1 OBJECTIVE AND SCOPE

1.1. Objective of this Procedure

This document's objective is to provide a guide to managing Material master data ZVER and ZUNB materials.


This document is a complement to Standard Operating Procedure "Article Creation and Management", adapting the process to ZVER and ZUNB Material master data management for GBU Technology Solutions (Legacy Cytec organization).


Material Master Data management process includes creation and modification of the packaging material as well as its inactivation and flagging for deletion. Creation of Basic Data, Sales, Purchasing and General plant data will be presented in this procedure. Finance and planning teams should be informed after packaging code creation and/or extension.


Requests of Material Master creation or maintenance can be performed by approved requestors listed in Appendix 2 - List of contacts.

For Composite Materials, the request will be sent via Sharepoints, in this case no additional approval is required.


All requests are sent to Master Data via Freshdesk or alternatively by e-mail. Common e-mail address of Riga SBS Data Management team: datamanage@solvay.com


Request form for packaging should usually be provided by requester. Link to the form can be found in Google Documents Template for RM and Packaging

For Composite Materials, there is a template which is combined with ZMAT materials and will be provided in the Sharepoints/Freshdesk request.


The referral lists mentioned in this procedure, such as Purchasing Groups and Profit Center List are embedded in the TS SAP Material request form file

1.2. Scope

Under Riga SBS Data Management's scope is the management of ZPRC, ZMAT, ZVER and ZUNB materials for GBU Technology Solutions and Composite Materials (legacy Cytec) sites in WP1 SAP system. Management of ZERS and ZMAT materials is described in separate procedure. Riga SBS Data Management can create and extend ZDIE materials if requested so by Finance.

Material Type

Description

Division

ZMAT

Finished Goods
Semi-finished Goods
Raw Materials

Multiple
Multiple
KV

ZPRC

Commercial Products

N/A

ZVER

Packaging

WD

ZUNB

Stocked and non-valuated materials

WD (for packaging)

ZDIE

Services

Multiple

1.3. Abbreviations

Abbr.

Description

Abbr.

Description

RCS

Rhodia Core System

SBS

Solvay Business Services

ZMAT

Finished product, semi-finished product, raw material

HSE

Health, Safety and Environment

ZVER

Packaging

DG

Dangerous goods

ZUNB

Stocked and not valuated material

MRP

Material Resource Planning

ZDIE

Service

UoM

Unit of Measure

ZPRC

Commercial Product

 

 


1.4. Roles and responsibilities

ZVER setup can be performed only once MOC-ID code is available.
Prior to submitting a new ZVER/ZUNB request, it is the requester´s responsibility to ensure the material does not exist in SAP already, so no duplicates are created in the system. If the material was not found, the TS SAP Material request form must be filled and submitted to Data Management for material master setup in SAP. A second search in the system is performed by the Data Management team to ensure no duplicates are created.

2 STANDARD OPERATING PROCEDURE DESCRIPTION

2.1. Creation of ZVER material in RCS

2.1.1. Pre-requisites - Technology Solutions

ZVER setup can be performed only once MOC-ID available.
In all cases when MOC-ID is missing Lindsay Schramm and HazCom team should be contacted to clarify whether ZVER code can be set up without this information.
Prior to material creation in the system search is performed by the Data Management team to ensure no duplicates are created.

2.1.1.1. Accessing MOC Gensuite Portal

ZPRC and PRCO can be found validating MOC in Gensuite Portal.


User: data.manage@solvay.com
Password: Solvay123
Once you access the MOC Portal, please:

In this step:




Important documents and information to be observed in the MOC


Screening Questions




Completed Packaging request form should be attached for all ZVER codes. ZVER description must follow
Packaging rules table which can be found here - Packaging Instructions

2.1.1.2 Checking for duplicates

#

Main activities

Tips / Best practices

Key points

1

Enter transaction MM03

T-code can be entered directly in Command field. T-code can be saved in Favorites.

Full path: Logistics -> Materials Management -> Material master -> Material -> Display

#

Main activities

Tips / Best practices

Key points

2

Press multiple choice button to receive pop-up window with search options for material master

 

 

#

Main activities

Tips / Best practices

Key points

3

Click on to open the menu

 

 

4

Select the option 'Material Number/Material Description'

Field 'Old material number' can be used to look up material by BPCS Code (temporarily).

 


#

Main activities

Tips / Best practices

Key points

5

Run a search in Material Description

Use Wildcards to best describe

Open the material request form, copy the short text from the requested material and run a search in Material description with wildcards.

6

Hit Enter

 

 

#

Main activities

Tips / Best practices

Key points

7

Verify entries found – compare results with the material's "short description" mentioned in the request form. If you have doubts about the material already created, contact the Requester to clarify.

 

If result points to or if the Requester mentions a new article need to be created then proceed with the creation.


2.1.2. Creation of material

#

Main activities

Tips / Best practices

Key points

8

Enter transaction MM01

T-code can be entered directly in Command field. T-code can be saved in Favorites.

Full path: Logistics -> Materials Management -> Material master -> Material -> Create (General)


#

Main activities

Tips / Best practices

Key points

9

Enter Industry Sector

 

Always choose "Chemical Industry"

10

Enter Material Type

 

Always ZVER for packaging

11

Copy from… Material

Option to copy data from an existing material can be useful in some cases.

 

12

Hit Enter

 

 



#

Main activities

Tips / Best practices

Key points

13

Select Views to be created

Creation of views can be performed all at once or in separate steps

Select Basic Data 1 & 2, Sales: General /Plant Data, Purchasing, General plant Data / Storage 1, General plant Data / Storage 2

List of single Storage locations can be found in Appendix 3

Sales Organization and Distribution Channel should not be filled by creation.

NOTE! Warehouse Management 1 & 2 Views to be created and warehouse number added (in brackets) for warehouse managed plants only:
8520 (077), 8521 (054), 8522 (076), 8712 (C26), 8636 (K19) – by default.
For 8359 - only if requested.

14

Hit Enter

Use Default Setting button to save your selections for future creations

 


#

Main activities

Tips / Best practices

Key points

15

Fill in Organizational Levels

Fill Plant as indicated in request form and add Storage Location. Appendix 3.

Note: Sales Organization and Distribution Channel should not be filled.

Storage location should be added for plants when only one option is available
For Composite Check Appendix 5 and open the material for all storage locations correspondent to each plant.

16

Hit Enter

 

 



#

Main activities

Tips / Best practices

Key points

17

Enter Packaging Description

Check the request form for "SHORT DESCRIPTION"

Technology Solutions: Should be checked whether description meets Packaging instructions. [Packaging name + dimensions + capacity + specific characteristics (if exists)]
Composite Materials: Copy from the template.

18

Enter Base Unit of Measure

 

Technology Solutions: Always PC

Composite Materials:

19

Enter Material Group


Technology Solutions: Should be checked by type of packaging in Packaging Instructions table.

Composite Materials: Check the request form

20

Enter Division

 

Always WD

21

Enter General Item Category Group

 

Always VERP

22

Enter UoM for Weight

 

Always KG

*Gross WeightFor Composite Materials and pallets onlyCheck the request form
*Net WeightFor Composite Materials and pallets onlyCheck the request form
*Enter Ref. mat. for pckgFor Composite only!Enter default number 1911973

23

Go to Descriptions tab

From Basic Data View Descriptions tab can be accessed by pressing Additional Data button in the top part of screen as well. Tabs in Additional Data can be filled in any sequence.

 



#

Main activities

Tips / Best practices

Key points

27

Enter material descriptions in local languages

Request for should be checked for descriptions in other languages e.g.

ZH – Chinese might be indicated in original language.

12 mandatory languages are:
EN – English
Z9 – Brazilian Portuguese
ZH – Chinese
KO – Korean
DE – German
FR – French
IT – Italian
JA – Japanese
PL – Polish
PT – Portuguese
ES – Spanish
NL – Dutch

28

Return to Main Data

 

 

For Composite only


#

Main activities

Tips / Best practices

Key points

a.

Enter Alternative units of measure


Default conversion should be added for all packaging materials 1EA = 1PC

Copy from the template if nay additional conversion informed.

b.

Go to Basic data text

 

 



#

Main activities

Tips / Best practices

Key points

c.

For Composite - material long description (copy from the form)

Use  button to add languages
Copy English text to all other languages:

12 mandatory languages are:
1 – Chinese (EN!)
E – English
F – French
D – German
I – Italian
J – Japanese
3 – Korean
L – Polish
P – Portuguese
S – Spanish
& – Brazilian Portuguese
N – Dutch

d.

Return to Main Data

 

 


#

Main activities

Tips / Best practices

Key points

29

Go to Basic data 2 view

 

 

30

Enter Basic material

Generic ZPRC number for all ZVER materials

Always 90029754

31

Go to Sales: general/plant view

 

 


#

Main activities

Tips / Best practices

Key points

35

Enter Availability check

 

Technology Solutions: Always 02

Composite Materials: Always KP

36

Enter Transportation Group

 

Always 0001

37

Enter Loading Group

 

Always 0001

***

Packaging Mat type

Entered only for Pallets

0001

38

Enter Profit Center

 

Technology Solutions: List of profit centers can be found in following link.

Composites Materials: Check the request form

39

Go to Purchasing view

 

 


#

Main activities

Tips / Best practices

Key points

40

Enter Purchasing Group

 

Technology Solutions: List of purchasing groups can be found in following ZVER Purchasing Groups

Composite Materials: Check the request form

41

Enter Plant-specific material status

Once Finance creates Accounting and Costing Views and performs material costing run, the status will be removed by Finance to allow use of material in operations.

Status Z1 is to be used at the time of material creation.

42

Activate automatic Purchase Order indicator

 

Always checked

43

Enter Purchasing value key

 

Always 0001

44

Enter GR processing time

Plant data administrators will change the field value if necessary

Default value at the time of material creation – 2

45

Go to next view

Plant data / storage 1 view

 


#

Main activities

Tips / Best practices

Key points

46

Enter Physical inventory indicator for cycle counting

Plant data administrators will change the field value if necessary

Technology Solutions: Default value at the time of material creation – B

Composite Materials: Check the request form

47

Go to Plant data / storage 2 view

Nothing should be entered as Profit center data are being copied from Sales: general/plant view

 

48

Save material

 


NOTE! Technology Solutions: After material code is created Finance and Planning teams from appropriate plant should be informed to create missing views, contacts can be found in TS MM Support Organization file.

2.1.3. Extension of material

Following MOC procedure plants are obligated to review existing MOC process every two to three years, therefore valid MOC ID is mandatory component for Packaging extension, this information should be provided by requester any time material should be created for a new plant.


Lindsay Schramm should be contacted in case of missing MOC-ID.


NOTE: Raw Materials and Packaging should not be extended to Trading plants (8572 – MX, 8573 – CL, 8571 – PE, 8580 – NL, 7788 – ID, 7786 – AU, 8574 - CN).


To extend material enter transaction MM01. Copy from… option can be used, preferably to copy from an existing view of the same material.



To extend ZVER material to a Plant, select Sales: General/Plant Data, Purchasing, General Plant Data/Storage 1 & 2.


2.1.4. Extension of Composite Materials to Sales Organization view

If provided in the form, extended the composite materials for sales organization as per image below:


#

Main activities

Tips / Best practices

Key points

1

Enter Cross-distribution-chain specific material status

 

Status 63 is to be set at the moment of material creation to allow use of material in operations

2

Enter Valid from date for Cross-distribution-chain specific material status

DD.MM.YYYY

 

3

Maintain Tax classifications

System will automatically determine which Countries' tax lines should be added

Always 1 for all countries unless otherwise indicated by Finance or Tax department

4Go to Sales: sales org. 2 view



#

Main activities

Tips / Best practices

Key points

5

Enter Material statistics group

 

Always 1

6

Enter Account assignment group


Check the request form, if not provided populate with F

7

Enter Item category group


Always VERP

8Save the extension



2.2. Creation of ZBOM material in RCS

Requester should provide us with correct Description and Plant where material should be created. 

#

Main activities

Tips / Best practices

Key points

1

Enter transaction MM01

T-code can be entered directly in Command field. T-code can be saved in Favorites.

Full path: Logistics -> Materials Management -> Material master -> Material -> Create (General)

#

Main activities

Tips / Best practices

Key points

2

Enter Industry Sector

 

Always choose “Chemical Industry”

3

Enter Material Type

 

Always ZBOM for Phantom assemblies

4

Copy from… Material

Option to copy data from an existing material can be useful in some cases.

 

5

Hit Enter

 

 


#

Main activities

Tips / Best practices

Key points

6

Select Views to be created

Creation of views can be performed all at once or in separate steps

Select Basic Data 1, Basic Data 2, MRP 1, MRP 2, MRP 3, MRP 4,

Sales Organization and Distribution Channel should not be filled.

