1 OBJECTIVE AND SCOPE


1.1 Objective of this Procedure

This document describes the full procedure related to contract and PIR maintenance in SAP WP1 system. It’s a revised version from previous working instructions (Work Instruction - PUR - SAP - 02 & PIR Maintenance).
For Technology Solutions, requests can be performed by buyers and planners from each plant and for Composite Materials PIRs, Source Lists and Contracts can be modified and created by site Buyers (Strategic RM buyers. Planners can not (and should not) make changes themselves, but turn to buyers or us for that. 
All requests are sent to Data Operations team via FreshDesk 


1.2 Scope

Under Riga SBS Data Operations scope is the management of Contracts, PIRs and Source Lists for all Technology Solutions and Composite plants.

1.3 Abbreviations


Abbr.

Description

SBS

Solvay Business Services

HSE

Health, Safety and Environment

DG

Dangerous goods

MRP

Material Resource Planning

UoM

Units of Measure

PIR

Purchasing Info Record

STO

Stock Transfer Order

SLSource lists


1.4 Roles and responsibilities

Prior to submitting a new Contract/PIR/SL request, it is the requester’s responsibility to ensure the contract/PIR/SL does not exist in SAP already, so no duplicates are created in the system. If the contract/PIR/SL was not found, a request should be submitted to Data Operations for its set up in SAP. A second search in the system is performed by the Data Operations team to ensure no duplicates are created.


2 STANDARD OPERATING PROCEDURE DESCRIPTION


Purchase Info Record (PIR) is a method of managing the purchase price. An alternate management method is a contract. When a contract exists, then the PIR should not be used for the same material. A new PIR is created when a purchase from a new material/supplier combination is needed. Within the PIR there is another unique combination named Purchasing Org. Data, formed by the combination of the Purchasing Org., Info Category and Plant Code. If one of those elements is changed, this results in a new record within the PIR. In the PIR’s General View the global fields are available. These fields determine the information common to all plants using the material/supplier combination. The PIR’s maintenance is the responsibility of the Buyer. Any information missing in the ZERS form (approved by the Buyer) and necessary in the PIR should be completed by them.

2.1 Creation of PIR (Purchase Info Record) in WP1

PIRs are created when we have STO,  consignment PO or a subcontracting contract.

We have 4 types of PIR: 


2.1.1 Requirements for new PIR

In order to create new PIR we will need the following information:

2.1.2 Creating PIR

Main activities

Tips / Best practices

Key points

Enter transaction ME11

T-code can be entered directly in Command field. T-code can be saved in Favorites.


Vendor 


Information provided in the request

Material


As informed

Purchasing Organization

Information may change depending on the plant region/type of order

If not informed, you can find on Appendix 4

For ZERS (Materials with Division WA)
NAM - 3012
EMEA - 3004
LAM - 3020
APAC - 3028

Plant 


Information provided in the request

PIR category


If not informed, choose Standard

For ZERS (Materials with Division WA) - Standard

Press enter




Main activities

Tips / Best practices

Key points

Enter Vendor Material Number


Optional info

Enter Salesperson


Optional info

Enter Telephone


Optional info

Enter Order Unit

Example: If the price is 1.02 USD / per 1 YD, then the Order Unit should be YD

  • Creation: This field should match with the price unit of measure given by the requester.

Go to Purchasing Organization Data 1 view

Pressing Enter will move you to Purch. Org. Data 1

 

Main activities

Tips/Best practices

Technology Solutions

Composite Materials

Enter Planned Delivery Time


If pre-populated with a value lower than 5 days, update to 5 days
Enter Purchasing group


For ZERS (Materials with Division WA)
YBM for plants 8359, 8371 (US), 8373 (CA)
YBH for plant 8356 (MX)

Other material types change only if requested

Should be the buyer’s group, can be checked in the file

For US based STOs (where receiving plant is US based such as Rock Hill or Piedmont) - FJ0
For GB/UK based STOs (where receiving plant is EU based, for example GB, Wrexham, K&N Bonded and Non Bonded) - FH0

Note! For packaging materials the purchasing group is defined based on the material group. In order to determine the correct code, refer to tabs: EU (Europe) Packaging or NA (North America Packaging, based on the plant location for which PIR is created.

Enter Standard Quantity

 

Always 1 if no special requests

Enter Tax Code

Check location of plant and Vendor

Other countries

Plant Country

Local Tax

Import Tax

Australia

C”

D”

Brazil

GO* May have more than one option

GO

Canada

LY

AS

Chile

LR

LQ

China

LC

JP

Korea

IE


Mexico

NK

NF

Peru

MM

ML

USA

LN

AS

Europe

Import procedureApplicable for European plants only (Please refer to table above)If the plant that you are creating the PIR is in the same country of the supplier, no import procedure is required.
If the plant that you are creating the PIR is in different country of the supplier then import procedure is required based on vendor's location

Enter Net Price


As requested 

For Brazil Plants (8525/8789) - Intercompany (p. org 3200): Must have price in
USD (Condition ZI01). Contact Sol Silva (Sol.Silva@solvay.com) for the price.

As requested 

Incoterms 1 and 2

Mandatory for all!As informed
  • For Brazil Plants (8525/8789) - DAP SANTOS PORT
  • For STO's (p. org 3200) if not provided by the requester use as default DAP DESTINATION
  • For ZERS (Materials with Division WA): Use PPD Destination as default Incoterms in cases when value is not indicated by requestor


Note!
No "." should be used for the second part on the Incoterms, if not provided, clarify with the requester

As informed 

For STO's (p. org 3200) if not provided by the requester use as default DAP DESTINATION

Note! No "." should be used for the second part on the Incoterms, if not provided, clarify with the requester


Confirmation Control Key (CCK)

Check Incoterms

If Incoterms are COL - always Z003, (exception if going from Kemira to Kemira’s plant 8543 then blank). 
For Brazil Plants (8525/8789), CCK is always Z016

This field is applicable for US plants only 
If it is an import (Tax code AS) then Z004 , if domestic (Tax code LN) and Incoterms are COL then Z003

GR-Bsd IV
Always checked

For Brazil Plants (8525/8789) - Intercompany (STO): Not marked
Always checked


Ackn. rqd
Always checked
Pricing Date Control
For Brazil Plants (8525/8789), Always 1

Go to Conditions view

 


 

 

Main activities

Technology Solutions

Composite Materials:

Update the validity period

The validity period to be used is 31.12.2025 (All material types)

The validity period to be used is 31.12.9999 (ZMAT and ZVER)

For ZERS (Materials with Division WA) - The validity period to be used is 31.12.2021

Click on




Main activities

Key points

Go to Texts view


Main activities

Key points

Purchase Order text

Double click the Purchase order text field to add longer tests via text editor – see step below

Main activities

Key points

Purchase Order text in text editor

For ZERS (Materials with Division WA): Check the request form, if not provided add the material´s long description.

For other material types add only if requested.

Click on


Click on  to save the PIR

 

The PIR number is displayed in the confirmation message at the bottom of SAP screen – copy it to request form for further reference

2.1.2.1 Adding Scale

When in conditions we are able to add Scales related to the price of the material. 

Some items we can have discounts when we buy in a higher quantity.

Main activities

Key points

Select the price line


Click on Scale 

 

Main activities

Key points

Add the scale quantity


Add price for new quantity

 

Save it 



2.1.2.2 STO PIRs

For Stock Transfer Orders we have 2 types:

When creating a STO (Stock Transfer) PIR, we need to delete the condition in order to the correct price reflect for the item. 

NOTE: ALL STO PIRs ARE CREATED FOR PURCHASING ORGANIZATION 3200, NO NEED TO UPDATE THE “VALID TO” IN THIS CASE.

After saving the new PIR, go back to the conditions and follow the procedure below:

Main activities

Key points

Select Price line


Delete 

Confirm deletion

Save it

As informed


2.1.2.3 Adding Freight condition


Main activities

Key points

Condition type

FRB1

Price

As informed

Currency

As informed

2.1.3 Change PIR

Main activities

Key points

Enter transaction ME1M


Vendor 

If informed, otherwise keep it blank

Material

As informed

Purchasing Organization

If informed, otherwise keep it blank

Plant 

If informed, otherwise keep it blank

Click on

 



Main activities

Key points

Select PIR

 

Press Change Info Record 

 



Main activities

Key points

Go to Conditions



Main activities

Key points

Single click on the valid period


New with reference



Main activities

Key points

Validity From

As informed, other wise current date

Valid to

if not informed, end of current year

Amount

As informed

Per

As informed

Price Unit of measure

As informed

Save it 




2.1.4 Delete PIR

Main activities

Key points

Enter transaction ME12 or ME1M as on Change section


Vendor 

Information provided in the request

Material

As informed

Purchasing Organization

As informed

Plant 

As informed

PIR category

If not informed choose Standard

Press enter



Main activities

Tips / Best practices

Key points

Purchasing Group


E00

Extras > Deletion Flags

Shift + F12



Main activities

Key points

Complete info record

Flag if Full PIR should be deleted

Purch. Org. Data

Flag if only plant/p. Org data should be deleted.

