P&I Lead Times | Level Required | Proposed SAP Field | Purpose in SAP | SAP Level | Comment |
Procurement LT | Material / Plant | SAP Processing time for purchasing (Workdays) | Time (Plant workdays) that the purchasing department requires to convert a purchase requisition into a purchase order. | Plant x workdays | |
Material / Plant | SAP Planned delivery time (Calendar days)Could be maintained at different place:-Pld Delivery time from Purchase info Record (1st priority)
- Pld Delivery time from MRP2 view (only if PIR is NA)
| Number of calendar days needed to obtain the material or service if it is procured externally. | Material x PlantCalendar days | If both PIR + MRP2 view 'Pld Delivery time' are defined, we take PIR as 1st priority.Attention : this Pld Delivery time (both in MRP2 view or PIR) should only consider transit time => the transit time will be used to back calculate the correct Production & Good issue date in shipping site on SAP. | |
GR Processing LT | Material / Plant | GR processing time (MARC-WEBAZ)
| Number of workdays required after receiving the material for inspection and placement into storage. | Material / PlantWorkdays |

Monolevel RLT | Represents the total time between placing a production / replenishment order and the availability date. It’s “monolevel” since it only considers the product’s own lead times (scheduling / production lead time / ….) , does not consider other BOM level.
For more information about "Produced" or "Purchased LT", please refer to: Lead times coming from SAP | Monolevel Independent of SHS |
SHS RLT | Represents the total time between placing a production / replenishment order and the availability date. It considers other BOM levels lead times (multi level) + distribution network (multi sites) and stock holding strategies. | Multilevel LT SHS dependent |