This document's objective is to provide a guide to ZPRC, ZUNB and ZMAT – Raw Material Material master data management for GBU Technology Solutions and Composite Materials (Legacy Cytec organization).
Material Master Data management process includes creation and modification of the material as well as its inactivation and flagging for deletion. Creation of Basic Data, Classification, Sales general/plant, Foreign Trade, Purchasing, General, Plant Storage and Label Data Views will be presented in this procedure. Management of MRP, Work Scheduling, Quality Management, Accounting and Costing Views is being performed by Process Teams.
Requests of Technology Solutions Material Master creation or maintenance can be performed by approved requestors listed in Appendix - Technology Solutions - List of contacts. Requests of Composite Materials Material Master creation or maintenance should be submitted via Sharepoint.
All requests are sent to Riga Data Operations team via Freshdesk or alternatively by e-mail. Common e-mail address of Riga Data Operations team: datamanage@solvay.com
Request form for Technology Solutions materials should usually be attached to MOC Gensuite web page under MOC ID provided by requester.
The referral Technology Solutions lists mentioned in this procedure, such as Purchasing Groups and Profit Center List are embedded in the TS SAP Material request form file.
Under Riga Data Operations scope is the management of ZMAT, ZVER and ZUNB materials for GBU Technology Solutions and Composite Materials (legacy Cytec) sites in WP1 SAP system. Management of ZERS materials is described in a separate procedure. Riga Data Operations can create and extend ZDIE materials if requested so by Finance.
Material Type | Description | Division |
|---|---|---|
ZMAT | Finished Goods | Multiple |
ZPRC | Commercial Products | N/A |
ZVER | Packaging | WD |
ZUNB | Stocked and non-valuated materials | WD (for packaging) |
ZDIE | Services | Multiple |
Abbr. | Description | Abbr. | Description |
|---|---|---|---|
RCS | Rhodia Core System | SBS | Solvay Business Services |
ZMAT | Finished product, semi-finished product, raw material | HSE | Health, Safety and Environment |
ZVER | Packaging | DG | Dangerous goods |
ZUNB | Stocked and not valuated material | MRP | Material Resource Planning |
ZDIE | Service | UoM | Unit of Measure |
ZPRC | Commercial Product |
Technology Solutions ZMAT – Raw Material setup can be performed only once MOC-ID and ZPRC code are available.
Prior to submitting a new ZMAT request, it is the requester´s responsibility to ensure the material does not exist in SAP already, so no duplicates are created in the system. If the material was not found, the TS SAP Material request form must be filled and submitted to Data Management for material master setup in SAP. A second search in the system is performed by the Data Management team to ensure no duplicates are created.
Raw Material setup can be performed only once MOC-ID and ZPRC available.
In all cases when MOC-ID is missing Lindsay Schramm and HazCom team should be contacted to clarify whether raw material code can be set up without this information.
Prior to material creation in the system search is performed by the Data Management team to ensure no duplicates are created.
ZPRC and PRCO can be found validating MOC in Gensuite Portal.
User: data.manage@solvay.com
Password: Solvay123
Once you access the MOC Portal, please:
In this step:

Important documents and information to be observed in the MOC:
Screening Questions




Attachments
In this section you will find the additional documents to be used in the raw material creation


Main activities | Tips / Best practices | Key points |
Enter transaction MM03 | T-code can be entered directly in Command field. T-code can be saved in Favorites. | Full path: Logistics -> Materials Management -> Material master -> Material -> Display |

Main activities | Tips / Best practices | Key points |
Press multiple choice button to receive pop-up window with search options for material master |

Main activities | Tips / Best practices | Key points |
Click on | ||
Select the option 'Material Number/Material Description' and/or 'Materials by Commercial Product (PRCOM)' | Field 'Old material number' can be used to look up material by BPCS Code (temporarily). |

Main activities | Tips / Best practices | Key points |
Run a search in Material Description | Use Wildcards to best describe | Open the material request form, copy the short text from the requested material and run a search in Material description with wildcards. |
Hit Enter |