Go to Conditions



Main activities

Key points

Double click on the valid period



Main activities

Key points

Validity To

Date in the past

Save it 



2.1.5 Re-activating a supressed PIR

Requests to re-activate PIR that is marked for deletion can be received.


Main activities

Key points

Enter transaction ME1M

Full path: Logistics -> Materials Management -> Purchasing -> Master Data -> Info Record -> List Displays -> By Material


Main activities

Key points

Enter material number


Click on



Main activities

Key points

Check value in Deletion Flag column


Select the PIR to be re-activated


Click on Change Info Record button

Alternatively F7 can be used.

Warning message(s) will be displayed to inform that the record is flagged for deletion.


 



Main activities

Key points

Go to Extras -> Deletion Flags

After removing deletion flag take care to update other information – Purchasing Group, Net price, currency, unit and validity period, Incoterms.


Main activities

Key points

Un-check the Deletion flag box(es)

Save the changes by clicking

Save the changes by clicking



2.2 Source List

A source list is needed every time a new contract is created, a new line is added in an existing contract or when a PIR is created.

2.2.1 Creating Source List


Main activities

Key points

Enter transaction ME01


Material

As informed

Plant

As informed

Press enter




Main activities

Key points

Click on generate records



Main activities

Key points

Press enter or click on confirm



Main activities

Key points

Select “Not changed”


Press enter or click on confirm




Main activities

Technology Solutions

Composite Materials

Valid to

The validity period to be used is 31.12.2025 (All material types)

The validity period to be used is 31.12.9999 (ZMAT and ZVER)

For ZERS (Materials with Division WA) - The validity period to be used is 31.12.2021

Save it 




2.2.2 Deleting Source List


Main activities

Key points

Enter transaction ME01


Material

As informed

Plant

As informed

Press enter




Main activities

Key points

Select the line to be deleted


Press


Save



2.3 Creation of contract

2.3.1 Prerequisites

A contract is created in WP1 when some special negotiation was made with the vendor, for example, some specific material is paid with better terms than it is already set up on Vendor Master Data. 

NOTE: THIS IS NOT A STANDARD PROCESS AND SHOULD BE PERFORMED ONLY WHEN NO OTHER OPTION IS AVAILABLE.

2.3.2 Checking for duplicates

 

Main activities

Tips / Best practices

Key points

Enter transaction ME33K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


Press multiple choice button to receive pop-up window with search options for material master

you can also press F4


Main activities

Tips / Best practices

Key points

Select Purchasing Documents per vendor

T-code can be entered directly in Command field. T-code can be saved in Favorites.


Add vendor


Information provided in the request

Purchasing Document Category


Always K

Press enter

If no values return, you can proceed with the creation



Main activities

Tips / Best practices

Key points

Enter on contracts that shows up

We have one contract by plant. In case it’s not the plant requested, proceed with contract creation, otherwise add item to the existing contract.



2.3.3 Creating a contract

Main activities

Tips / Best practices

Key points

Enter transaction ME31K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


Vendor 


Information provided in the request

Agreement type


MK - Quantity contract

WK - Value Contract

Purchasing Organization


Always CP01

Purchasing Group


Plant buyer code

Plant 


Information provided in the request

Press enter





Main activities

Tips / Best practices

Key points

Validity end


As requested

Target Value 


Optional info


NOTE: In the header you can also set up some different information other than the one in vendor master data, such as different payment term, incoterms, etc. (this information will be the one selected when PO is created)


Press Item Overview 




Main activities

Tips / Best practices

Key points

Material 


As informed

Target Quantity


Mandatory for MK contracts

Order Unit

If not populated, it will get from Material Master


Net Price

NOTE: Price can only be added with 2 decimal characters, in case price informed is as example $1.012 USD/EA > net price would be $10.12 and per will be 10

As informed

Per


As informed

Order Unit Price


As informed

Save it 

After the contract  is created, source list should be created


 

2.3.4 Adding new item in an existing contract

Main activities

Tips / Best practices

Key points

Go to transaction ME32K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


Add contract number



Main activities

Tips / Best practices

Key points

Material number

Find the first blank line
Follow the same procedure as step XX to XX

Add information as requested

Save it




2.3.5 Changing items in an existing contract

Main activities

Tips / Best practices

Key points

Go to transaction ME32K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


Add contract number



Press enter




Main activities

Tips / Best practices

Key points

Select line that needs to be changed

T-code can be entered directly in Command field. T-code can be saved in Favorites.


