Tasks to be completed when documenting an operation (from creation to publication)1. Enter the Title of the operation / page2. Add the following Labels :
3. Fill in all fields as described above4. Once the description of the operation is completed, ensure it is approved and published by launching the SBS-Finance approval workflow |
| Domain: Finance Data & Reporting |
Responsibility area: Ensure consistency of Reporting axis |
Solvay is organized in:
This structure is used to provide the proper reports for business follow-up
The purpose of this document is to provide the operational / technical details describing the maintenance of a Business structure in WP1.
This procedure covers the implementation of a new business structure in SAP WP1.
All requests for data under the responsibility of Finance Data & reporting must be made through the “MDWF” workflow.
For complex changes and topics, there are usually several preliminary contacts and the workflow is created when the solution has been designed and agreed.
In terms of reporting axes, the information can also be provided by an email from Corporate Controlling.
The description of the process of defining Reporting axes in the systems linked WP1 can be divided into 5 sub-processes, for an easier understanding:
New IECRA in an existing Activity 1
Implementation of an existing PF1 activity 1 in WP1
Reorganization of reporting elements “below activity 1”
Update of Group structure “above activity 1”
All the structure implemented by Data administrators and IS Materials & Structure Data team can be displayed in SAP transaction (Report ZWFAR571 - Reporting structure axes), which is a combination of axis managed at GBU level (Data administrators) and tables updated to link SAP codes to BFC codes.
The introduction of a new “BFC Activity 1” is requested by the GBU and approved by GAR / Corporate Controlling, who assign its code in BFC.
After GAR’s approval, the GBU needs to communicate to Finance Data & Reporting the necessary elements in order to activate the set-up process.
The BFC activity 1 is mainly materialized in SAP WP1 by :
Determination of the IECRA in the P&L
Go to the page Rules - WP1 - IECRA |
Determination of the IECRA in the Working Capital:
Go to the page Rules - WP1 - WC - Activity 1 & 2 |
The creation of a new “BFC activity 1” may require the maintenance of all or some of the following WP1 objects:
The implementation of a new “BFC activity 1” requires the following steps:
The implementation of a new “BFC Activity 1” requires the following steps:
CD x Div link to IECRA
IECRA link to Activity 1 (CDPRF in SAP) /ENTRP/ZSECT
Finance Data analyzes the request and, if all clear and ok:
Checks transaction ZWFAR571 (class ZS2 (new year) or ZS1 (during the year)) to validate that new combination/ structure appears.
Updates table ZWFAT228 to link :
CDPRF code to BFC activity 1 code,
ENTRP code to BFC group of activities if a new group of activities has been created
ZSECT code link to BFC GBU code
Checks in transaction KES2 if the new COPA characteristics codes is already available.
Updates table ZWFAT111 company code XEU1 for BW & BI4 reports
Updates ZWFAT111 at company level using GBU document. To be repeated for all companies quoted in the GBU document :
GBU doc / GBU xx / sheet “DC- Vte” and “DC Interco” to identify by Sale organization the cross DC (distribution channel) x division and sheet Soc (link sales org - company code ) to find in witch companies ZWFAT111 has to be updated or with SM30 on view V_TVKO_ASSIGN.
Example:
Sheet DC- Vte
BR33 / 9NxSB / IECRA in ZWFAR571 IECRA01219
ZWFAR571 : 9NSB IECRA01219 PHOSPHORUS DERIVATIV
GBU doc TS sheet Soc BR33 link to the entity
So you have to create in table ZWFAT111, company 7523 the link IECRA1219/ market TSDP
This sub-process deals with the request of a new distribution channel (new market) or new product division within an existing “activity 1”.
Typically, this type of decision is made by the GBU Global Controller.
The GBU needs to communicate to Finance Data the necessary elements in order to activate the set-up process.
A new IECRA involves the following SAP objects:
Distribution channel (DC) x Division link to IECRA ( ZWFAR571)
IECRA link to Activity 1 (CDPRF in SAP) /ENTRP/ZSECT (ZWFAT228)
The implementation of a new IECRA requires the following steps:
GBU data administrators request, with a template to IS Materials & Structure Data team, the creation of a new link DC x Div in transaction ZWOC54A (freshdesk ticket).