Main activities | Tips / Best practices | Key points |
Verify entries found – compare results with the material's "short description" mentioned in the request form. If you have doubts about the material already created, contact the Requester to clarify. | If result points to |

Main activities | Tips / Best practices | Key points |
Enter transaction MM01 | T-code can be entered directly in Command field. T-code can be saved in Favorites. | Full path: Logistics -> Materials Management -> Material master -> Material -> Create (General) |

Main activities | Tips / Best practices | Key points |
|---|---|---|
Enter Industry Sector | Always choose "Chemical Industry" | |
Enter Material Type | Select the material type indicated in the request form | |
Copy from… Material | Option to copy data from an existing material can be useful in some cases. | |
Hit Enter |


Main activities | Tips / Best practices | Key points |
|---|---|---|
Select Views to be created | Creation of views can be performed all at once or in separate steps | List of single Technology Solutions Storage locations can be found in Appendix 4. NOTE! Quality Management view should be selected for Composite only. NOTE! Before creating a Raw Material Product for Composite Materials check if there is a ZUNB already created for the ZPRC. NOTE! Warehouse Management 1 & 2 Views to be created and warehouse number added (in brackets) for warehouse managed plants only: For Composite Materials always extend to Warehouse based on the file per plant |
Hit Enter | Use Default Setting button to save your selections for future creations |

| # | Main activities | Key Points |
|---|---|---|
| 15 | Fill in Organizational Levels | Technology Solutions
Composite Materials
Note! If we receive a request to extend the raw material to distribution channel 0B, a workflow in sharepoints needs to be created using the Change flow and the EHS approval needs to be attached to the flow. |
| 16 | Hit Enter |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
17 | Enter Material Description | Check the request form for "SHORT DESCRIPTION". It is used for search and restricted to 40 characters. If the information does not fit on this field, then the complete description should be added on the basic data text. | Should match ZPRC record provided by HazCom Team. Preferably the chemical designation (and not a formula/Brand name) followed by the Net weight and the type of packaging associated with the material. *For Composite Materials - copy from the template |
18 | Enter Base Unit of Measure | Always KG *For Composite Materials | |
19 | Enter Material Group | Always 0451 | |
20 | Enter Division | Always KV | |
21 | Enter General Item Category Group | Always NORM | |
22 | Enter Gross Weight | Check the request form | Proportion of Gross weight to Net weight to be entered (Net = 1) *For Composite Materials - copy from the template |
23 | Enter Net Weight | Always 1 *For Composite Materials - copy from the template | |
24 | Enter UoM for Weight | Always KG | |
25 | Enter Packing Group | 0005 for Packed material | |
| * | Enter Ref. mat. for pckg | For Composite only! | Enter default number 1911973 |
26 | Go to Descriptions tab | From Basic Data View Descriptions tab can be accessed by pressing Additional Data button in the top part of screen as well. Tabs in Additional Data can be filled in any sequence. |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
27 | Enter material descriptions in local languages | 12 mandatory languages are: | |
28 | Go to Units of measure tab | From Basic Data View Units of Measure tab can be accessed by pressing Additional Data button in the top part of screen as well. Tabs in Additional Data can be filled in any sequence. |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
29 | Enter Alternate Units of Measure conversions | Fixed conversion 11023 LB <-> 5000 KG | |
| * | Add all the Alternative Conversions provided in the form (Tab: Alternative UoM Calculator) and additional conversions in the same dimension. For example: If the requester provides units of measure in KG and M, then add the conversion for pound, yards and feet.
For example: If the requester does not provide Alternative units of measure for Packaging and Pallet add the default conversion based on the Base Unit of measure and Packaging. If you have Base Unit of measure in M and the Packaging type BX, then add 1 BX = 500 M and add 1 PAL = 5000 M.
Exception: for BULK only add the default LB conversion Note! If there is any change/update request in the Alternative units of measure, before updating check if the material is shared.
| ||
30 | Enter conversion of Stock keeping UoM to Base UoM | Conversion between one packaging unit and base unit of measure | |
31 | Enter any additional conversion if requested | Check the request form | |
32 | Return to Main Data |
For Composite Only!

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
* | Enter Material Long description | Use button to add languages | 12 mandatory languages are: & – Brazilian Portuguese N – Dutch |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
33 | Go to Basic data 2 view | ||
34 | Enter Basic material (related ZPRC Code) | Mandatory field! | For Technology Solutions: Check the MOC For Composite Materials: if not provided in the form, check in the Sharepoint on EHS Info tab
|
35 | Enter Dangerous Goods indicator profile | Technology Solutions and Composite Materials (general rule): ZIP for all materials at the moment of material creation For Composite materials (exception): if the material has one of the ZPRCs mentioned below, the DG indicator, should be Z00 ZPRC 90077853 Release Paper | |
36 | Tick Environmentally relevant | Technology Solutions and Composite Materials (general rule): Mandatory for all materials For Composite materials (exception): if the material has one of the ZPRCs mentioned below, the Environmentally relevant should not be flagged ZPRC 90077853 Release Paper | |
37 | Go to Classification view |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
38 | Select "Batch" type of Classification |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
39 | Enter Class Type 023 | Select class as per required GBU: 014 – Technology Solutions | |
| * | Additional class for Composite Materials only | Select Class type 001 | |
a. | Enter Material Class | Default Z_CM_MAT | |
| b. | Copy all the values provided in the form in "Classification" tab | ||
| c. | Note! If requester adds new value in the template for classification, we should send to Lisa Wohnlich (lisa.wohnlich@solvay.com) for approval | ||
40 | Press Next screen button to move to next selected view |
Only for Composite Materials - upon material creation
Extended the composite materials for sales organization as per image below:

Main activities | Tips / Best practices | Key points |
|---|---|---|
Enter Cross-distribution-chain specific material status | Status 63 is to be set at the moment of material creation to allow use of material in operations | |
Enter Valid from date for Cross-distribution-chain specific material status | DD.MM.YYYY | |
Maintain Tax classifications | System will automatically determine which Countries' tax lines should be added | Always 1 for all countries unless otherwise indicated by Finance or Tax department |
| Go to Sales: sales org. 2 view |

Main activities | Tips / Best practices | Key points |
|---|---|---|
Enter Material statistics group | Always 1 | |
Enter Account assignment group | Check the request form, if not provided populate with F | |
Enter Item category group | Always ZMAN | |
| Save the extension |

