1 PURPOSE


This work instruction describes the process for maintaining (creation, changes) in SAP for the following material types including samples:


Process Flow

Finished Goods/Intermediates creation (Material Type: ZPRO)

Finished Goods/Intermediates change (Material type: ZPRO)

Factory Goods creation (Procured Materials) (Material type: ZROH, ZHBE, ZUNW, ZLAG, ZHRS)

Factory Goods change (Procured Materials) (Material type: ZROH, ZHBE, ZUNW, ZLAG, ZHRS)

2 PROCESS DESCRIPTION


Requestor (can be from various functions, for example R&D, planning, etc.) initiates business request and submits it to the Plant Data Steward depending on:


Process step by step:

  1. Plant Data Steward and/or product steward submits a request to PSRA for MSDS (if required), HTS and ECCN codes.
  2. Plant Data Steward submits a request to Data Management (providing a filled out Request Form) to set up a global view (at this time the material is also temporarily blocked until all local views have been created). We make sure that there are no duplicates already existing in the system, and if all required data has been provided, set up the Global view as requested. Then the DM ticket is closed and the Plant Data Steward receives a notification that the Global view is completed.
  3. Plant Data Steward gathers all information required for the local views (using the Collection form).
  4. Plant Data Steward populates all the collected data for the local views.
  5. Plant Data Steward advises Manufacturing, QM, Procurement and Logistics that a new item has been created so they can set up additional data (BOMs, routings, inspection plans, QIR's, Source List, etc.)
  6. Once all additional data is created, the Plant Data Steward advises Finance that a new item was created.
  7. Finance runs Costing.
  8. Plant Data Steward then releases the block.


Data Governance is responsible for material maintenance process and its changes.

3 PROCESS DESCRIPTION FOR DMO


3.1 New Material Code (no code presently in SAP)

3.1.1 Preliminary checks and request validation



3.1.2 Check for potential duplicates


Please refer to chapter 7.1
Validate/report/search

3.1.3 Create material - MM01



PLEASE NOTE! DM should only populate GLOBAL views – BASIC DATA 1, 2 and Classification
In case there is a need to populate PLANT views, please refer to the PLANT view instruction below.




Basic Data View:


Basic Data text view is located in Additional Data:


Please Note!
For all sold materials AUoM PER is mandatory
1 PER = 1 BUoM
If the Sales Indicator in Classification view is marked as SOLD, please enter AUoM – PER
To Exit 'Units Of Measure tab' press „Main Data"


Batch class is mandatory for ZROH materials (except packaging) and ZPRO materials (including packaging).
1 millimeter = 1000 micrometers

4 MASS UPDATE 


5 DEACTIVATE/ACTIVATE



For global deactivation change the following values of the Material:

For local deactivation change the following values of the Material:


Deactivation in MM06:


P.S. It is possible to deactivate/activate materials for specific Plant/ Stor.location/ Sales org./ Distr. Channel/ Warehouse Nr, that is usually performed by the Plant Data Steward

6 LIST OF MULTIPLE STORAGE LOCATIONS - MMSC



7 CREATING PLANT VIEWS / EXTENDING TO ANOTHER PLANT


The process of creating plant views and extending to another plant are very similar – both are performed using MM01 and the user has to select the Plant Views + Organizational levels!



Following chapters will cover each plant view separately and provide defaulted values as a reference.

7.1 Sales View


Please use defaulted tax codes:

BR

Brazil

IBRX

0

FR

France

MWST

1

FR

France

LCFR

A

GB

United Kingdom

MWST

1

IT

Italy

MWST

1

IT

Italy

LCIT

0

MX

Mexico

MWST

0

TW

Taiwan

MWST

0

US

USA

UTXJ

1

DE

Germany

MWST

1



choose from the list (see template):

Business Line

Region





NA

LA

AP

EU

Structural Materials

1201

3201

5201

7201

Process Materials

1202

3202

5202

7202


7.2 Purchasing View



7.3 Purchase Order Text view


7.4 MRP views





7.5 Work Scheduling view (not visible for ZROH)


Production Supervisor – choose from table ONLY if the Procurement Type = E:

Plant

Prod Superv.

Prod Scheduler


Plant

Prod Superv.

Prod Scheduler

2010

103

MTS- TC1


2040

104

MTS- TC2

2010

104

MTS- TC2


2040

YB2

MTS PI valuated

2010

YB2

MTS PI valuated


2045

104

MTS- TC2

2015

101

MTS-ITAR


2045

YB2

MTS PI valuated

2015

103

MTS- TC1


2050

104

MTS- TC2

2015

104

MTS- TC2


2050

YB2

MTS PI valuated

2015

106

MTO-ITAR


2055

YB2

MTS PI valuated

2015

108

MTO-TC1


2065

YB2

MTS PI valuated

2015

109

MTO-TC2


2070

YB2

MTS PI valuated

2015

YB2

MTS PI valuated


2075

YB2

MTS PI valuated

2020

102

MTS-EUML


2085

YB2

MTS PI valuated

2020

103

MTS- TC1


2090

YB2

MTS PI valuated

2020

104

MTS- TC2


2095

102

MTS-EUML

2020

YB2

MTS PI valuated


2095

103

MTS- TC1

2025

104

MTS- TC2


2095

104

MTS- TC2

2025

YB2

MTS PI valuated


2095

105

MTS-TAA

2030

YB2

MTS PI valuated


2095

YB2

MTS PI valuated

2035

104

MTS- TC2


2100

104

MTS- TC2

2035

109

MTO-TC2


2100

YB2

MTS PI valuated

2035

YB2

MTS PI valuated






Production Scheduling Profile – choose from table below, ONLY if the Procurement Type = E or Procurement Type = X:

