> P&I methodology Lead times (Macro view)



> SAP Lead times summary (detailed view)


P&I solution takes the Lead times coming from SAP until the Material Availability Date.

All that happens afterward (Loading + Pick Pack + Transit time to customer), in gray below, is not part of DynaSys P&I scope and is carried outside the tool.


> SAP Lead times transferred to P&I



Key information to be taken into account:


Production Scheduling: No information in SAP related to the Scheduling LT -> Will be defined in the P&I solution.

It's considered in SHS RLT calculation but not like an 'addition'. More information in 'Scheduling LT' part.


Inter/Intra Company Scheduling: