AROMA

Manual input - To/day

=>  MDC by couple Plant x Material x Resource


S&OP Manager
  • For 1 couple Resource-Prod group, the MDC does not change

TS



NOVECARE






SettingsExplanation AROMATSNOVECARE
OEE

Overall Effectiveness Equipment

MDC x OEE = Production Planning capacity

Plant x Resource by default

  • yes


NB OF SHIFTS

We can manage the nb of shifts, meaning that Dynasys will multiply this number to the Nb of Hours per shift to get the Opening hours per day

By default 1 or 3

  • Available but not used


HRS PER SHIFT

Hrs per shift x Nb of shift = Nb hrs available per day

By default 24Hr or 8Hr

  • Available but not used


CLOSED DAYS

Decrease the capacity of the month by putting some closed days

By default:

Plant x Resource x Month

  • Specific by Days instead of Month in order to manage the current month


TYPES OF CLOSED DAYSWe can define several types of closed days - Sum of all = Total closed days
  • Yes, 5 types


NB OF EQUIPMENT

By default = 1 unit

It will multiply the available Hrs

  • No


COMMENTSPossibility to add a general comment by month
  • yes


Screens






SettingsExplanation AROMATSNOVECARE
Item priority

Define priority between the products inside the same "rule" of calculation.

ex: if we calculate the production planning by Planning Level, then the priority is made between SKUs inside the same Planning Level

By default: same priority for all SKUs

  • Yes, the target is to put in 2nd priority the main Material in order to see shortages at one material


Minimum production

Quantity to define in the Production Plan as minimum to do (and mandatory even if there are no requirement)

=> We can plug from SAP the "Process order"

  • Yes, plugged from SAP


Maximum productionQuantity to define in the Production Plan as maximum to do, even if the requirements are higher and capacities available
  • No


Minimum run

Quantity minimum to do in the production planning, but only if it required some production

=> We can plug the SAP MRP View "Minimum Lot Size"

  • No


Forced production

Quantity to fix in the system as to Produce in the month. Be careful on the current month and netting with actuals.

=> By default at SKU level (material x Plant)

  • Yes, at SKU and specific % at Resource level (but it requires only one material on that resource)


Batch size

Batch quantity to define in the production plan

=> We can plug the SAP MRP View "Fixed Lot Size"

  • No

Specific batch size at Product Group level (for one family) required specific Production Plan calculation