# | Main activities | Tips / Best practices | Key points | ||||||||
42 | Enter Availability check | Raw materials and packaging – 02 *For Composite - Default ZD | |||||||||
43 | Enter Material freight group | Mandatory for Packed materials for US, CA and BR Bulk – empty Material Hazardous class can be found in RM SDS sheet under section 14th in attached documentation for MOC-ID provided by requester |
*For Composite - Copy from the template | ||||||||
44 | Activate Batch Management requirement indicator | Same field is also available in Purchasing, Plant data / storage 1 and Warehouse Management 1 views | Always checked for ZMAT | ||||||||
45 | Enter Transportation Group |
| Should be checked in Sinequa for SDS sheet. Using sections 9 and 14 correct Transportation group can be determined. In Sinequa RM SDS can be found using ID underlined below.
*For Composite - Default 0001 | ||||||||
46 | Enter Loading Group | Bulk – 0002 Else – 0001 | |||||||||
47 | Enter Profit Center | Same field is also available in Plant data / storage 2 view | List of profit centers can be found in following Google drive link *For Composite - per template | ||||||||
48 | Go to Foreign trade export view |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
*** | Commodity/import code is NOT to be entered at the time of material creation – it will be loaded by responsible team | When extending material to a new Plant the Commodity/import code field is to be left blank (to be cleared if Copy from… option is used). Whenever a material is extended to any of non-GTS plants (see Appendix 3), extension has to be added in the linked file. | |
49 | Control code | Required for all Brazilian plants | Contact HTS Team (htsclassification@solvay.com) for correct code |
50 | Enter Country of origin | Check the request form | |
51 | Enter Mat. CFOP category | Field is mandatory for Brazil plants only | Always 0 |
52 | Go to next view | Go to Purchasing view. |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
53 | Enter Purchasing Group | List of purchasing groups can be found in following Google drive link *For Composite - per template | |
54 | Enter Plant-specific material status | Once Finance creates Accounting and Costing Views and performs material costing run, the status will be removed by Finance to allow use of material in operations. | Status Z1 is to be used at the time of material creation. |
55 | Activate automatic Purchase Order indicator | Always checked | |
56 | Enter Purchasing value key | Packed ZMAT – 0001 | |
57 | Enter GR processing time | Plant data administrators will change the field value if necessary | Default value at the time of material creation – 2 *For Composite - Default to 1 |
58 | Go to next view | Foreign trade Import | Values will be copied from Foreign trade export view |
59 | Go to next view | Plant data / storage 1 view |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
| * | Temp. Conditions | *For Composite (Mandatory!) | Per template |
60 | Enter Physical inventory indicator for cycle counting | Plant data administrators will change the field value if necessary | Default value at the time of material creation – B |
61 | Enter Minimum Remaining Shelf Life | Default value at the time of material creation – 1 | |
62 | Enter Total shelf life | Important: Shelf life days should be consistent on Commercial Product level |
|
63 | Go to Plant data / storage 2 view | Nothing should be entered as Profit center data are being copied from Sales: general/plant view | |
64 | Go to Label data |
For Composite only!

Main activities | Tips / Best practices | Key points |
|---|---|---|
| Inspection interval |
| |
QM proc. active | Always flagged | |
| QM Control Key | European plants - default REACH |
Label View
| Technology Solutions | Composite Materials |
|---|---|
Important! Material number with MOC ID and ZPRC# should be sent to responsible parties from plant to complete missing views for RM (MRP, QM, Acct, Costing). Template Dear (Requester's name),
Kind regards, |
Important! It is crucial to request the correct DG indicator for Finished products after the material creation. For now, release the Sharepoint request, keep the Freshdesk ticket open and contact the people listed below to obtain the correct value. On the request provide the ZPRC#
|
Following MOC procedure plants are obligated to review existing MOC process every two to three years, therefore valid MOC ID is mandatory component for Raw Material extension, this information should be provided by requester any time material should be created for a new plant.
HazCom Team should be involved in Raw Material activation process due to their responsibility to verify MSDS (ZPRC) code validity and correctness. They will also verify whether existing MOC ID can still be used.
NOTE: Raw Materials should not be extended to Trading plants (8572 – MX, 8573 – CL, 8571 – PE, 8580 – NL, 7788 – ID, 7786 – AU, 8574 - CN).
To extend material enter transaction MM01. Copy from… option can be used, preferably to copy from an existing view of the same material.
To extend Raw material material to a Plant, select Sales: General/Plant Data, Foreign Trade: Export Data, Purchasing, Foreign Trade: Import Data, General Plant Data/Storage 1 & 2. 
Material modification is allowed only if validated by all Plants using the material.
Requests to change the fields listed below must not be performed – in this case a new material has to be created.
In some exceptional cases range can be added to Raw Material, e.g. TALLOW ALKYL AMINE >97% 159/165KG DR
Another exception can be a mistake for recently created material that has not yet had any stock and stock movements in the system. 
# | Main activities | Tips / Best practices | Key points |
1 | Enter transaction MM03 | T-code can be entered directly in Command field. T-code can be saved in Favorites. | Full path: Logistics -> Materials Management -> Material master -> Material -> Display |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
2 | Enter Material number | ||
3 | Select Purchasing (or Sales: General/Plant Data) view |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
4 | Verify the possible Plants related to the Material by clicking on the match code. | ||
5 | All Plants using the material are listed |
If material is open for more than one Plant, contact the other Plants to validate the requested modification.
If the answer is positive, change the material as shown in section 2.2.2. Manual modification of material.
If the answer is negative, create a new material as described in Chapter 2.1.2. of this OP, associated with the Plant that made the request.

