1. OBJECTIVE AND SCOPE


1.1. Objective of this Procedure

This document describes the full procedure related to contract and PIR maintenance in SAP WP1 system. It’s a revised version from previous working instructions (Work Instruction - PUR - SAP - 02 & PIR Maintenance)

Requests can be performed by buyers and planners from each plant.

All requests are sent to Data Operations team via FreshDesk 


1.2. Scope

Under Riga SBS Data Operations’ scope is the management of Contracts and PIRs for all plants

1.3. Abbreviations


Abbr.

Description

SBS

Solvay Business Services

HSE

Health, Safety and Environment

DG

Dangerous goods

MRP

Material Resource Planning

UoM

Units of Measure

PIR

Purchasing Info Record

STO

Stock Transfer Order


1.4. Roles and responsibilities

Prior to submitting a new Contract/PIR request, it is the requester’s responsibility to ensure the contract/PIR does not exist in SAP already, so no duplicates are created in the system. If the contract/PIR was not found, a request should be submitted to Data Operations for its set up in SAP. A second search in the system is performed by the Data Operations team to ensure no duplicates are created.


2. STANDARD OPERATING PROCEDURE DESCRIPTION


Purchase Info Record (PIR) is a method of managing the purchase price. An alternate management method is a contract. When a contract exists, then the PIR should not be used for the same material. A new PIR is created when a purchase from a new material/supplier combination is needed. Within the PIR there is another unique combination named Purchasing Org. Data, formed by the combination of the Purchasing Org., Info Category and Plant Code. If one of those elements is changed, this results in a new record within the PIR. In the PIR’s General View the global fields are available. These fields determine the information common to all plants using the material/supplier combination. The PIR’s maintenance is the responsibility of the Buyer. Any information missing in the ZERS form (approved by the Buyer) and necessary in the PIR should be completed by them.

2.1. Creation of PIR (Purchase Info Record) in WP1

PIRs are created when we have STO,  consignment PO or a subcontracting contract.

We have 4 types of PIR: 


2.1.1 requirements for new PIR

In order to create new PIR we will need the following information:

2.1.2 Creating PIR

#

Main activities

Tips / Best practices

Key points

1

Enter transaction ME11

T-code can be entered directly in Command field. T-code can be saved in Favorites.


2

Vendor 


Information provided in the request

3

Material


As informed

4

Purchasing Organization

Information may change depending on the plant region/type of order

if not informed, you can find here.

5

Plant 


Information provided in the request

6

PIR category


If not informed choose Standard

7

Press enter




#

Main activities

Tips / Best practices

Key points

8

Enter Vendor Material Number


Optional info

9

Enter Salesperson


Optional info

10

Enter Telephone


Optional info

11

Enter Order Unit


Change if requested

12

Go to Purchasing Organization Data 1 view

Pressing Enter will move you to Purch. Org. Data 1

 

#

Main activities

Tips / Best practices

Key points

13

Enter Planned Delivery Time

Pre-populated - pulled from Material master data

Use 5 as default value in cases when Planned Delivery Time is not indicated by requestor

14

Enter Standard Quantity

 

Always 1 if no special requests

15

Enter Tax Code

Check location of plant and Vendor


Plant Country

Local Tax

Import Tax

Australia

C”

D”

Brazil

GO* May have more than one option

GO

Canada

LY

AS

Chile

LR

LQ

China

LC

JP

EU

TT

DE

Korea

IE


Mexico

NK

NF

Netherlands

TT

TS

Peru

MM

ML

USA

LN

AS


16

Enter Net Price


As requested 

17

Incoterms 1 and 2


Add if requested, otherwise keep it blank

18

Confirmation Control Key (CCK)

Check Incoterms

If Incoterms are COL - always Z003, (exception if going from Kemira to Kemira’s plant 8543 then blank). 

For Brazil Plants, CCK is always Z016

19

Go to Conditions view

 

 


 

#

Main activities

Tips / Best practices

Key points

20

Update the validity period

 

The validity period is to be extended to the end of the current year

21

Click on (save)

 

 

 


2.1.2.1 Adding Scale

When in conditions we are able to add Scales related to the price of the material. 

Some items we can have discounts when we buy in a higher quantity.

#

Main activities

Tips / Best practices

Key points

22

Select the price line

 


23

Click on Scale

 

 

#

Main activities

Tips / Best practices

Key points

24

Add the scale quantity

 


25

Add price for new quantity

 

 

26

Save it




2.1.2.2 STO PIRs

When creating a STO (Stock Transfer) PIR, we need to delete the condition in order to the correct price reflect for the item. NOTE: ALL STO PIRs ARE CREATED FOR PURCHASING ORGANIZATION 3200, NO NEED TO UPDATE THE “VALID TO” IN THIS CASE.

After saving the new PIR, go back to the conditions and follow the procedure below:

#

Main activities

Tips / Best practices

Key points

27

Select Price line



28

Delete


Confirm deletion

29

Save it


As informed


2.1.3. Change PIR

#

Main activities

Tips / Best practices

Key points

30

Enter transaction ME1M

T-code can be entered directly in Command field. T-code can be saved in Favorites.


31

Vendor 


If informed, otherwise keep it blank

32

Material


As informed

33

Purchasing Organization


If informed, otherwise keep it blank

34

Plant 


If informed, otherwise keep it blank

35

Click on

 




#

Main activities

Tips / Best practices

Key points

36

Select PIR

 

 

37

Press Change Info Record

 

 



#

Main activities

Tips / Best practices

Key points

38

Go to Conditions




#

Main activities

Tips / Best practices

Key points

39

Single click on the valid period



40

New with reference




#

Main activities

Tips / Best practices

Key points

41

Validity From


As informed, other wise current date

42

Valid to


if not informed, end of current year

43

Amount


As informed

44

Per


As informed

45

Price Unit of measure


As informed

46

Save it





2.1.4. Delete PIR

#

Main activities

Tips / Best practices

Key points

47

Enter transaction ME12 or ME1M as on Change

T-code can be entered directly in Command field. T-code can be saved in Favorites.


48

Vendor 


Information provided in the request

49

Material


As informed

50

Purchasing Organization


As informed

51

Plant 


As informed

52

PIR category


If not informed choose Standard

53

Press enter




#

Main activities

Tips / Best practices

Key points

54

Purchasing Group


E00

55

Extras > Deletion Flags

Shift + F12



#

Main activities

Tips / Best practices

Key points

56

Complete info record


Flag if Full PIR should be deleted

57

Purch. Org. Data


Flag if only plant/p. Org data should be deleted.

58

Go to Conditions




#

Main activities

Tips / Best practices

Key points

59

Double click on the valid period




#

Main activities

Tips / Best practices

Key points

60

Validity To


Date in the past

61

Save it




2.2. Source List

A source list is needed every time a new contract is created, a new line is added in an existing contract or when a PIR is created.

2.2.1. Creating Source List


#

Main activities

Tips / Best practices

Key points

62

Enter transaction ME01

T-code can be entered directly in Command field. T-code can be saved in Favorites.


63

Material


As informed

64

Plant


As informed

65

Press enter





#

Main activities

Tips / Best practices

Key points

66

Click on generate records




#

Main activities

Tips / Best practices

Key points

67

Press enter or click on confirm




#

Main activities

Tips / Best practices

Key points

68

Select “Not changed”



69

Press enter or click on confirm





#

Main activities

Tips / Best practices

Key points

70

Save it




2.3 Creation of contract

2.3.1 Prerequisites

A contract is created in WP1 when some special negotiation was made with the vendor, for example, some specific material is paid with better terms than it is already set up on Vendor Master Data. 

NOTE: THIS IS NOT A STANDARD PROCESS AND SHOULD BE PERFORMED ONLY WHEN NO OTHER OPTION IS AVAILABLE.

2.3.2 Checking for duplicates

 

#

Main activities

Tips / Best practices

Key points

71

Enter transaction ME33K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


72

Press multiple choice button to receive pop-up window with search options for material master

you can also press F4


#

Main activities

Tips / Best practices

Key points

73

Select Purchasing Documents per vendor

T-code can be entered directly in Command field. T-code can be saved in Favorites.


74

Add vendor


Information provided in the request

75

Purchasing Document Category


Always K

76

Press enter

If no values return, you can proceed with the creation



#

Main activities

Tips / Best practices

Key points

77

Enter on contracts that shows up

We have one contract by plant. In case it’s not the plant requested, proceed with contract creation, otherwise add item to the existing contract.



2.3.3 Creating a contract

#

Main activities

Tips / Best practices

Key points

78

Enter transaction ME31K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


79

Vendor 


Information provided in the request

80

Agreement type


MK - Quantity contract

WK - Value Contract

81

Purchasing Organization


Always CP01

82

Purchasing Group


Plant buyer code

83

Plant 


Information provided in the request

84

Press enter





#

Main activities

Tips / Best practices

Key points

85

Validity end


As requested

86

Target Value 


Optional info

87


NOTE: In the header you can also set up some different information other than the one in vendor master data, such as different payment term, incoterms, etc. (this information will be the one selected when PO is created)


88

Press Item Overview




#

Main activities

Tips / Best practices

Key points

89

Material 


As informed

90

Target Quantity


Mandatory for MK contracts

91

Order Unit

If not populated, it will get from Material Master


92

Net Price

NOTE: Price can only be added with 2 decimal characters, in case price informed is as example $1.012 USD/EA > net price would be $10.12 and per will be 10

As informed

93

Per


As informed

94

Order Unit Price


As informed

95

Save it

After the contract  is created, source list  should be created


 

2.3.4 Adding new item in an existing contract

#

Main activities

Tips / Best practices

Key points

96

Go to transaction ME32K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


97

Add contract number



#

Main activities

Tips / Best practices

Key points

98

Material number

Find the first blank line
Follow the same procedure as step XX to XX

Add information as requested

99

Save it




2.3.5 Changing items in an existing contract

#

Main activities

Tips / Best practices

Key points

100

Go to transaction ME32K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


101

Add contract number



102

Press enter




#

Main activities

Tips / Best practices

Key points

103

Select line that needs to be changed

T-code can be entered directly in Command field. T-code can be saved in Favorites.


104

Click on conditions




#

Main activities

Tips / Best practices

Key points

105

Single click on the valid period



106

New with reference




#

Main activities

Tips / Best practices

Key points

107

Amount


Information provided

108

Save it

Note: Additional information can be changed also (texts)



2.3.6 Changing Target value in an existing contract



#

Main activities

Tips / Best practices

Key points

109

Go to transaction ME32K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


110

Add contract number



111

Select Header Details




#

Main activities

Tips / Best practices

Key points

112

Change to Target value to the information provided



113

Save it




2.3.7 Deleting item in an existing contract

#

Main activities

Tips / Best practices

Key points

114

Go to transaction ME32K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


115

Add contract number



116

Press enter




#

Main activities

Tips / Best practices

Key points

117

Select Line(s) you want to delete



118

click on “Delete



119

Save it



#

Main activities

Tips / Best practices

Key points

120

After deleting all lines go to header



121

Change Validity end to the past



122

Save it





ATTACHMENTS


ATTACHMENT 1. Approved Requesters

Approvers and requesters are Buyers and Planners.

The full list can be found here.

ATTACHMENT 2. Additional Definitions

CONSIGNMENT 

A form of business in which a vendor (external supplier) maintains a stock of materials at a customer (purchaser) site. The vendor retains ownership of the materials until they are withdrawn from the consignment stores. Payment for consignment stock is required only when the material is withdrawn for use. For this reason, the vendor is informed of withdrawals of consignment stock on a regular basis.

SUBCONTRACTING

An instruction to a supplier (subcontractor) to manufacture an ordered part, material or assembly using specified "materials to be provided" (free-issue materials).  A subcontract order contains a maximum of one order item for the ordered material, service, or work, and one or more "material to be provided" items for materials that the orderer makes available to the subcontractor, without charge, for processing.

ATTACHMENT 3. Q&A


In this link we have a Q&A where we can find the most common questions and answers regarding this activity.





ATTACHMENT 4. Purchasing Organizations


Domain

Europe

North America

Latin America

APAC

1 - General Expenses

3001

3009

3017

3025

2 - Packaging

3002

3010

3018

3026

3 - Energy

3003

3011

3019

3027

4 - Industrial Supplies

3004

3012

3020

3028

5 - IT & Telecom

3001

3009

3017

3025

6 - Raw Materials

3006

3014

3022

3030

7 - Industrial Services

3007

3015

3023

3031

8 - Transport/Logistics

3008

3016

3024

3032

9 - Inter-Company

3200

10 - Third Party

3100

3101

3102

3103