7

Hit Enter

Use Default Setting button to save your selections for future creations

 

#

Main activities

Tips / Best practices

Key points

8

Fill in Organizational Levels

Fill Plant as indicated in request. 

Sales Organization and Distribution Channel  should not be filled.

Storage location should be added for plants when only one option is available

9

Hit Enter

 

 

#

Main activities

Tips / Best practices

Key points

10

Enter Phantom Description


Check the request

11

Enter Base Unit of Measure

 

Always EA

12

Enter Material Group


Always 0450

13

Enter Division

 

Always WD

14Enter Gross Weight
Always 1
15Enter Net Weight
Always 1

16

Enter UoM for Weight

 

Always KG

17

Go to Descriptions tab

From Basic Data View Descriptions tab can be accessed by pressing Additional Data button in the top part of screen as well. Tabs in Additional Data can be filled in any sequence.

 

#

Main activities

Tips / Best practices

Key points

18

Enter material descriptions in local languages

 

Request for should be checked for descriptions in other languages

e.g. ZH – Chinese might be indicated in original language.

12 mandatory languages are:

EN – English

Z9 – Brazilian Portuguese

ZH – Chinese

KO – Korean

DE – German

FR – French

IT – Italian

JA – Japanese

PL – Polish

PT – Portuguese

ES – Spanish

NL – Dutch

19

Go to Basic data text tab

 

 

#

Main activities

Tips / Best practices

Key points

20

Enter Basic data text – same as material description.

Use  button to add languages

Copy English text to all other languages:

 


12 mandatory languages are:

1 – Chinese (EN!)

E – English

F – French

D – German

I – Italian

J – Japanese

3 – Korean

L – Polish

P – Portuguese

S – Spanish

& – Brazilian Portuguese

N – Dutch

21

Return to Main Data


 

22Go to Basic Data 2 viewNo data has to be maintained in Basic Data 2, however the view has to be created
23Go to MRP1 view



#

Main activities

Tips / Best practices

Key points

24

Enter MRP Type

 

Default value – PD

25

Enter MRP Controller

 

Default value – P05

26Enter Lot Size
Default value – EX

27

Go to MRP 2 view

 

 

#

Main activities

Tips / Best practices

Key points

28

Enter Special procurement

 

Default value – 50

29

Enter Backflush

 

Default value – 2

30

Go to MRP 3 view

 

 

#

Main activities

Tips / Best practices

Key points

31

Enter Period Indicator

 

Default value – M

32Enter Availability Check
Default value – KP

33

Go to MRP 4 view

 

 

#

Main activities

Tips / Best practices

Key points

34

Enter Individual/coll.

 

Default value – 2

35

When all data has been entered, save the material by pressing  button and exit material creation

 

 

2.3. Material modification

2.3.1. Pre-requisites

Material modification is allowed only if validated by all Plants using the material.


Requests to change Base unit of Measure must not be performed – in this case a new material has to be created.


Another exception can be a mistake for recently created material that has not yet had any stock and stock movements in the system.


#

Main activities

Tips / Best practices

Key points

1

Enter transaction MM03

T-code can be entered directly in Command field. T-code can be saved in Favorites.

Full path: Logistics -> Materials Management -> Material master -> Material -> Display


#

Main activities

Tips / Best practices

Key points

2

Enter Material number

 

 

3

Select Purchasing (or Sales: General/Plant Data) view

 

 


#

Main activities

Tips / Best practices

Key points

4

Verify the possible Plants related to the Material by clicking on the match code.

 

 

5

All Plants using the material are listed

 

 


If material is open for more than one Plant, contact the other Plants to validate the requested modification.


If the answer is positive, change the material as shown in section 2.2.2. Manual modification of material.


If the answer is negative, create a new material as described in Chapter 2.1.2. of this OP, associated with the Plant that made the request.

2.3.2. Manual modification of material

#

Main activities

Tips / Best practices

Key points

1

Enter transaction MM02

T-code can be entered directly in Command field. T-code can be saved in Favorites.

Full path: Logistics -> Materials Management -> Material master -> Material -> Change

2

Select the view containing the field that needs modification

 

 

3

Select the Organizational Level for which the modification is requested

Repeat the modification for all Sales Areas or Plants if applicable.

 

4

Save the changes performed

 

 


Appendix 1 – List of contacts

Requests for Packaging requests can be accepted from Purchasing representative.
Detailed Technology Solutions Support Organization file by plants can be found in following link.

 Region

Representative

Email

US and Canada

 

 

 

 

Vanessa Scott

vanessa.scott@solvay.com

Leslie Fleming

leslie.fleming@solvay.com

Lori Collins

lori.collins@solvay.com

Thierry Leclerc

thierry.leclerc@solvay.com

Mario Bruins

mario.bruins@solvay.com

LAM

 

Yarian Cuenca

yarian.cuenca@solvay.com

Abril Gomez

abril.gomez@solvay.com

APAC

 

 

 

 

Natpapan Chueakongtrakul (Poon)

natpapan.chueakongtrakul@solvay.com

Celine Koh

celine.koh@solvay.com

Catherine Lu

catherine.lu@solvay.com

Sorrawit Parknondhkul

sorrawit.parknondhkul@solvay.com

Nathan Purvis

nathan.purvis@solvay.com

EMEA

Thierry Leclerc

thierry.leclerc@solvay.com

ZPRC/MOC

HazCom

hazcom.rawmat@solvay.com

MOC-ID

Lindsay Schramm

Lindsay.schramm@solvay.com

Appendix 2 – List of Plants in non-GTS countries


Whenever a material is extended to any of non-GTS plants, extension has to be added in a file to notify the responsible team. Location of the file.

Country

Plant Code

Description

Japan

8524

7418 / Gas Chem Logistic Osaka

Singapore

8506

6062 / Poh Tiong Choon Jurong


Appendix 3 – List of Single Storage Locations

Storage Location

Description

8380

7786 / JF Hillebrand Fremantle

8433

7788 / Jakarta

8496

7722 / BDP Peru Arequipa

8500

7725 / Andimex San Antonio

8503

7988 / Daesung Whse Yangsan

8505

7723 / FH Logist Azcapotzalco

8506

6062 / Poh Tiong Choon Jurong

8507

7725 / Sercabol Antofagasta

8508

7776 / Sinotrans Intl Shanghai

8509

7734 / KWE Logistics Shanghai

8511

7794 / CML Ltd Walvis Bay

8515

7786 / Toll Contr Laverton Nth

8519

7786 / NSS Port Sth Townsville

8520

7008 / XPO Logistic Bristol

8521

7008 / XPO Logistic La Porte

8522

7008 / XPO Logistic Plainfield

8525

7523 / NATAM Express Maua

8527

7794 / Schenker Kempton Park

8528

7734 / Sinotrans Intl Shanghai

8543

7008 / KEMIRA WATER MOBILE

8545

7008 / FLUID ENERGY HATFIELD

8548

7008 / MOBILE SOLVENT EIGHT MILE

8549

7752 / NOVA MOLECULAR PASADENA

8553

7008 / SOUTH COAST HOUSTON

8554

7008 / SPRAY TEK MIDDLESEX

8559

7008 / TOLL COMPACTION NEPTUNE

8589

7734 / Tianjin DLD Beicheng Wh

8605

7794 / Kemira Chem Bradford

8614

7734 / COSCO Logistic Tianjin

8617

7776 / COSCHEM Logist Shanghai

8618

7794 / Praxair Oevel-Westerlo

Appendix 4 – Sinequa

Link to Sinequa Portal

Appendix 5 – Storage location for Composite Materials


ROLLOUTSOLSTICE PLANTPLANT DESCRIPTIONSLOCSLOC DESCRIPTION

R1

            8367 - 7180 Piedmont          CENTMain Warehouse
GP1AGP1 Area
GP2AGP2 Area
GP3AGP3 Area
PRIFPriform
PTCHPitch
RWRKRework Warehouse
SPINSpinning
STRMStore Room
TANKTanks
RHWFRH White Fiber
TWSTTwisting

8785

7180 Rock Hill

PRODProd. Warehouse
RETNReturns
RWRKRework
STRMStore Room

8350

7771 Wrexham

ADFLADH Plant Film
ADLLADH Laminator
ADRDADH Roll Doctor
ADRMADH Resin Room
ADSLADH Slitter
ADWIAdh WIP
CENTMain Warehouse
CUSTSend to customer
MABCMain Braid Coat
MSKRMain Kroenert
MSLAMain Laminator
MSRBMain Re-Batcher
MSRMMain Resin
MSSLMain Slitter
MST1Main Tape 1
MST3Main Tape 3
MST4Main Tape 4
MSWIMain WIP
MTO1Tower 1
MTO2Tower 2
PROSProserve
RWRKRework
STR1Store Room Main
STR2Store Room Adhe
TNKATanks - Adhesive
TNKMTanks - Main