The GBU data administrator creates the structure in ZWOC54A, linking the combination DC x Div to IECRA / CDPRF / ENTRP / ZSEECT
The GBU controller makes a request to Finance Data including the elements defined in step above or Finance Data formalizes in one Worflow the structure validated together.
DC x Div link to IECRA
IECRA link to Activity 1 (CDPRF in SAP)
Finance Data analyzes the request and, if all clear and ok:
Checks transaction ZWFAR571 (class ZS2 (new year) or ZS1 (during the year)) to validate that new combination/ structure appears.
Updates table ZWFAT228 to link CDPRF code to BFC activity 1 code
Checks in transaction KES2 if the new COPA characteristics codes is already available.
Updates table ZWFAT111 company code XEU1 for BW & BI4 reports
Updates ZWFAT111 at company level using GBU document. To be repeated for all companies quoted in the GBU document :
GBU doc / GBU xx / sheet “DC- Vte” and “DC Interco” to identify by Sale organization the cross DC (distribution channel) x division and sheet Soc (link sales org - company code ) to find in witch companies ZWFAT111 has to be updated or with SM30 on view V_TVKO_ASSIGN.
This sub-process deals with the request of a new distribution channel (new market) or new product division within an existing “activity 1”.
Depending on the type of flows to implement (sales of products, services or only post costs on one cost center) the process will be different.
The SAP Objects, roles and actors are the same as "New IECRA in an existing Activity 1" process.
The production division in WP1 must include in description between brackets the PF1 product division code. |
This sub-process deals with the request to change the link for IECRA’s to BFC activity 1.
Typically, this type of decision is made by the GBU Global Controller.
There are 3 types of updates:
The GBU needs to communicate to Finance Data the necessary elements in order to activate the set-up process.
Open a freshdesk ticket to IS requesting to add *OBS* at the beginning of IECRA description in KES2
Update table ZWFAT111 in XEU1 & in all companies impacted with date end of validity 31.12 of next year, to avoid COPA issues. If activity 1 linked to IECRA also became obsolete, create a new entry for one year on another activity 1 defined with the GBU.
Update all intercompany tables ZWFAT041, ZWFAT042, ZWFAT043 for the obsolete IECRA.
Update table ZWFAT111 in XEU1 & in all companies impacted: Create a new line by copy with the new validity date from (Most of the time the first of January of the current year to 31.12.9999 and the end of validity for the old line will be updated automatically.
Update tables ZWFAT111 in XEU1 & in all companies impacted: Create a new line for the new IECRA’s linked to the activity 1.
At the end of each year, the Corporate Management decides on the modifications of the group structures, in terms of Operating Segment (clusters), groups of GBU, GBU, group of activities and “activity 1 and 2”.
The update of Group structure “above activity 1” is requested by the GBU and formally accepted / decided by Corporate controlling, who implements the required changes in BFC.
After Corporate controlling approval, corporate controlling & the GBU (administrators or contact defined for the GBU) needs to communicate to Finance Data the necessary elements in order to implement changes in the ERP’s.
Checks transaction ZWFAR571 (class ZS2 (new year) or ZS1 (during the year)) to validate that new combination/ structure appears.
Updates table ZWFAT228 to link CDPRF code to BFC activity 1 code
Checks in transaction KES2 if the new COPA characteristics codes is already available.
Updates table ZWFAT113 in all impacted company codes
Update the Profit centers hierarchy, if activity 2 has to be moved under a new ENTRP code or ENTRP code have to be move under a new ZSECT code. Be careful that IECRA code in profit center link to VS link to activity 2 must be in same ENTRP code as activity 1.
The implementation of a change of organization above “Act1” requires the following steps :
Finance Data fixes a date for implementing the change, together with the GBU Controller and the Service Center manager (usually at the end of the year)
At the given date, Finance Data implements the change in the tables and the profit center hierarchies.
For new entries/codes, COPA characteristics are automatically updated.
Check in transaction KES2 if the new/updated elements are already available.
If not, open a Freshdesk ticket to IS, asking to update it accordingly: