Type (Expense): Internal Operations for Regular Family Projects and Innovation Project for R&I Family Projects.
System Status: (REL) - Released and SETC (Settlement Rule Created) - Read 3.3. Paragraph
Person Responsible No.: Code managed in T-Code OPS06 to identify who is in charge of the project.
Account Assignment Element:
X (Should be selected in order to receive costs).
Responsible Cost Center: Cost Center that the costs will go trough.
Required Cost Center: Cost Center that the costs will go trough.
Required Company Code: Automatically populated after Cost Center are inserted.


Next tab to be maintained is Assignments:

The fields will be automatically populated using the same information provided in the Project Master data.
For Expense Projects the Object Class: Overhead should be selected. All remaining information should be according to request.


Next tab to be maintained is User fields:

Only some GBU's use field Code of Group, in order to aggregate projects by groups created in T-Code ZWPST004.

Checkboxes: X Replicon  (If the WBS is used to track and charge hours of labor by engineer's or laboratory employees)


Next tab to be maintained is Cust. Enhancement:

The majority of the information related to Cust. Enhancement is to identify the market that is related the WBS and Invoicing information.

First Fields are related to the GBU/Business Unit, that should be filled in according to request.


Fill in next fields related to WBS Family, and Position Code (SMR7 Approver) provided by the requester.


Specifically for R&I Projects the WEGO Number and Category can be requested:


3.4. I create the settlement rule

The Settlement Rule and Settlement Parameters define how the costs will be processed for expense costs we can have the following cost objects available:

  • Cost Center
  • WBS
  • Order
  • GL Accounts

  • Edit -> Costs -> Settlement Rule-> Go To-> Settlement Parameters:



Options Available will change according to what is defined in the Settlement Rule Parameters:


For R&I WP2 example, to allocate costs to a CC in the Settlement Parameters should be the Settlement Profile: ZPS3 and Allocation Structure: AL.

There are several different combinations possible in order to reflect the costs with different accounts in the receiver cost object.

3.5. I inform the requester


3.6. Other requests - Creation


During the month there may be requests such as this one:


image-2026-4-20_12-45-50.png


Open transaction CJ02

image-2026-4-20_12-46-46.png


If the project was already created, we just need to add a new “sub-level” (WBS element):


image-2026-4-20_12-47-45.png



Check if everything is filled under "Assignments":


image-2026-4-20_12-52-2.png




Under "Responsibilities", the cost center must be added

 image-2026-4-20_12-53-39.png



Under "Control", the Investment profile must be defined

(Otherwise the costs of WBS could go directly to the Cost center).

image-2026-4-20_12-55-2.png



A few WBS elements may seem intangible (ZAUC_I), like Labour or planning activities.

However, they should be defined as ZAUC_T (RCS Tangible AuC) as they are part of the process (if the engineer doesn’t set the machine, it will not work).



Define WBS fields such as WBS family and Position

 image-2026-4-20_12-56-38.png


image-2026-4-20_12-56-59.png



Note: WBS family for “Colmar projects” are always REGULAR.



Set the WBS element status

image-2026-4-20_13-0-6.png



While adding the first WBS element of a new project, usually the status is on creation. It should be released.


The best way to change it is to change the “header” of the project:

image-2026-4-20_13-1-16.png

image-2026-4-20_13-1-32.png



3.7. Notes regarding WBS Indicators


image-2026-4-20_12-48-48.png



The fields must be selected when necessary:


SU – WBS element used in project summarization (it’s always set).

PE – Planning element: used as a tool of planning just in a few plants.

Acct – Account assignment element: when ticked it means that WBS element can have costs associated; if not ticked, then the WBS is just statistic.

Bill – Billing element: only used for Interco projects (COLMAR projects are excluded from Interco.)


3.7. How to find the correct Position


Go to transaction ZWFA119.

image-2026-4-20_12-58-41.png


image-2026-4-20_12-59-0.png




3.7. Useful notes


a) To go back while changing WBS, use:

image-2026-4-20_13-2-23.png


b) Another way of checking the project: CN43N

image-2026-4-20_13-2-49.png


4. R&I WBS Creation


Enter the "SCO of R&I WBS creation form" file.


View the lines that are associated with new requests to create;

In column D we can see which company the order refers to;


See column K for the type of project that needs to be created;


Insert the project into transaction CJ20N and create the WBS with the information entered from column L to column AH;

Example:

 


Note: Examples of information that we can observe in some columns.


When we need to do the invoicing, we have to send the information entered between the AI ​​column and the AT column to the Intercompany team;

Example:



Note: Examples of information that we can observe in some columns.


Example of Ticket created to the Intercompany Team:


After the intercompany team answers and completes their update, we can update the "SCO of R&I WBS creation form" file from cell AU to cell AZ.

In this way, the request is processed and the requester can proceed with using the WBS.



5. Opening WBS with reinvoicing


Create an Intercompany Ticket: (Ex:390648)




In the ticket description, include the WBS (Work Breakdown Structures) that are in column X of the attached Excel spreadsheet and attach that same file:



After creating the Intercompany Ticket, you need to reply to requester Ticket with its Request ID;


After the Intercompany team completes the process:

Go to transaction ZZJ02;


 


“Execute”

Select "Export to Excel". Copy the Excel file sent by the Controller to the new Excel sheet;



Important Note:

- Copy everything from column A - AD; Copy individually from column AE - AH because the columns do not correspond;

- Delete the values ​​from column K;

- Place an “X” in column AH if there is a Replicon; Do not consider the tabs “2nd Settlement Receiver (interco)” and “2nd SR Percentage (interco)”;

-Choose “Save as” and go back;

-Select “Dialog run” and put the excel file in the “File name”;


“Execute”

Select all projects and choose “Project/WBS/Settl. Rule”;


NOTE: It's okay to create projects with warnings, as long as they don't contain errors.

Go back and choose “Yes”;

Once the projects are created, you need to reply via Ticket to confirm that everything is OK;


“Dear Requester_name,

The projects were created as requested.

Could you please confirm if the projects are set up correctly, so we can proceed with the release.

Thank you in advance,

Best regards,”


After receiving the OK, release the projects;


“Execute”

The X in the “R” means the projects have not yet been released;




The projects have now been released;

Inform the requester that the projects have been released.