By default only OPEX are displayed in the dashboard but it is possible to display all costs including CAPEX ( Capital Expenditure) & Capital Leases
![]()
All costs posted in a WBS element or a PM order (*) with the type IM - CAPEX (Invest.)
(*) The value IM is determined in BW and assigned to the Order, if the cost in the Order is fully or partially settled to a WBS element type IM - CAPEX (Invest.).
This table is used to upload the inflation rate that is used in the dashboard Co$ta: view Financial Evolution (€)

1. Download the file here and update it with the inflation rate by country :
| YEAR | Country code | Inflation (%) labour | Inflation (%) Other |
|---|---|---|---|
Enter a year ex: 2020 | Enter the country code or WW (WW is used by default when the country code doesn't exist) ex: FR | Enter the inflation rate ex: 2,5 | Enter the inflation rate ex: 2,5 |
| ... | ... | ... | ... |
2. Once the file is ready, follow the procedure here to upload it in BW.
This table is used to filter costs that are part of the scope ZBB (F2G - Fuel for Growth) in the dashboard Co$ta

1. Download the file here and update it with the list of subpackages in or out of the ZBB scope :
| Cost Sub-Package | ZBB |
|---|---|
Enter the subpackage code ex: P20001 | Enter Yes or No ex: No |
| ... | ... |
2. Once the file is ready, follow the procedure here to upload it in BW.
This table is used to determine the responsible cost center when the origin flow is FI or COPA.
1. Download the file here and update it with the list of combinations to be used for the determination of responsible cost centers (you can leave some fields blank):
| GBU | Cost macro-package | Cost package | BFC Activity 1 | Company code | Plant | Controlling area | Responsible cost center |
|---|---|---|---|---|---|---|---|
Enter the BFC GBU code ex: PE | Enter a macro-package ex: P00003 | Enter a package ex: P10012 | Enter an Activity 1 ex: CSNR | Enter a company code ex: 0237 | Enter a plant ex: CJEI | Enter the controlling area corresponding to the company code ex: CHEF | Enter the responsible cost center ex: X481200000 |
| ... | ... |
2. Once the file is ready, follow the procedure here to upload it in BW.
This table is a setting table to maintain the mapping of General reason for investment for WBS.
→ Update the table in BW
1. Download the file here and update the mapping between Reason for investment and General reason for investment :
| Source System | Reason for investment | General reason for investment | F2G - CAPEX in F2G budgeting scope |
|---|---|---|---|
Enter a Source System ex: WP1_400 | Enter a Reason for investment ex: 2W | Enter a General reason for investment ex: HSE | Enter a CAPEX in F2G budgeting scope ex: |
2. Once the file is ready, follow the procedure here to upload it in BW.