| BW Server | WBP |
|---|---|
| Application | PP - Production Planning |
| Query Name | BW - Capacity planning - Monthly (Core Query) |
| Query Technical Name | BW_QRY_CUB_CAPM_0001 |
| Core/Specific Scope | Core |
| Specific Reason | If the query is not core, explanation on why it's specific (Ex : Special Tax system in India...) |
| Provider Name | CUB_CAPM |
| Usage type | Direct execution in Analysis |
| Expected users | Supply Chain, Production Planner, Capacity Planner, Demand Planner, Scheduleur |
| Related queries |
This report in BW is showing in a period until 5 years the load of production resources depending on their working hours, and on the production plan (planned orders & process orders) in place. The load is expressed in hours and % and Qty Produced is based on phase in Recipe.
There are two transactions in SAP that can be used for capacity analysis:
In each case,
However,
Two Capacity Planning reports were developed in BW to mirror the existing reports in APO
CM01 | CM38 | BW | ZWPP31A | |
Shows Both Hours and Qty | X | X | X | |
Shows past Due Elements | X | X | ||
Scaled to display hours within period | X | X | X | |
Qty Produced is shown in Start Period, Finish Period or Both Periods | Both | Both | Finish | Finish |
Qty Produced is based on Planned order Qty | X | X | X | |
Qty Produced is based on phase in Recipe | X | |||
Multi-step Recipe Resource is accommodated | X | X | X | |
Allows for 5 years of capacity review | 180 days | 180 days | X | X |
| Variable Name | Authorization Object | Description |
|---|---|---|
| Convert Unit | No | To convert to a single quantity unit |
| Plant | Yes |

| Object | Filter Value | Explanation |
|---|---|---|
| None | Ex : <> 1 | Ex : Exclude intercompanies |
| Characteristic Name | Characteristic code | Explanation |
|---|---|---|
| Work Center | 0WORKCENTER | Displays Work Center Code and Name (Medium text) |
| Material | Display material code and name |
Key Figure | Description | Calculation rule detail |
|---|---|---|
Capacity | Number of hours available in the period | |
Stream (85%) | Indication of 85% of capacity, typical OEE | capacity * .85 |
Cap. Con | How many hours are allocated to that resource | |
Capa cons % | % of capacity utilisation | Cap.con/Capacity * 100 |
Prod | qty planned to be produced in the resource in that period |
Unit : Variable
The full explanation on how the quantity conversion works can be found in the Quantity Unit Conversion page.
Each night AFTER MRP completes, a job runs to extract the MRP results. These jobs are linked
MRP Jobs here

Data Extract Jobs here

The data then is loaded into BW
In case of new plant, post an IS request to include your plant on the Data Extract Jobs in SAP