Go to transaction code KKF6N and select

  1. the material code 
  2. the plant code 

 

 

 


Select  to create the new cost collector, and automatically you'll get a screen to fill the following information:


  • Order Type: always use RM01
  • Select the correct production version for the respective plant

 




You'll receive a message asking if you want to create the preliminary cost estimate.
Select YES

  


 You can get the cost collector number as below information

 



You can also get the information of the costs calculated



You can also get the information of the costs calculated