Tasks to be completed when creating an operating procedure (from creation to publication)
|
This OP explains the steps necessary to update the confirmation control - ARIBA NETWORK
Maintained in WP1_400 and PF1_020.
ARIBA is an online platform that aims to facilitate Buyer-Supplier transactional activities.
Allows the supplier:
- to receive and process electronic purchase orders;
- submit electronic invoices;
- track status of their invoices
When requested to mark a vendor as ARIBA it is used the transaction ZMM_ARN_VND_ACT_DCT (PF1_020 or WP1_400).
It is added the vendors number and the type of account. The type is informed by the ARIBA team.

Then by clicking in execute the system will automatically performed the update:
![]()
Then , it is needed to add the vendor to the Google File (in the correct tab) and in PF1_050 the Search Term of the vendor needs to be added the code "ARIBA".
NOTE 1: The platform does not allow to activate more than 20 vendors at the same time through the standard system. It needs to be used the VIRTUS.
NOTE 2: Also, all the communication must be performed by email (to keep the history for people who don't have access to Freshdesk).
NOTE 3: When created an OA linked to an ARIBA vendor, the OA must be also activated as ARIBA.
To remove the vendor for the ARIBA enrolment the action is first done by the Purchasing team (group PTP Internal Controls), then Materials team and only later by the Vendors team.
It is used the transaction XK02 (PF1_020, WP1_400 or in both) and it is removed the Confirmation Control code:

Then, it is used the same transaction in the PF1_050 to remove the ARIBA mark in the field Search Term 2:

When marking for deletion an ARIBA vendor, it is not needed to inform ARIBA team, unless a new vendor has been created to replace the old one. There is no need to unmark the old vendor.
Every day, a job will run transaction ZMM_ARIBA_NEW_SUPP in PF1_020 & WP1_400 selecting a variant created with the criteria provided by the ARIBA TEAM.
| Variant ARIBA | ||
| Vendor |
| P000000000 - PZZZZZZZZZ |
| Domain Code |
| 8 |
| Segment Code |
| P204 P005 P010 P045 P049 P052 P053 P054 P067 P073 P076 P077 P098 P099 P104 P252 P253 P254 P255 PLO1 P208 |
| Class |
| A Blank |
| Country |
| NL GB FI US ES CA FR BE DE |
| Account Group |
| KRED PERS Z012 Z013 ZZCP ZZPE ZXAG ZZCD Z3UA Z7RA Z9TA ZAAD ZCAD ZDAD ZEAD ZFAD ZIAD ZNAD ZPAD ZQAD ZUAD ZA15 ZD15 |
| Created on |
| current date - 1 day |

The steeps done by this job are described here.
In the end, an email will be sent to ptp-data.analysis@support.solvay.com with the execution report in order to confirm if all steps have been made without any block.
Finally, the Google sheet created to monetized the ARIBA enrollment should be filled in - Tab Standard ACC.
The following columns must be filled in:
Column A | Country of the supplier | |
| Column B | Name of the supplier | |
| Column C | PRS / PF1 vendor code | If available in PF1 |
| Column D | WP1 Vendor code | If available in WP1 |
| Column I | IMPORTANT REMARK | Origin of the activation - ex. ZMM_ARIBA_NEW_SUPPLIERS |
Column J | Confirmation Key VENDOR DD/MM/YYYY | Ex. (it can be one our two systems) PF1 - Populated on 30.10.2020 WP1 - Populated on 30.10.2020 |
| Column K | Contracts and PIRs check DD/MM/YYYY | Same as Column J |
| Column L | Contracts and PIRs Comments | Same as Column J |
| Column M | Contracts + PIR CCK Info present | Same as Column J |
| Column N | Output message - Go-live date | Same as Column J |
| Column R | Current status PF1 | Ex. Active on 03.12.2020 or NA |
| Column S | Current status WP1 | Ex. Active on 03.12.2020 or NA |
Note:
1. In case the vendor was not created in the last working day the vendors code must be searched in the Google file:
2. In case it was created in the last working day the vendors code must be added to the Google file.
3. When linked to a different system the operator needs:
Every day, a job will run transaction ZMM_ARIBA_EXTND_PORG in PF1_020 & WP1_400.
Variant ARIBA | ||
Vendor | left blank | |
Created on |
| current date - 1 day |
Confirmation Control |
| Z017 |

The steeps done by this job are described here.
In the end, an email will be sent to ptp-data.analysis@support.solvay.com with the execution report in order to confirm if all steps have been made without any block.
NOTE: The operator must check if the vendor is being enrolled for a Purchasing Organization for the same system:
On the column I please add the origin of the activation, in this case ZMM_ARIBA_EXTND_PORG.
ARIBA Support Team (Ariba.Enrolment@solvay.com) will contact Data OPs. Vendors Team sending and email to the inbox (ptp-data.analysis@support.solvay.com) which will created a FreshDesk Ticket.
All interactions should be done replying to the email and not using the internal notes.
If any action needed from other team (Materials, Provisioning...), the ticket should be transferred to the respective FreshDesk Group.
ARIBA Support Team should send a suppliers' list to check if there are any OAs linked to the provided suppliers in both systems (PF1 & WP1)
The following queries should be executed in both systems:
SQ00
Go to Environment and than Query Areas:

Select:

Go to:

And double click on Group ZW_PU:
![]()
Then two queries should be executed
in both systems:
1st ZMM-036C Emails of OAs @ Vendor Master Data
2nd ZMM-036B Emails of OAs @ Purchasing Docs

| PRS | SE16N - Variant ARIBA OAs | |
| ||
| PF1 | ZMM-036C | ZMM-036B |
|---|---|---|
| 1. | 2. |
| 1. | |
| 1. | |
|
| |
| WP1 | ZMM-036C | ZMM-036B |
| 1. | 2. |
| 1. | |
| 1. | |
|
| |

Send the file to ARIBA support Team and close the request.
Each time that is detected that a supplier with ERS is also enrolled on ARIBA (or the other way opposite), the ARIBA Support Team should be contacted also using the email address Ariba.Enrolment@solvay.com via Freshdesk.
After analysis, we Data Ops. Vendors Team will be informed about which are the next steps to be performed.
Whenever Data Ops. Team is aware that an ARIBA supplier have changed their VAT number, please follow the steps below:
Whenever Data Ops. receives a request to update the email address of an Ariba supplier, the following steps should be followed:
1. Data team adds a note in the ticket (if the request is done via VWF, a ticket should be created) with vendor code (VN or OA code) and notifies Daiana Boruzs to check if the supplier has the account set up
2. a) If the account is set up, Daiana passes the ticket to Ariba Support Group and asks them to inform the user/supplier that the modifications need to be made by the supplier in their Ariba account
b) If the account is not set up, Daiana informs Data team to update the email address of the supplier. The next PO will be sent via Ariba to the new email address and the supplier is responsible for setting up their account
These steps can be found in our internal Ariba FAQs.