ISSUE-At PO 4513654336 In SC 1003388988 al the line are create in urgency code 99 but In ATB /Prq 4003232043 the code from 10-70 has suddenly changed to code 30 in SAP.



Reference Ticket:-https://sbs-support.solvay.com/a/tickets/5169223.



Request: To  Understand why a SC created with a Requirement Urgency 99 (no urgent) was transformed into a Requirement Urgency 30 (urgent) once PREQ / PO generated in SAP.  



SOLUTION:


There is an automation in SAP that automatically changes the default 99 to a 30 when the PReq/PO item is considered as Critical OR Capex:

 Some lines of that PReq have the default 99 value while others were automatically changed by SAP to value 30: This happened because:



The value 30 informs the Service Centers that the items must be handled with special care and attention.


Please see the  Solvay Capex Rule