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
1 | Enter transaction MM02 | T-code can be entered directly in Command field. T-code can be saved in Favorites. | Full path: Logistics -> Materials Management -> Material master -> Material -> Change |
2 | Select the view containing the field that needs modification | ||
3 | Select the Organizational Level for which the modification is requested | Repeat the modification for all Sales Areas or Plants if applicable. | |
4 | Save the changes performed |
Should not be performed by material creation, can be opened for Intercompany (e.g. US23/9O; NL01/9O etc) sales area only when extending Raw Material to different plant and Stock Transfer is required from one location to another.
Should not be extended to commercial sales area.

Main activities | Key points |
|---|---|
| Cross-distribution-chain specific material status | Status 63 is to be set at the moment of material creation to allow use of material in operations |
| Valid from date for Cross-distribution-chain specific material status | DD.MM.YYYY |
Maintain Tax classifications | Always 1 for all countries unless otherwise indicated by Finance or Tax department |

Main activities | Tips / Best practices | Key points |
|---|---|---|
Enter Material statistics group | Always 1 | |
Enter Account assignment group | Always I | |
Enter Item category group | ZVRP |
Before inactivating material an approval from appropriate purchasing contact should be received, material should also be checked for open items under "Stock overview".
If there are no open activities, Stock will show only "0". If any other values displayed, appropriate Product Manager should be contacted for Stock removal.
After Stock is cleared material can be inactivated.
If material has to be inactivated for all plants and sales areas:
If material has to be inactivated for specific plants or sales areas:
Inactivation of ZPRC material can be performed only if all ZMAT materials linked to it are inactive:
It is in Data Management scope to create ZPRC records for Raw Materials when requested comes from HazCom Team. When ZPRC record is completed in SAP WP1, systems are being synchronized overnight and PRCO code appears on HazCom side.
To complete this request material chemical name should be verified and provided by HazCom Team. 
# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
1 | Enter Industry Sector | Always C | |
2 | Enter Material Type | ZPRC |

# | Main activities | Tips / Best practices | Key points |
3 | Select views | Basic Data 1; Basic Data 2; Classification; Label Data |

# | Main activities | Tips / Best practices | Key points |
4 | Enter description | Material chemical name provided by HazCom + / GENERIC | |
5 | Base Unit of Measure | Always KG | |
6 | Material Group | Always 0451 |

# | Main activities | Tips / Best practices | Key points |
7 | 12 mandatory languages are: |

# | Main activities | Tips / Best practices | Key points |
8 | Classification view – Class type 001 | LIP # LIP0020148 should be entered | |
9 | Go to label view | No data maintained | |
10 | Save material |
It is in Data Management scope to create ZPRC records for Raw Materials when requested comes from HazCom Team. When ZPRC record is completed in SAP WP1, systems are being synchronized overnight and PRCO code appears on HazCom side.
To complete this request material chemical name should be verified and provided by HazCom Team.
![]()
# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
1 | Enter Industry Sector | Always C | |
2 | Enter Material Type | ZPRC |

# | Main activities | Tips / Best practices | Key points |
3 | Select views | Basic Data 1; Basic Data 2; Classification; Label Data |

# | Main activities | Tips / Best practices | Key points |
4 | Enter short description | Material Name in standard languages provided by Hazcom | |
5 | Base Unit of Measure | Always KG | |
6 | Material Group | Always 0451 | |
| 7 | Old Material number | MSDS reference provided by requester | |
| 8 | Lab/Office | Z20 for RM | |
| 9 | Basic Data Text | Maintained in standard languages when description does not fit in short text field |

# | Main activities | Tips / Best practices | Key points |
10 | Class Type | 001 Material Class | |
| 11 | Class | Generic LIP00 by default | LIP0034040 |
12 | Go to label view | No data maintained | |
13 | Save the material |
Important! After the ZPRC creation also create the ZUNB!

# | Main activities | Tips / Best practices | Key points |
1 | Enter transaction MM01 | T-code can be entered directly in Command field. T-code can be saved in Favorites. | Full path: Logistics -> Materials Management -> Material master -> Material -> Create (General) |
![]()
# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
2 | Enter Industry Sector | Always choose "Chemical Industry" | |
3 | Enter Material Type | Select "ZUNB Stocked and non-valuated" | |
4 | Copy from… Material | Option to copy data from an existing material can be useful in some cases. | |
5 | Hit Enter |

| 6 | Select Views to be created | Creation of views can be performed all at once or in separate steps | Select Basic Data 1, Basic Data 2, Purchasing and Label Data Views. |
7 | Hit Enter | Use Default Setting button to save your selections for future creations |

| # | Main activities | Tips / Best practices |
|---|---|---|
| 8 | Fill in Organizational Levels | Extend to the following plants: 7264 ZZZZ ex 3969 / Négoce IT |
| 9 | Hit Enter |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
10 | Enter Material Description | "SHORT DESCRIPTION" | Copy from the ZPRC |
11 | Enter Base Unit of Measure | Copy from ZPRC | |
12 | Enter Material Group | Copy from ZPRC | |
13 | Enter Old Material Number | Copy from ZPRC, if is not provided, leave it blank. | |
14 | Go to Additional Data |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
15 | Enter material descriptions in local languages | 12 mandatory languages are: | |
15 | Go to Units of measure tab | From Basic Data View Units of Measure tab can be accessed by pressing Additional Data button in the top part of screen as well. Tabs in Additional Data can be filled in any sequence. |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
16 | Enter Alternate Units of Measure conversions | Fixed conversions: 1 BJ <-> 1 KG 1 DR <-> 1 KG 1 PL <-> 1 KG | |
17 | Return to Main Data |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
18 | Go to Basic data 2 view | ||
19 | Enter Basic material (related ZPRC Code) | Check the Freshdesk Ticket | |
20 | Go to Purchasing view |

# | Main activities | Tips / Best practices |
|---|---|---|
21 | Go to Label Data view | No data has to be maintained in Purchasing view, however the view has to be created |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
22 | Enter the Primary Packaging Unit (PPU) | Default DR - Drum | |
23 | Select the primary packaging unit of measurement | ||
24 | Press the indicated button to Import labeling specifications for selected packaging. | Templates for Label data: All available on Material 2028246 |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
25 | Enter the Material #2028246 | ||
| 26 | Press |

# | Main activities | Tips / Best practices | Key points |
|---|---|---|---|
28 | Leave all the material types selected | ||
| 29 | Press | ||
| 30 | When all data has been entered, save the material by pressing button and exit material creation | Copy number of the created material into communication to Requestor, system confirmation message on the bottom of the screen can be used: | |
| 31 | Note! Remember to perform the extension for all the six plants | 7264 ZZZZ ex 3969 / Négoce IT |
Packaging type | Label category | Gen. Var. | Copies | ||
DR, BX, CY, JRC, PL, BULK, BAG | Z_RAW | Raw material label | GLM_RAW_01 | 1 | |
TE, BB | Z_RAW | Raw material label | GLM_RAW_01 | 2 |
Requests for Raw Material requests can be accepted from Purchasing representative.
Detailed Technology Solutions Support Organization file by plants can be found in following link.
Representative | ||
US and Canada | Vanessa Scott | |
Leslie Fleming | ||
| Peter Mertzanis | peter.mertzanis@solvay.com | |
Thierry Leclerc | ||
Mario Bruins | ||
LAM | Abril Gomez | |
APAC | Natpapan Chueakongtrakul (Poon) | |
Celine Koh | ||
Catherine Lu | ||
Sorrawit Parknondhkul | ||
Nathan Purvis | ||
EMEA | Thierry Leclerc | |
ZPRC/MOC | HazCom | hazcom.rawmat@solvay.com |
MOC-ID | Lindsay Schramm | Lindsay.schramm@solvay.com |
Whenever a material is extended to any of non-GTS plants, extension has to be added in a file to notify the responsible team. Location of the file.
Country | Plant Code | Description |
Japan | 8524 | 7418 / Gas Chem Logistic Osaka |
Singapore | 8506 | 6062 / Poh Tiong Choon Jurong |
Storage Location | Description |
8380 | 7786 / JF Hillebrand Fremantle |
8433 | 7788 / Jakarta |
8496 | 7722 / BDP Peru Arequipa |
8500 | 7725 / Andimex San Antonio |
8503 | 7988 / Daesung Whse Yangsan |
8505 | 7723 / FH Logist Azcapotzalco |
8506 | 6062 / Poh Tiong Choon Jurong |
8507 | 7725 / Sercabol Antofagasta |
8508 | 7776 / Sinotrans Intl Shanghai |
8509 | 7734 / KWE Logistics Shanghai |
8511 | 7794 / CML Ltd Walvis Bay |
8515 | 7786 / Toll Contr Laverton Nth |
8519 | 7786 / NSS Port Sth Townsville |
8520 | 7008 / XPO Logistic Bristol |
8521 | 7008 / XPO Logistic La Porte |
8522 | 7008 / XPO Logistic Plainfield |
8525 | 7523 / NATAM Express Maua |
8527 | 7794 / Schenker Kempton Park |
8528 | 7734 / Sinotrans Intl Shanghai |
8543 | 7008 / KEMIRA WATER MOBILE |
8545 | 7008 / FLUID ENERGY HATFIELD |
8548 | 7008 / MOBILE SOLVENT EIGHT MILE |
8549 | 7752 / NOVA MOLECULAR PASADENA |
8553 | 7008 / SOUTH COAST HOUSTON |
8554 | 7008 / SPRAY TEK MIDDLESEX |
8559 | 7008 / TOLL COMPACTION NEPTUNE |
8589 | 7734 / Tianjin DLD Beicheng Wh |
8605 | 7794 / Kemira Chem Bradford |
8614 | 7734 / COSCO Logistic Tianjin |
8617 | 7776 / COSCHEM Logist Shanghai |
8618 | 7794 / Praxair Oevel-Westerlo |
Plant | Data Governance Lead | DGL Backup |
Anaheim | Rehan Suhrwardy | Nic Donovan |
Orange | Corinne Nelson | |
D’Air | Bruce Gormley | |
Greenville | Hope Helton | Brianna Hammond |
Winona | Danielle Dietermann | Jenna Sand |
Kalamazoo | Carrie Replogle | |
Havre de Grace | John Cahoon | Kenya Eaton |
Piedmont / Rock Hill | Harrison Blackwelder | Mike Zitricki |
Wrexham | Stuart Tudor Jones | Peter Kaye |
Oestringen | Nina Kunze | Jose Marin |
Fengxian | Rick Marmol |
Appendix – List of plants for Composite Materials
Plant | Name of Plant in SAP | Company Code | Sales Organization | Country |
|---|---|---|---|---|