8822

7180 / Palmetto Greenville SC

8822Palmetto
RHWFRH White Fiber
88027771 / K&N Non-Bonded ReadingKNNBK&N WH non bond
87967771 / K&N Bonded ReadingKNBOK&N WH - Bonded

Appendix 6 – Data Governance List for Composite Materials 


Wrexham:
Stuart Tudor Jones - backup Dave Harvey

CCF:
Harrison Blackwelder - backup Mike Zitricki


Texas:
Hope Helton - backup Brianna Hammond

Anaheim:
Lisa McGee - backup Rehan Surhwardy

Orange:
Corinne Nelson - backup Ryan Walker

D'Air:
Bruce Gormley

Kalamazoo:
TBD


Appendix 7 – List of plants for Composite Materials  

Plant Name of Plant in SAPCompany CodeSales OrganizationCountry
83418341 - 7180 / Tempe7180US32 - Composite MaterialsUSA
83478347 - 7772 Oestringen7772DE13 - Composites MaterialsGermany

8350

8350 - 7771 Wrexham7771GB40 - Composites MaterialsUnited Kingdom
83618361 - 7180 Orange7180US32 - Composite MaterialsUSA
83638363 - 7180 Anaheim D'Aircraft7180US32 - Composite MaterialsUSA
83648364 - 7180 Anaheim7180US32 - Composite MaterialsUSA
83658365 - 7180 Greenville7180US32 - Composite MaterialsUSA
83678367 - 7180 Piedmont7180US32 - Composite MaterialsUSA
83688368 - 7180 Havre de Grace7180US32 - Composite MaterialsUSA
83708370 - 7180 Winona7180US32 - Composite MaterialsUSA
83748374 - 7180 / Bellevue7180US32 - Composite MaterialsUSA
83938393 - 7771 / Wilton7771GB40 - Composites MaterialsUnited Kingdom
84568456 - 7180 Kalamazoo7180US32 - Composite MaterialsUSA
84668466 - 7188 / Tempe CDM7188US32 - Composite MaterialsUSA
85868586 - 7776 / Shanghai7776Tech Solutions (CEM)China
86098609 - 7180 / Alpharetta7180US32 - Composite MaterialsUSA
86268626 - 7180 / Saddle Brook7180US32 - Composite MaterialsUSA
86288628 - 7776 Fengxian7776Composites Mats 7776China
87858785 - 7180 Rock Hill7180US32 - Composite MaterialsUSA

8786

8786 - 7180 / Princeton7180US32 - Composite MaterialsUSA
87938793 - 7180 / ATSCOTT MFG Pine City7180US32 - Composite MaterialsUSA
87948794 - 7180 / MCC Huntington Beach7180US32 - Composite MaterialsUSA
87958795 - 7180 / ET Horn La Mirada7180US32 - Composite MaterialsUSA
87968796 - 7771 / K&N Bonded Reading7771GB40 - Composites MaterialsUnited Kingdom
88028802 - 7771 / K&N Non-Bonded Reading7771GB40 - Composites MaterialsUnited Kingdom
88158815 - 7180 / Taichung City7180US32 - Composite MaterialsUSA
88178817 - 7180 / Hale Baltimore7180US32 - Composite MaterialsUSA
88188818 - 7180 / First Choice Vineland7180US32 - Composite MaterialsUSA
88198819 - 7180 / XPO Logistics Levittown7180US32 - Composite MaterialsUSA
88208820 - 7180 / Lonestar Richardson7180US32 - Composite MaterialsUSA
88218821 - 7180 / Delta Greenville TX7180US32 - Composite MaterialsUSA
88228822 - 7180 / Palmetto Greenville SC7180US32 - Composite MaterialsUSA
88238823 - 7180 / Seven Rivers Winona7180US32 - Composite MaterialsUSA
88248824 - 7180 / Rinchem Eagan7180US32 - Composite MaterialsUSA
88258825 - 7180 / KPAC Wilmington7180US32 - Composite MaterialsUSA
88268826 - 7180 / Lewis Howard Kalamazoo7180US32 - Composite MaterialsUSA
88348834 - 7180 / Jensen-Souders Itasca7180US32 - Composite MaterialsUSA
88458845 - 7180 / eShipping Ontario7180US32 - Composite MaterialsUSA