Plant

Prod Profile

Description


Plant

Prod Profile

Description

2010

YB0002

MTS Process Manufacturing


2045

YB0002

MTS Process Manufacturing

2010

ZSTC1

MTS- TC1


2045

ZSTC2

MTS- TC2

2010

ZSTC2

MTS- TC2


2050

YB0002

MTS Process Manufacturing

2015

YB0002

MTS Process Manufacturing


2050

ZSTC2

MTS- TC2

2015

ZOITAR

MTO-ITAR


2055

YB0002

MTS Process Manufacturing

2015

ZOTC1

MTO-TC1


2065

YB0002

MTS Process Manufacturing

2015

ZOTC2

MTO-TC2


2070

YB0002

MTS Process Manufacturing

2015

ZSITAR

MTS-ITAR


2075

YB0002

MTS Process Manufacturing

2015

ZSTC1

MTS- TC1


2085

YB0002

MTS Process Manufacturing

2015

ZSTC2

MTS- TC2


2090

YB0002

MTS Process Manufacturing

2020

YB0002

MTS Process Manufacturing


2095

YB0002

MTS Process Manufacturing

2020

ZSEUML

MTS-EUML


2095

ZSEUML

MTS-EUML

2020

ZSTC1

MTS- TC1


2095

ZSTAA

MTS-TAA

2020

ZSTC2

MTS- TC2


2095

ZSTC1

MTS- TC1

2025

YB0002

MTS Process Manufacturing


2095

ZSTC2

MTS- TC2

2025

ZSTC2

MTS- TC2


2100

YB0002

MTS Process Manufacturing

2030

YB0002

MTS Process Manufacturing


2100

ZSTC2

MTS- TC2

2035

YB0002

MTS Process Manufacturing


4055

YB0002

MTS Process Manufacturing

2035

ZOTC2

MTO-TC2


2035

ZOTC2

MTO-TC2

2035

ZSTC2

MTS- TC2


2035

ZSTC2

MTS- TC2

2040

YB0002

MTS Process Manufacturing


2100

ZSTC2

MTS- TC2

2040

ZSTC2

MTS- TC2


2045

ZSTC2

MTS- TC2


7.6 Plant Data View




7.7 Warehouse mgmt. views



Please note Storage Strategies section is visible only if Warehouse Number is filled in selection screen of Organizational Levels.

7.8 Quality management view




Inspection Type

Description

Criteria for Selection

01

If the Material will have a Goods Receipt

If the ZPRO Material can be sub-contracted

03

If the Material just got Manufactured and needs to be inspected

If ZPRO Material

04

If the Materials is currently getting Manufactured and needs to be inspected

IF ZPRO Material

09

If it will be in stock over a period of time and may need re-inspection

If ZPRO Material


For Inspection types 01, 04 & 09 average inspection duration needs to be entered by the user. The other settings are Default and will be populated automatically.
Maintain 01 and 09 for Raw materials.

Inspection Type

Description

Criteria for Selection

01

If the Material will have a Goods Receipt

For all ZROH Materials

09

If it will be in stock over a period of time and may need re-inspection

If ZROH Material


For Inspection types 01 & 09 average inspection duration needs to be entered by the user. The other settings are Default and will be populated automatically.
ZHBE/ZLEH – for Structural Materials Quality Management Data view should not be created

7.9 Accounting views


PLEASE NOTE FOR ZROH: Please change Price Determination to 2 for all materials except Re-sale Items. If saved by mistake, please notify the FI team to change via CKMM. Once entered, this will be un-editable via material master.

PLEASE NOTE FOR ZROH: Please change Price Control Indicator to V for all materials except Re-sale Items. If saved by mistake, please notify the FI team to change via CKMM. Once entered, this will be un-editable via material master.


*re-sale ZROH – value RESALE MATERIAL - Purchased Finished Good in Material Planning Subtype field in Classification

7.10 Costing Views



Materials can be created using reference material (already existing one). The system will copy all the information from the old to the new one except:


9 VALIDATE /REPORT/SEARCH

9.1 MM03 – view material master






In order to Search material by any value in the Classification view, please use "Materials for Class" search option.
First of all the user has to know which Classification class contains the necessary value, e.g., "Old Material number" is in Engineering Class – ZCYMC_ENGR_MAT


9.2 MM04 – Material based changes


 


9.3 ZCYMAT_QUERIES – view based report





List of program names:

ZDM_MAT_QUER10Texts


Exporting the report


9.4 MM60 – field report



9.5 ZCYMAT_CD – display changes



Appendix 1 – List of Plant Data Stewards for both Structural and Process Materials


Appendix 2 – Material Request form


Appendix 3 – Material Types



Appendix 4 – Material number ranges



Appendix 5 – Material type definition


Appendix 6 – Required Documentation for Material Maintenance Requests Based on the Type of Change