| 8341 | 8341 - 7180 / Tempe | 7180 | US32 - Composite Materials | USA |
| 8347 | 8347 - 7772 Oestringen | 7772 | DE13 - Composites Materials | Germany |
8350 | 8350 - 7771 Wrexham | 7771 | GB40 - Composites Materials | United Kingdom |
| 8361 | 8361 - 7180 Orange | 7180 | US32 - Composite Materials | USA |
| 8363 | 8363 - 7180 Anaheim D'Aircraft | 7180 | US32 - Composite Materials | USA |
| 8364 | 8364 - 7180 Anaheim | 7180 | US32 - Composite Materials | USA |
| 8365 | 8365 - 7180 Greenville | 7180 | US32 - Composite Materials | USA |
| 8367 | 8367 - 7180 Piedmont | 7180 | US32 - Composite Materials | USA |
| 8368 | 8368 - 7180 Havre de Grace | 7180 | US32 - Composite Materials | USA |
| 8370 | 8370 - 7180 Winona | 7180 | US32 - Composite Materials | USA |
| 8374 | 8374 - 7180 / Bellevue | 7180 | US32 - Composite Materials | USA |
| 8393 | 8393 - 7771 / Wilton | 7771 | GB40 - Composites Materials | United Kingdom |
| 8456 | 8456 - 7180 Kalamazoo | 7180 | US32 - Composite Materials | USA |
| 8466 | 8466 - 7188 / Tempe CDM | 7188 | US32 - Composite Materials | USA |
| 8586 | 8586 - 7776 / Shanghai | 7776 | Tech Solutions (CEM) | China |
| 8609 | 8609 - 7180 / Alpharetta | 7180 | US32 - Composite Materials | USA |
| 8626 | 8626 - 7180 / Saddle Brook | 7180 | US32 - Composite Materials | USA |
| 8628 | 8628 - 7776 Fengxian | 7776 | Composites Mats 7776 | China |
| 8785 | 8785 - 7180 Rock Hill | 7180 | US32 - Composite Materials | USA |
8786 | 8786 - 7180 / Princeton | 7180 | US32 - Composite Materials | USA |
| 8793 | 8793 - 7180 / ATSCOTT MFG Pine City | 7180 | US32 - Composite Materials | USA |
| 8794 | 8794 - 7180 / MCC Huntington Beach | 7180 | US32 - Composite Materials | USA |
| 8795 | 8795 - 7180 / ET Horn La Mirada | 7180 | US32 - Composite Materials | USA |
| 8796 | 8796 - 7771 / K&N Bonded Reading | 7771 | GB40 - Composites Materials | United Kingdom |
| 8802 | 8802 - 7771 / K&N Non-Bonded Reading | 7771 | GB40 - Composites Materials | United Kingdom |
| 8815 | 8815 - 7180 / Taichung City | 7180 | US32 - Composite Materials | USA |
| 8817 | 8817 - 7180 / Hale Baltimore | 7180 | US32 - Composite Materials | USA |
| 8818 | 8818 - 7180 / First Choice Vineland | 7180 | US32 - Composite Materials | USA |
| 8819 | 8819 - 7180 / XPO Logistics Levittown | 7180 | US32 - Composite Materials | USA |
| 8820 | 8820 - 7180 / Lonestar Richardson | 7180 | US32 - Composite Materials | USA |
| 8821 | 8821 - 7180 / Delta Greenville TX | 7180 | US32 - Composite Materials | USA |
| 8822 | 8822 - 7180 / Palmetto Greenville SC | 7180 | US32 - Composite Materials | USA |
| 8823 | 8823 - 7180 / Seven Rivers Winona | 7180 | US32 - Composite Materials | USA |
| 8824 | 8824 - 7180 / Rinchem Eagan | 7180 | US32 - Composite Materials | USA |
| 8825 | 8825 - 7180 / KPAC Wilmington | 7180 | US32 - Composite Materials | USA |
| 8826 | 8826 - 7180 / Lewis Howard Kalamazoo | 7180 | US32 - Composite Materials | USA |
| 8834 | 8834 - 7180 / Jensen-Souders Itasca | 7180 | US32 - Composite Materials | USA |
| 8845 | 8845 - 7180 / eShipping Ontario | 7180 | US32 - Composite Materials | USA |
Check for Active/Inactive PIR (ME1M)



Check for open Purchase Orders (ME2N)
Open PO’s can be located using transaction ME2L. ME2N can also be used.
Scope of List: determines that system will search for all PO’s for this supplier;
Selection Parameters: narrows the search down for PO’s with open invoices.


Check for open Sales Orders