Click on conditions




Main activities

Tips / Best practices

Key points

Single click on the valid period



New with reference




Main activities

Tips / Best practices

Key points

Amount


Information provided

Save it 

Note: Additional information can be changed also (texts)



2.3.6 Changing Target value in an existing contract



Main activities

Tips / Best practices

Key points

Go to transaction ME32K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


Add contract number



Select Header Details 




Main activities

Tips / Best practices

Key points

Change to Target value to the information provided



Save it 




2.3.7 Deleting item in an existing contract

Main activities

Tips / Best practices

Key points

Go to transaction ME32K

T-code can be entered directly in Command field. T-code can be saved in Favorites.


Add contract number



Press enter




Main activities

Tips / Best practices

Key points

Select Line(s) you want to delete



click on “Delete” 



Save it 



Main activities

Tips / Best practices

Key points

After deleting all lines go to header



Change Validity end to the past



Save it 





Appendix - Approved Requesters - Technology Solutions

The full list can be found here.

NOTE: Requests from Finance team related to Kemira Water Solutions vendor,  can be accepted without further approval. The supplier sends to Finance the summary billing invoice which is reviewed and Finance decides which prices to use as planned for the next period. The Buyers are not involved, since the type of operation with Kemira is tolling and not purchases.



ZERS (Materials with Division WA) and PIR
creation/modification/deletion

PIR creation/modification/deletion
PlantBuyerStoreroom OwnerLPR
8359Willow IslandUSDennis Andlinger

Allen Arnott
Benjamin Burns

Procurement team
8371Mount PleasantUS

Terrence Bybee
Norm Hein
Mike Metcalf

8373WellandCA

James Oliver
Alex Cavasin
Peter Anikejew

8356AtequizaMXCesar RivasAlberto MoraAbril Gomez
8486FengxianCNShen JieMing Liu
Sarawut Sonmuang
Ming Liu
Sarawut Sonmuang


Appendix - Approved Requesters - Composite Materials 


Strategic buyers (Raw Material Buyer) and Site buyers are trained to create PIR's, Contracts and Source List as Riga Data Operations team, they are the owners of this data/process. Planners can also request PIR creation, since they can either turn to the Strategic buyers (Raw Material Buyer) and Site buyers or to Data Operations team. For Source List creation no approval is required.

The full list can be found here (Note: this is only a guidance file).



ZERS (Materials with Division WA) and PIR
creation/modification/deletion
PIR creation/modification/deletion
PlantBuyerStoreroom OwnerLPR
83677180 PiedmontUS

Kay Drake

David Williams

Procurement team

8785

7180 Rock Hill

US

David Lynn

Procurement team

8350

7771 Wrexham

GBKen SharpBen PineProcurement team


Appendix - List of Plants - Composite Materials 


Roll Out 1 for composite material direct procurement data part involves plants:


8367 - 7180 Rock Hill
8785 - 7180 Piedmont
8350 - 7771 Wrexham
8802 - 7771 K&N Non-Bonded Reading
8796 - 7771 K&N Bonded Reading
8822 - 7771 Palmetto Greenville, SC


Roll Out 2


8361 - 7180 Orange
8364 - 7180 Anaheim
8365 - 7180 Greenville, TX
8795 - 7180 ET Horn La Mirada (Wh)

Appendix - Additional Definitions

CONSIGNMENT 

A form of business in which a vendor (external supplier) maintains a stock of materials at a customer (purchaser) site. The vendor retains ownership of the materials until they are withdrawn from the consignment stores. Payment for consignment stock is required only when the material is withdrawn for use. For this reason, the vendor is informed of withdrawals of consignment stock on a regular basis.

SUBCONTRACTING

An instruction to a supplier (subcontractor) to manufacture an ordered part, material or assembly using specified "materials to be provided" (free-issue materials).  A subcontract order contains a maximum of one order item for the ordered material, service, or work, and one or more "material to be provided" items for materials that the ordered makes available to the subcontractor, without charge, for processing.

Appendix  - Q&A


In this link we have a Q&A where we can find the most common questions and answers regarding this activity.


Appendix  - Embargo check in Purchase Order



If the following message appears, trade.control@solvay.com team should be contacted.





Appendix  - Purchasing Organizations


Domain

Europe

North America

Latin America

APAC

2 - Packaging

3002

3010

3018

3026

4 - Industrial Supplies

3004

3012

3020

3028

6 - Raw Materials

3006

3014

3022

3030

9 - Inter-Company

3200

10 - Third Party

3100

3101

3102

3103

Appendix  - ARIBA Project


Once a vendor in enrolled in the ARIBA project the following set up will be created in SAP



When these criteria are matched, it means the supplier is working with Solvay using the Ariba Platform, receiving Purchase Orders and sending Invoices.


If we already have the above information at Vendor Level and Contracts / PIR, all new creation will assume the code by default that cannot be removed, unless the request comes from the Ariba Team.
All new PIR / Contracts will take the default Control Key from Purchasing / Plant Level.