Tasks to be completed when documenting an operation (from creation to publication)1. Enter the Title of the operation / page2. Add the following Labels :
3. Fill in all fields as described above4. Name the title of each section using OPD methodology naming convention - Infinitive verb without the “to”, mainly action verb...something) - " I do something..."5. Once the description of the operation is completed, ensure it is approved and published by launching the SBS-Finance approval workflow |
| Domain: Investments & Divestment |
Responsibility area: Control SBS IS Projects |
Reflect the SBS IS Function Controllers decisions on the status of the projects to the WBS Elements.
The capitalization process must be triggered for all SBS IS projects WW and in all ERP systems.
Definitions should be added in the Finance Glossary - Add definition and link it to respective Letter in Finance Glossary
See Finance Glossary:
WHAT and HOW - Main content of the operation
The content should be mainly organized in 2 levels of Headings to ensure a proper link with the Table of Contents.
Select the level of heading in the "Paragraph" option.

Example, if the year is 2020, select the SBS Budget Plan 2020.
![]()
Click on the image next to the file name for download.

For example Q2 2019:

Note If the status of the FXA08 Qx YYYY decision on the project is:
IN PROGRESS - Keep the WBS status released
NOT YET APPROVED - Keep the WBS status released
IN PROGRESS / CAPITALIZATION CAN BE DONE
Investment WBS Elements → proceed to capitalization but don't close the WBS
Overhead WBS Elements → keep the WBS status released
RE-OPEN - Guarantee that both WBS Elements and networks are with status released
IN PROGRESS / CAPEX TO CLOSE (keep OTC)
Capitalize and close investment WBS (verify if there are pending PO's or invoices)
Keep overhead WBS released
FROZEN - NO STATUS - lock all networks for allocation
CLOSED
Investment WBS Elements - Capitalize and close the WBS.
If it is not possible to close the WBS because there are still open commitments:
- Close the related networks to don't allow allocation
- Alert the SBS IS Function controllers by sending an email with the detail of project, WBS Elements and PO. (You may obtain the detail of commitments by transaction cji5)
Overhead WBS Elements - Close all WBS. If there are open commitments, close the related networks to don't allow allocation and alert the SBS IS Function controllers by sending an email with the detail of project, WBS Elements and PO. (You may obtain the detail of commitments by transaction cji5)
CANCELLED - Close all WBS if existing. Transfer all Investment WBS Elements costs to OTC or Cost center and close the WBS Elements.
For EMEA SAP PF1 WBS Projects, the capitalization is performed by the local contacts for Assets Accounting.
After identifying the WBS Elements in 3.3. point, it is needed to forward the capitalization requests to the local contacts by mail, making sure to indicate if it is only to capitalize the project and keep it with release status or to capitalize and close the project.
Upload the forms here, taking into account the year and the quarter.
After the SBS IS Controllers perform the revision of the forms, they indicate if there is needed some correction on Management Accounting team side.
For example:
(a) The transfer of costs to a cost center or to another WBS Element must be performed by using the WW - Global Posting File and opening a ticket using Freshdesk tool.
Once the capitalization forms have been reviewed by the SBS IS Controllers, it is needed to request the capitalization to SUMAC team by opening a ticket using Freshdesk tool (the ticket must be created by company code):

Dear all,
Can you please proceed to the capitalization, or closing of the projects attached?
Please take in consideration the tab ASSET ON COMPLETION FORM, if it is indicated that the closure type is total or partial. Meaning:
Thank you in advance!
Best regards,